 
          2974
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          0.00
        
        
          -10.00
        
        
          -20.00
        
        
          -40.00
        
        
          -30.00
        
        
          ELEVATION [m a.s.l.]
        
        
          SFs/ML
        
        
          CL/CH
        
        
          ML/SFs
        
        
          G
        
        
          CL/CH
        
        
          c=0 kPa
        
        
          
        
        
          =30°
        
        
          Cu=20-40kPa
        
        
          Cu=40-80kPa
        
        
          c=10 kPa
        
        
          
        
        
          =28°
        
        
          c=0kPa
        
        
          
        
        
          =40°
        
        
          SPT correlation
        
        
          Shear VaneTest
        
        
          CPT
        
        
          Consolidated UnrainedTest
        
        
          Direct ShearTest
        
        
          Consolidated UndrainedTest
        
        
          Direct ShearTest
        
        
          SPT correlation
        
        
          -50.00
        
        
          +10.00
        
        
          Figure 2 Geotechnical soil profile with performed in-situ exploratory
        
        
          works and laboratory tests.
        
        
          3 MEASURMENTS AND CONSTRUCTION PHASES
        
        
          Terminal construction was divided into four main phases:
        
        
          execution of vibrated stone columns and preloading in the
        
        
          storage area, execution of piles from the coast on previously
        
        
          prepared terrain, excavation and underwater embankments, and
        
        
          construction of the coastal structure.
        
        
          There are two zones of execution in stone columns: dense
        
        
          (triangular grid 2x2m) and sparse improvement (square grid
        
        
          2.8x2.8m). Dense soil improvement was carried out down to -
        
        
          8m a.s.l. Sparse improvement was performed down to -15m
        
        
          a.s.l. i.e. -20m a.s.l. in such a way that every other column of
        
        
          dense improvement is extended down to the required depth. The
        
        
          role of stone columns is to provide global stability, and
        
        
          settlement reduction and acceleration.
        
        
          Because of terminal construction dynamics, pre-loading of
        
        
          storage areas was, due to limitations of material for preloading,
        
        
          performed independent of phases, on the condition that they are
        
        
          executed before the execution of coastal structure. Preloading
        
        
          was executed in three segments (fields).
        
        
          STORAGE AREA
        
        
          STONE COLUMNS 2x2m
        
        
          STONE COLUMNS 2.8x2.8m
        
        
          -8 m a.s.l.
        
        
          -20 m a.s.l.
        
        
          -33 m a.s.l.
        
        
          -42 m a.s.l.
        
        
          -52 m a.s.l.
        
        
          Cu=20-40kPa
        
        
          Cu=40-80kPa
        
        
          c=10 kPa
        
        
          
        
        
          =28°
        
        
          c=0 kPa
        
        
          
        
        
          =40°
        
        
          SFs/ML
        
        
          CL/CH
        
        
          ML/SFs
        
        
          G
        
        
          CL/CH
        
        
          INCLINOMETER
        
        
          DEFORMETER
        
        
          COASTAL
        
        
          CONSTRUCTION
        
        
          TERRAIN
        
        
          c=0 kPa
        
        
          
        
        
          =30°
        
        
          +5,55
        
        
          +2,55
        
        
          -20,0
        
        
          -8,0
        
        
          -15,0
        
        
          PRELOADING
        
        
          Figure 3 Construction phase I: improvement of foundation soil with
        
        
          stone columns and pre-loading in the area of storage and traffic
        
        
          surfaces.
        
        
          Each construction phase was monitored through geotechnical
        
        
          and geodetic measurements. Geotechnical measurements in the
        
        
          area of storage and traffic surfaces consisted of measuring
        
        
          vertical displacements by horizontal inclinometers, and
        
        
          settlement measurements by layers using vertical deformeter
        
        
          (see Figure 3). A net of geodetic points was placed on the top of
        
        
          pre-load.
        
        
          Pre-loading was performed in three fields, in such a way that
        
        
          the material was transferred from one field to another.
        
