 
          2904
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          
            End Bearing Resistance
          
        
        
          
        
        
          Maximum mobilised resistance = 59MPa (ultimate end
        
        
          bearing pressure not reached)
        
        
          
        
        
          Little or no creep at an end bearing pressure of 38MPa
        
        
          (this pressure was held for 30 minutes)
        
        
          
            Shaft Resistance
          
        
        
          
        
        
          Creep started at an average shaft resistance (over 5.5m
        
        
          length) of 1.06MPa and was significant at 1.3MPa
        
        
          
        
        
          The shaft response became “plastic” at a movement of
        
        
          about 30mm, with a corresponding average shaft
        
        
          resistance of 1.74MPa
        
        
          The O-Cell test results confirmed the ultimate design values
        
        
          adopted for design, and as in Case Study 1, demonstrated that
        
        
          significantly higher serviceability end bearing pressure could be
        
        
          considered in the design of rock socketed piles in Sydney rock.
        
        
          If the presumptive end bearing pressure given in Table 2 for
        
        
          Class I and II Sandstone was adopted, the serviceability end
        
        
          bearing resistance would have been limited to 12MPa.  The O-
        
        
          Cell test clearly demonstrated that significantly higher
        
        
          serviceability end bearing could be adopted, provided the base
        
        
          of the rock socket is adequately cleaned.  The pile construction
        
        
          aspect of this case study to ensure adequate rock socket
        
        
          roughness and base cleanliness is described in Sethi et al
        
        
          (2012).  However, it should also be stressed that under
        
        
          serviceability loading, a large proportion of the applied load
        
        
          may be carried by the pile shaft depending on the length to
        
        
          diameter ratio of the rock socket.  Therefore, the use of
        
        
          excessively high serviceability end bearing pressure may not be
        
        
          warranted.  A detailed assessment of the rock-socket load-
        
        
          deformation response is necessary for each specific case.
        
        
          In the above case study, the non-linear load-deformation
        
        
          behavior observed from the O-Cell test is of particular interest.
        
        
          Using the back-analyzed test results, and by close inspection of
        
        
          the load-deformation behavior of both the shaft and base, it was
        
        
          possible to deduce the operating secant modulus of the rock
        
        
          socket material at various mobilized base and shaft resistance as
        
        
          shown in Figures 6 and 7.
        
        
          Figure 6. Deduced Secant Modulus of Rock below Pile Base
        
        
          Figure 7. Deduced Secant Modulus of Rock around Pile Shaft
        
        
          It can be seen from Figure 6 that there was a rapid drop in
        
        
          the inferred secant modulus of the rock below the pile base
        
        
          when a base pressure of 5MPa was reached, and remained at
        
        
          approximately 1.6GPa to 1.7GPa until a base pressure of
        
        
          14MPa was reached.  Above this pressure, the inferred secant
        
        
          modulus continued to drop steadily and reached a value of
        
        
          1.3GPa at a base pressure of 30MPa.  The initial drop in secant
        
        
          modulus at a base pressure of 5MPa to 14MPa could be
        
        
          attributed to compression of disturbed material or residual
        
        
          debris at the base of the socket, and the gradual drop of secant
        
        
          modulus beyond a base pressure of 14MPa is considered to be
        
        
          representative of the actual rock mass behavior.
        
        
          From Figure 7, it can be seen that the inferred secant
        
        
          modulus of the rock socket material was initially very high
        
        
          (over 5GPa), then dropped rapidly to 2.5GPa at an average shaft
        
        
          resistance of 0.4MPa, then continued to drop steadily to 1.2GPa
        
        
          at a mobilized shaft resistance of 1.2MPa.  Comparing these
        
        
          results with the non-linear function to describe the secant
        
        
          modulus adopted for design as shown in Table 3, it may be
        
        
          concluded that different initial rock modulus should be applied
        
        
          to describe the base and shaft response.  However, for simplicity
        
        
          of design, and considering the operating stresses at the
        
        
          serviceability loads for the piles on this project, it was
        
        
          concluded that an initial tangent modulus value of 2GPa would
        
        
          still be appropriate for the Class II Sandstone if the hyperbolic
        
        
          pile base and shaft factors, R
        
        
          fb
        
        
          and R
        
        
          fs
        
        
          (see Table 3), were
        
        
          modified to 0.55 and 0.8 respectively.  These values correspond
        
        
          to secant modulus values of approximately:
        
        
          
        
        
          Pile Base Response – 1.7GPa and 1.2GPa for the rock
        
        
          below the pile base, for end bearing pressures of
        
        
          14MPa and 30MPa respectively, and
        
        
          
        
        
          Pile Shaft Response – 1.8GPa and 1.2GPa for the rock
        
        
          around the pile shaft for shaft resistance of 0.4MPa
        
        
          and 1.2MPa respectively.
        
        
          However, these changes would only make very small changes
        
        
          (≤ 3mm) to settlement prediction values at serviceability
        
        
          loading.  Therefore, the original design parameters were
        
        
          adopted without changes for subsequent designs.
        
