 
          2977
        
        
          
            Proceedings of the 18
          
        
        
          
            th
          
        
        
          
            International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
          
        
        
          1
        
        
          Instrumented Trial Embankment on Soft Ground at Tokai, State of Kedah, Malaysia
        
        
          Embankment essai instrumenté sur un sol mou à Tokai, État de Kedah, en Malaisie
        
        
          TAN Yean-Chin, LEE Peir-Tien & KOO Kuan-Seng
        
        
          
            G&P Geotechnics Sdn Bhd, Malaysia.
          
        
        
          ABSTRACT: The geometrical tolerance of railway tracks at high operating speed is generally very stringent.  Hence, when long
        
        
          stretches of the railway embankment traversing through soft alluvium deposits, cost effective designs meeting the design performance
        
        
          and construction schedule are required.  A cost effective treatment such as prefabricated vertical drain (PVD) with temporary
        
        
          surcharging was designed to meet the stringent performance requirements. In addition, basal reinforcement was adopted to allow
        
        
          higher embankments to be built without compromising on the embankment stability during construction and to meet the tight
        
        
          construction schedule. Therefore, a fully instrumented trial embankment was carried out at Tokai, State of Kedah, Malaysia to verify
        
        
          the design philosophy of the ground treatment method adopted. This paper presents the consolidation settlement behavior and excess
        
        
          pore water pressure responses of the trial embankment during construction and surcharge waiting period. Back analyses using Finite
        
        
          Element Modeling (FEM) was performed to evaluate the performance of the ground treatment and to verify the subsoil parameters
        
        
          used in the design.
        
        
          RÉSUMÉ :
        
        
          La tolérance géométrique des voies ferrées à grande vitesse de fonctionnement élevée est généralement très strictes. Ainsi,
        
        
          lorsque de longues étendues de la voie ferrée traversant remblai par des dépôts d'alluvions souples, efficaces coûtent conceptions
        
        
          répondant à la performance de la conception et du calendrier de construction sont nécessaires. Un traitement rentable telles que
        
        
          vidange verticaux préfabriqués (PVD) avec surcharge temporaire a été conçu pour répondre aux exigences de performance
        
        
          rigoureuses. En outre, le renforcement de base a été adopté pour permettre aux plus digues pour se construire sans compromettre la
        
        
          stabilité de remblai lors de la construction afin de respecter le calendrier de construction serré. Par conséquent, un remblai d'essai
        
        
          entièrement instrumenté a été effectuée à Tokai, État de Kedah, en Malaisie afin de vérifier la philosophie de conception de la
        
        
          méthode de traitement des sols adopté. Cet article présente le comportement tassement de consolidation et de l'excès de pression d'eau
        
        
          interstitielle des réponses du remblai d'essai pendant la construction et la période d'attente. Retour à l'aide des analyses de
        
        
          modélisation par éléments finis (FEM) a été réalisée afin d'évaluer la performance du traitement des sols et de vérifier les paramètres
        
        
          du sous-sol utilisés dans la conception
        
        
          KEYWORDS: Instrumented trial embankment, soft ground, consolidation settlement .
        
        
          1 INTRODUCTION
        
        
          The construction of the electrified double track project in
        
        
          northern part of Peninsular Malaysia commenced in year 2007.
        
        
          As most of the embankments are founded on soft alluvium
        
        
          deposit, cost effective ground treatment such as PVD with
        
        
          temporary surcharging was widely adopted to meet the stringent
        
        
          settlement requirements and tight construction schedule. In view
        
        
          of this, a fully instrumented trial embankment was constructed
        
        
          at Tokai, State of Kedah as shown in Figure 1 to verify the
        
        
          design philosophy of the ground treatment method adopted.
        
        
          This is to study the consolidation settlement behavior, excess
        
        
          pore water pressure response and lateral displacement at the toe
        
        
          of embankment as indicator of consolidation process and
        
        
          embankment stability during construction filling and rest
        
        
          period.
        
        
          This paper presents the settlement behaviour and excess
        
        
          pore water pressure response of the trial embankment. Back
        
        
          analyses using Finite Element Modelling (FEM) was also
        
        
          performed to evaluate the performance of the ground treatment
        
        
          and to verify the subsoil parameters adopted in the design.
        
        
          2 SUBSOIL CONDITION
        
        
          The subsoil is relatively homogenous consisting of very soft to
        
        
          soft CLAY (15m thick) overlying dense silty sand to sand from
        
        
          depth of 15m to 24m. Hard layer with SPT
        
        
          ‘
        
        
          N
        
        
          ’
        
        
          value of more
        
        
          than 50 was found below 24m. The general subsoil properties
        
        
          including bulk density, compression ratio (CR), re-compression
        
        
          ratio (RR), over consolidation ratio (OCR), pre-consolidation
        
        
          pressure (Pc), undrained shear strength (s
        
        
          u
        
        
          ) and Atterberg limit
        
        
          are plotted in Figure 2. The interpreted subsoil parameters based
        
        
          on the field and laboratory tests are summarized in Table 1.
        
        
          3 GROUND TREATMENT AND INSTRUMENTATION
        
        
          The general ground treatment details for trial embankment are
        
        
          summarised in Table 2. The instrumentation scheme includes
        
        
          settlement gauges, extensometers, inclinometers, ground
        
        
          displacement markers, vibrating wire piezometers, standpipe
        
        
          and surface settlement markers as shown in Figure 3. Settlement
        
        
          at centre of embankment was measured by settlement gauges
        
        
          SG2, SG5 and SG8. Whilst, settlements at edge of embankment
        
        
          were measured by settlement gauges SG1, SG3, SG4, SG6, SG7
        
        
          and SG9.  Settlements at various depths were measured by
        
        
          extensometers EXT1, EXT2 and EXT3. The multistage
        
        
          construction with higher height of up to 7.6m was carried out
        
        
          due to site condition and problems such as delay in view of wet
        
        
          monsoon season, no borrow source, etc. The original intent is to
        
        
          construct the trial embankment in single stage loading of up to
        
        
          5.9m
        
        
          4 BACK ANALYSIS BY FEM MODELLING
        
        
          Back analyses were carried out by using finite element
        
        
          modelling (FEM) software (Plaxis). Soft Soil Model (SSM) was
        
        
          Tan Y.-C., Lee P.-T., Koo K.-S.