 
          3237
        
        
          Technical Committee 307 /
        
        
          
            Comité technique 307
          
        
        
          Following backfilling of the craters, earthworks were
        
        
          undertaken to reshape the surface of the various benches after
        
        
          which conventional fill placement was carried out to achieve
        
        
          design levels.  In areas, this required the placement of up to 2 m
        
        
          of compacted fill which was placed under Level 1 geotechnical
        
        
          control to the requirements of Australian Standard AS3798 –
        
        
          1996.  As a result of the success of the dynamic compaction
        
        
          phase (which provided a solid base), the undertaking of
        
        
          additional earthworks was relatively straightforward with a
        
        
          compaction requirement of 100% of standard maximum dry
        
        
          density achieved in all fill areas.  Fill materials included the use
        
        
          of coal washery rejects, a mining by-product from the coal
        
        
          washing process that is obtained at low cost (typical transport
        
        
          only) but has very good civil engineering properties for use as
        
        
          general fill and no negative environmental impacts.
        
        
          5.3
        
        
          
            Site Monitoring
          
        
        
          Construction works for the ground consolidation contract were
        
        
          undertaken in accordance with a Construction Environment
        
        
          Management Plan (CEMP).  The key objective of the CEMP
        
        
          was to develop a monitory programme for regulatory
        
        
          compliance and early detection of any significant environmental
        
        
          or community impacts.
        
        
          Given the potential impacts due to dynamic compaction
        
        
          being carried out on the site and the presence of buildings on
        
        
          neighbouring properties, vibration trials were undertaken prior
        
        
          to commencement of compaction.  An attenuation graph was
        
        
          prepared as shown in Figure 4 with a boundary buffer distance
        
        
          of 25 m nominated for a proposed vibration limit of 8 mm/sec
        
        
          (sector sum and component peak particle velocity).  Texcel
        
        
          Vibration Monitors were installed for continuous data recording
        
        
          (one of which was in a neighbouring building) and adopting the
        
        
          buffer distances established by the trial, only nine exceedances
        
        
          were recorded during the 6 month construction period.  No
        
        
          complaints were received from neighbouring properties.
        
        
          Figure 4: Dynamic Compaction Vibration Attenuation Graph
        
        
          Whilst noise was considered to be the other major
        
        
          environmental impact that could cause community concern
        
        
          during compaction activities, monitoring over the 6 month
        
        
          period recorded a total of only 32 readings above the
        
        
          performance criteria of 75 dBA.  Odour was primarily of
        
        
          concern during the initial excavation phase and was managed by
        
        
          minimising waste exposure time.  Similarly, dust was managed
        
        
          by the implementation of good construction practices on site.
        
        
          Leachate and groundwater was monitored regularly with all
        
        
          outflow to the pre-determined requirements.  Whilst results
        
        
          were typical of those expected from a landfill site, manganese
        
        
          and ammonia were flagged as elements of concern.
        
        
          The obvious area of concern in all landfill projects is landfill
        
        
          gas (LFG).  Methane, carbon dioxide and oxygen levels were
        
        
          monitored both inside and outside the landfill boundary as well
        
        
          as within site buildings.  Daily monitory of landfill was
        
        
          undertaken using a GA2000 Gas Meter.  Both surface and well
        
        
          measurements were taken as well as barometric pressure and
        
        
          lower explosive limit.  Peak methane levels of up to 97% were
        
        
          recorded in wells in the landfill footprint, with levels generally
        
        
          in the range of 14 – 50%.  Monitoring in wells adjacent to the
        
        
          landfill boundary was generally below threshold levels or 0%
        
        
          methane.  Surface and enclosed space monitoring showed that
        
        
          LFG was not considered to be an issue at any time during the
        
        
          works.]
        
        
          6 FUTURE WORKS AND BUILDING DESIGN
        
        
          6.1
        
        
          
            Civil works, services and stormwater drainage
          
        
        
          All civil and building services (eg sewer, water, stormwater,
        
        
          electrical, gas) have been designed such that they will not need
        
        
          to penetrate the capping layer of the landfill.  All service
        
        
          trenches and other works that require excavation (eg
        
        
          landscaping) will be within ‘clean’ material and limited to
        
        
          excavation depths of 2m.  Earthworks associated with site
        
        
          reshaping will require construction of retaining walls up to 7m
        
        
          high. The walls have been designed as reinforced earth
        
        
          structures able to accommodate ground settlements of 300mm.
        
        
          6.2
        
        
          
            Foundations
          
        
        
          The main advantage of dynamically compacting the landfill is
        
        
          that long term settlement of the landfill (post building
        
        
          construction) will be significantly reduced, but not eliminated
        
        
          (Thom 1998).  As such, footing design for buildings located
        
        
          within the landfill footprint will be for driven steel piles
        
        
          founding in the underlying latite bedrock.  Flexible aprons will
        
        
          be needed between the buildings (which will experience
        
        
          negligible settlement) and adjoining carparks, walkways and
        
        
          recreation areas (which will experience ongoing settlement).
        
        
          Whilst raft slabs may be feasible for some lightweight single
        
        
          story buildings, preliminary analysis has indicated that a 1 m
        
        
          thick reinforced earth raft will be needed to provide uniform
        
        
          bearing and to equalise the longer term settlements so that
        
        
          differential movements will be within acceptable limits.
        
        
          
            Dynamic Compaction Vibration Attenuation Graph:  Nan Tien CampusSite
          
        
        
          y = 333.39x
        
        
          -1.1794
        
        
          0.1
        
        
          1.0
        
        
          10.0
        
        
          100.0
        
        
          0.1
        
        
          1.0
        
        
          10.0
        
        
          100.0
        
        
          Source-ReceiverDistance (m)
        
        
          Peak ParticleVelocity (mm/s)
        
        
          Allowed Limit
        
        
          BufferDistance
        
        
          TrialData:  PPVi
        
        
          6.3
        
        
          
            Leachate Control and Gas Drainage
          
        
        
          Leachate collection drains will be installed across the site and
        
        
          directed to the leachate treatment system.  The current options
        
        
          for leachate collection include disposal to sewer, reinjection,
        
        
          spray or drip irrigation, removal by contractor, ammonia
        
        
          stripping, constructed wet lands and membrane bio reactor.
        
        
          The primary elements of the environmental design are
        
        
          capping profile, methane drainage and leachate control.  The
        
        
          requirement of the site capping is twofold; firstly – physical
        
        
          separation by covering contaminated materials and secondly –
        
        
          prevention of infiltration to the substrate, thereby minimising
        
        
          leachate recharge and mobilisation and upward migration of
        
        
          methane.  Historically landfill capping systems have included a
        
        
          0.5 m clay cap however this system alone was not considered
        
        
          intrinsically safe at this site in areas underneath buildings or
        
        
          pavements where piles will breach the cap and gas can
        
        
          accumulate in enclosed spaces.
        
        
          The preliminary design for the capping consists of HDPE,
        
        
          GCL, geotextile fabric, 300 mm gravel gas drainage layer and a
        
        
          reinforcing geotextile, underlain by the existing waste, refer to
        
        
          Figure 5 below.  Undercrofts will be constructed where possible
        
        
          to allow for suspension of services and cross-ventilation.  In
        
        
          areas outside of the buildings an additional 1 m layer of clean
        
        
          fill material to further protect the cap from stormwater and root
        
        
          infiltration, drying out, cracking and accidental breaches will be
        
        
          installed.  The preliminary design requires the landfill cap to