        
          Supported by the O-Cell pile load testing, significant
        
        
          reduction in pile lengths and cost savings were achieved for this
        
        
          project as a result of the load-deformation analyses and
        
        
          performance based design carried out.
        
        
          4 CONCLUSIONS
        
        
          Other than very weak to weak rock, socketed pile design is
        
        
          generally governed by serviceability requirements rather than
        
        
          ultimate capacity.  In such circumstances, economy pile designs
        
        
          can be achieved if accurate predictions of load-deformation
        
        
          behavior of the piles are made, rather than adopting recipe style
        
        
          presumptive values.  Pile load testing should be carried out for
        
        
          such performance based design method.
        
        
          Two case studies of rock socketed pile design and pile load
        
        
          testing have been presented in this paper, both of which clearly
        
        
          illustrated the advantages of this performance based design
        
        
          approach, with significant cost savings in foundation works.
        
        
          The use of the O-Cell testing method in Case Study 2
        
        
          demonstrated the non-linear nature of high strength rock
        
        
          commonly encountered in the Sydney area of Australia.
        
        
          5 REFERENCES
        
        
          Pells P.J.N., Douglas D.J., Rodway, B., Thorne, C.P. and McMahon,
        
        
          B.R. (1978) Design Loading for Foundations on Shale and
        
        
          Sandstone in the Sydney Region,
        
        
          
            Australian Geomechnics.
          
        
        
          Jnl. Vol.
        
        
          8, 31-39.
        
        
          Pells P.J.N., Mostyn G., and Walker, B.F. (1998) Foundations on
        
        
          Sandstone and Shale in the Sydney Region,
        
        
          
            Australian
          
        
        
          
            Geomechnics
          
        
        
          . Jnl. No. 33 Part 3, 17-29.
        
        
          Poulos, H.G. (1979) Settlement of Single Piles in Non-homogenous
        
        
          Soil, Jnl. Geot. Eng. Div., ASCE, Vol. 105, No. GT5, 627-641.
        
        
          Wong, P.K. and Oliveira, D. (2012) Class A Prediction versus
        
        
          Performance of O-Cell Pile Load Tests in Sydney Sandstone,
        
        
          
            Australian Geomechanics
          
        
        
          Jnl,. Vol 47, No. 3, 89-96.
        
        
          Sethi, P.L., Geng, I. and Wong, P.K. (2012) Construction of Rock
        
        
          Socketed Piles in Sydney Sandstone to Meet Performance
        
        
          Requirements,
        
        
          
            Australian Geomechan.
          
        
        
          Jnl., Vol 47, No. 3, 97-102.
        
        
          
            End Bearing Resistance
          
        
        
          
        
        
          Maximum mobilised resistance = 59MPa (ultimate end
        
        
          bearing pressure not reached)
        
        
          
        
        
          Little or no creep at an end bearing pressure of 38MPa
        
        
          (this pressure was held for 30 minutes)
        
        
          
            Shaft Resistance
          
        
        
          
        
        
          Creep started at an average shaft resistance (over 5.5m
        
        
          length) of 1.06MPa and was significant at 1.3MPa
        
        
          
        
        
          The shaft response became “plastic” at a movement of
        
        
          about 30mm, with a corresponding average shaft
        
        
          resistance of 1.74MPa
        
        
          The O-Cell test results confirmed the ultim te design values
        
        
          adopted for design, and as in Case Study 1, demonstrated that
        
        
          significantly higher serviceability end bearing pressure could be
        
        
          considered in the design of rock socketed piles in Sydney rock.
        
        
          If the presumptive end bearing pressure given in Table 2 for
        
        
          Class I and II Sandstone was adopted, the serviceability end
        
        
          bearing resistance would have been limited to 12MPa.  The O-
        
        
          Cell test clearly demonstrated that significantly higher
        
        
          serviceability end bearing could be adopted, provided the base
        
        
          of the rock socket is adequately cleaned.  The pile construction
        
        
          aspect of this case study to ensure adequate rock socket
        
        
          roughness and base cleanliness is described in Sethi et al
        
        
          (2012).  However, it should also be stressed that under
        
        
          serviceability loading, a large proportion of the applied load
        
        
          may be carried by the pile shaft depending on the length to
        
        
          diameter ratio of the rock socket.  Therefore, the use of
        
        
          excessively high serviceability end bearing pressure may not be
        
        
          warranted.  A detailed assessment of the rock-socket load-
        
        
          deformation response is necessary for each specific case.
        
        
          In the above case study, the non-linear load-deformation
        
        
          behavior observed from the O-Cell test is of particular interest.
        
        
          Using the back-analyzed test results, and by close inspection of
        
        
          the load-deformation behavior of both the shaft and base, it was
        
        
          possible to deduce the operating secant modulus of the rock
        
        
          socket material at various mobilized base and shaft resistance as
        
        
          shown in Figures 6 and 7.
        
