 
          2971
        
        
          Technical Committee 214 /
        
        
          
            Comité technique 214
          
        
        
          each track area is up to 50 t/m². The foundation soil is 10 m
        
        
          thick soft bluish clay with an average undrained shear strength
        
        
          of 23 kPa from vane shear test results.
        
        
          Figure 6. Rehabilitated fabrication yard in use.
        
        
          In the calculations, the angle of load spread for the fill
        
        
          material reinforced with TriAx geogrid within the MSL is taken
        
        
          to be 1 vertical to 1 horizontal (i.e., 1V:1H) whereby the load
        
        
          distribution through the geocell mattress was taken as 1 vertical
        
        
          to 2 horizontal (i.e., 1V:2H) to model the very stiff nature of the
        
        
          construction (Figure 7).
        
        
          (a)
        
        
          (b)
        
        
          Figure 7. Geocell mattress and MSL platform (after Ong et al., 2011)
        
        
          Five layers of TriAx geogrids were used to form the 2 m
        
        
          thick MSL. Stiff uniaxial geogrids were used to form the
        
        
          interlocking cells of the 1 m thick geocell mattress and a layer
        
        
          of TriAx geogrid was placed at the base. The aggregate to be
        
        
          used as backfill material for the MSL and geocell mattress was
        
        
          specified as well graded granular material with particle size less
        
        
          than 75 mm. Full scale plate bearing test (PBT) was conducted
        
        
          to ascertain the performance of the geocell mattress in meeting
        
        
          the acceptance criterion (i.e., total settlement less than 100 mm
        
        
          under loading of 50 t/m²). The loading on the steel plate was
        
        
          increase in six steps: 10 t/m², 20 t/m², 30 t/m², 40 t/m², 50 t/m²
        
        
          and 60 t/m². Settlement versus applied load and settlement
        
        
          versus time were plotted. It was found that the specified
        
        
          settlement requirement was satisfied with total settlement of 41
        
        
          mm under 60 t/m² load.
        
        
          4 CONTAINER YARD IN GEBENG, KUANTAN
        
        
          In this project, a working platform in the form of container yard
        
        
          was built on soft subgrade with California bearing ratio (CBR)
        
        
          of 1% to 2%. The container yard was designed to support the
        
        
          following loadings:
        
        
          
        
        
          6 m by 2.4 m container with maximum weight of 30 tonnes.
        
        
          Maximum staking of containers was 2 containers.
        
        
          
        
        
          Container handler machine with maximum axle load of 105
        
        
          tonnes. Therefore maximum wheel load of 525 kN
        
        
          including dynamic factors.
        
        
          
        
        
          Total number passes of the container handler machine was
        
        
          designed as 250,000 during service life.
        
        
          The terms of reference are:
        
        
          
        
        
          To reduce thickness of unbound granular layer platform.
        
        
          
        
        
          To mitigate differential settlement.
        
        
          
        
        
          To provide stable storage area and to increase load spread
        
        
          using geocell mattress and mechanically stabilised layer
        
        
          (MSL) with TriAx geogrids.
        
        
          The analysis conducted indicated that the loadings from the
        
        
          trafficking movement due to container staker would be more
        
        
          critical than the static loadings due to the staking of 2
        
        
          containers. Thus, the requirement for total platform thickness
        
        
          was assessed based on heavy duty pavement design (Knapton,
        
        
          2008). By using geocell mattress and MSL, the thickness of
        
        
          granular fill required to construct the container yard has been
        
        
          reduced up to 810 mm. This resulted in substantial savings in
        
        
          terms of construction time and cost.
        
        
          MECHANICALLY
        
        
          STABILISED LAYER
        
        
          (MSL)
        
        
          GEOCELL MATTRESS
        
        
          2.0 m
        
        
          1.0 m
        
        
          SOFT CLAY
        
        
          EGL
        
        
          MAX. CRANE TRACK
        
        
          LOADING = 50 t/m
        
        
          For the heavy duty pavement construction of the container
        
        
          yard, 1 m high geocell mattress was placed on one layer of
        
        
          TriAx geogrid at subgrade level. The geocell mattress is to
        
        
          provide a firm and relatively rigid platform with a perfectly
        
        
          rough interface between the mattress and the soft foundation.
        
        
          This stiff platform is created by the high tensile strength of
        
        
          polymer grid material used in the cellular construction to
        
        
          confine the granular fill which enables an even distribution of
        
        
          load onto the foundation. On top of the geocell mattress is MSL
        
        
          of 500 mm to 750 mm compacted well graded granular fill with
        
        
          3 layers of TriAx geogrids. Granular layers reinforced with
        
        
          TriAx geogrids perform as composite due to the interlock
        
        
          phenomenon. The configuration of the geogrid ribs and the
        
        
          integral junctions provide lateral restraint to the aggregate
        
        
          particles as they partially penetrate the apertures by a process of
        
        
          interlock. This interlock effectively stiffens the aggregate and
        
        
          enables any imposed load to be distributed over a wider area.
        
        
          The container platform was finished with interlocking paving
        
        
          blocks. The construction of the container yard is expeditious
        
        
          starting from placement of TriAx geogrids, forming of geocells,
        
        
          filling with granular materials according to prescribed grading
        
        
          envelope, construction of MSL geogrid reinforced layers and
        
        
          installation of the paving blocks (Figures 8 to 12).
        
        
          GEOCELL MATTRESS
        
        
          2.0 m
        
        
          1.0 m
        
        
          SOFT CLAY (bearing capacity = 131 kPa)
        
        
          EGL
        
        
          MAX. CRANE TRACK
        
        
          LOADING = 50 t/m
        
        
          TRIAX GEOGRID
        
        
          TO FORM MSL
        
        
          1V:1H
        
        
          1V:2H
        
        
          5 DISCUSSION AND CONCLUSION
        
        
          Comparison is made in the pavement details and settlement
        
        
          performance of the working platform (Table 1). From Table 1 it
        
        
          can be seen that all the 3 platforms consist of soft clay layer of
        
        
          thickness varying from 4.5 m to 10 m. The crane track pressure
        
        
          exerted on the working platform was up to 500 kPa and axle
        
        
          load exerted by the reach stacker on the working platform is 105
        
        
          tonnes. Granular fill of varying thicknesses were used in all
        
        
          three working platforms. It appears that MSL constructed using
        
        
          biaxial and TriAx  geogrids with granular fill with or without
        
        
          geocell mattress performed satisfactorily in terms of platform
        
        
          settlement performances to support the heavily loaded crawler
        
        
          crane or stacker machine for the fabrication or container yard.