        
          Settlement of the first field was measured by horizontal
        
        
          inclinometer and vertical deformeter, and with a net of geodetic
        
        
          points 12x12 m. Measurements showed the settlement of 70 cm
        
        
          in the period of 105 days, and they are shown on Figure 4. The
        
        
          difference in settlement between the inclinometer and
        
        
          deformeter is caused by the fact that the deformeter's reference
        
        
          point is at 44 m and underneath it there are compressible layers
        
        
          which could not be followed by the deformeter.
        
        
          23/8/08 22/9/08 22/10/08 21/11/08 21/12/08 20/1/09 19/2/09
        
        
          Date
        
        
          800
        
        
          700
        
        
          600
        
        
          500
        
        
          400
        
        
          300
        
        
          200
        
        
          100
        
        
          0
        
        
          Settlement (mm)
        
        
          LEGEND
        
        
          inclinometer
        
        
          deformeter
        
        
          back analysis
        
        
          Figure 4.Inclinometer and deformeter settlement measurements together
        
        
          with the settlement curve obtained by back analyses in the first field of
        
        
          preloading.
        
        
          The requirement for duration of preloading of 90 days was
        
        
          obtained by analysing the consolidation curve. For the other two
        
        
          fields, the same preloading duration requirement was set.
        
        
          Settlement measurements in the second and third field were
        
        
          performed on geodetic points. Measurements in the second field
        
        
          have shown settlement of 30 cm, and in the third of 50 cm. The
        
        
          reason for smaller measured settlement is longer time of placing
        
        
          pre-loading, and the fact that the reference measurements were
        
        
          performed only after preloading was completed.
        
        
          Cu=20-40kPa
        
        
          Cu=40-80kPa
        
        
          c=10 kPa
        
        
          
        
        
          =28°
        
        
          c=0 kPa
        
        
          
        
        
          =40°
        
        
          SFs/ML
        
        
          CL/CH
        
        
          ML/SFs
        
        
          G
        
        
          CL/CH
        
        
          STORAGE AREA
        
        
          STONE COLUMNS 2x2m
        
        
          STONE COLUMNS 2.8x2.8m
        
        
          COASTAL
        
        
          CONSTRUCTION
        
        
          +5,55
        
        
          +2,55
        
        
          -8,0
        
        
          PRELOADING
        
        
          -20,0
        
        
          -15,0
        
        
          D
        
        
          B A
        
        
          C
        
        
          c=0 kPa
        
        
          
        
        
          =30°
        
        
          -8 m a.s.l.
        
        
          -20 m a.s.l.
        
        
          -33 m a.s.l.
        
        
          -42 m a.s.l.
        
        
          -52 m a.s.l.
        
        
          Figure 5 Construction phase II: execution of piles from the coast on
        
        
          previously prepared terrain.
        
        
          Cu=20-40kPa
        
        
          Cu=40-80kPa
        
        
          c=10kPa
        
        
          
        
        
          =28°
        
        
          c=0kPa
        
        
          
        
        
          =40°
        
        
          SFs/ML
        
        
          CL/CH
        
        
          ML/SFs
        
        
          G
        
        
          CL/CH
        
        
          STORAGE AREA
        
        
          STONE COLUMNS 2x2m
        
        
          STONE COLUMNS 2.8x2.8m
        
        
          COASTAL
        
        
          CONSTRUCTION
        
        
          +2,55
        
        
          -8,0
        
        
          -20,0
        
        
          -15,0
        
        
          D
        
        
          B A
        
        
          C
        
        
          c=0kPa
        
        
          
        
        
          =30°
        
        
          -8 m a.s.l.
        
        
          -20 m a.s.l.
        
        
          -33 m a.s.l.
        
        
          -42 m a.s.l.
        
        
          -52 m a.s.l.
        
        
          Figure 6 Construction phase III: undersea excavation and execution of
        
        
          undersea embankment.
        
        
          Geotechnical measurements on the coastal structure consisted of
        
        
          measurements in vertical inclinometers-deformeters inside the
        
        
          pile. Measuring equipment was installed in one profile, so that
        
        
          one vertical inclinometer-deformeter was placed in tensile zones
        
        
          of each of piles A and C. In pile D, two vertical inclinometers-
        
        
          deformeters were placed –one in the compressive zone and the
        
        
          other in the tensile zone. The tops of inclinometers-deformeters
        
        
          were at the same time geodetic points, whose displacements
        
        
          were geodetically followed. Inclinometer measurements showed