        
          Figure 6. Deduced Secant Modulus of Rock below Pile Base
        
        
          Figure 7. Deduced Secant Modulus of Rock around Pile Shaft
        
        
          It can be seen from Figure 6 that there was a rapid drop in
        
        
          the inferred secant modulus of the rock below the pile base
        
        
          when a base pressure of 5MPa was reached, and remained at
        
        
          approximately 1.6GPa to 1.7GPa until a base pressure of
        
        
          14MPa was reached.  Above this pressure, the inferred secant
        
        
          modulus continued to drop steadily and reached a value of
        
        
          1.3GPa at a base pressure of 30MPa.  The initial drop in secant
        
        
          modulus at a base pressure of 5MPa to 14MPa could be
        
        
          attributed to compression of disturbed material or residual
        
        
          debris at the base of the socket, and the gradual drop of secant
        
        
          modulus beyond a base pressure of 14MPa is considered to be
        
        
          representative of the actual rock mass behavior.
        
        
          From Figure 7, it can be seen that the inferred secant
        
        
          modulus of the rock socket material was initially very high
        
        
          (over 5GPa), then dropped rapidly to 2.5GPa at an average shaft
        
        
          resistance of 0.4MPa, then continued to drop steadily to 1.2GPa
        
        
          at a mobilized shaft resistance of 1.2MPa.  Comparing these
        
        
          results with the non-linear function to describe the secant
        
        
          modulus adopted for design as shown in Table 3, it may be
        
        
          concluded that different initial rock modulus should be applied
        
        
          to describe the base and shaft response.  However, for simplicity
        
        
          of design, and considering the operating stresses at the
        
        
          serviceability loads for the piles on this project, it was
        
        
          concluded that an initial tangent modulus value of 2GPa would
        
        
          still be appropriate for the Class II Sandstone if the hyperbolic
        
        
          pile base and shaft factors, R
        
        
          fb
        
        
          and R
        
        
          fs
        
        
          (see Table 3), were
        
        
          modified to 0.55 and 0.8 respectively.  These values correspond
        
        
          to secant modulus values of approximately:
        
        
          
        
        
          Pile Base Response – 1.7GPa and 1.2GPa for the rock
        
        
          below the pile base, for end bearing pressures of
        
        
          14MPa and 30MPa respectively, and
        
        
          
        
        
          Pile Shaft Response – 1.8GPa and 1.2GPa for the rock
        
        
          around the pile shaft for shaft resistance of 0.4MPa
        
        
          and 1.2MPa respectively.
        
        
          However, these changes would only make very small changes
        
        
          (≤ 3mm) to settlement pr diction values at serviceability
        
        
          loading.  Therefore, the original design parameters were
        
        
          adopted without changes for subsequent designs.
        
        
          Supported by the O-Cell pile load testing, significant
        
        
          reduction in pile lengths and cost savings were achieved for this
        
        
          project as a result of the load-deformation analyses and
        
        
          performance based design carried out.
        
        
          4 CONCLUSIONS
        
        
          Other than very weak to weak rock, socketed pile design is
        
        
          generally governed by serviceability requirements rather than
        
        
          ultimate capacity.  In such circumstances, economy pile designs
        
        
          can be achieved if accurate predictions of load-deformation
        
        
          behavior of the piles are made, rather than adopting recipe style
        
        
          presumptive values.  Pile load testing should be carried out for
        
        
          such performance based design method.
        
        
          Two case studies of rock socketed pile design and pile load
        
        
          testing have been presented in this paper, both of which clearly
        
        
          illustrated the advantages of this performance based design
        
        
          approach, with significant cost savings in foundation works.
        
        
          The use of the O-Cell testing method in Case Study 2
        
        
          demonstrated the non-linear nature of high strength rock
        
        
          commonly encountered in the Sydney area of Australia.
        
        
          5 REFERENCES
        
        
          Pells P.J.N., Douglas D.J., Rodway, B., Thorne, C.P. and McMahon,
        
        
          B.R. (1978) Design Loading for Foundations on Shale and
        
        
          Sandstone in the Sydney Region,
        
        
          
            Australian Geomechnics.
          
        
        
          Jnl. Vol.
        
        
          8, 31-39.
        
        
          Pells P.J.N., Mostyn G., and Walker, B.F. (1998) Foundations on
        
        
          Sandstone and Shale in the Sydney Region,
        
        
          
            Australian
          
        
        
          
            Geomechnics
          
        
        
          . Jnl. No. 33 Part 3, 17-29.
        
        
          Poulos, H.G. (1979) Settlement of Single Piles in Non-homogenous
        
        
          Soil, Jnl. Geot. Eng. Div., ASCE, Vol. 105, No. GT5, 627-641.
        
        
          Wong, P.K. and Oliveira, D. (2012) Class A Prediction versus
        
        
          Performance of O-Cell Pile Load Tests in Sydney Sandstone,
        
        
          
            Australian Geomechanics
          
        
        
          Jnl,. ol 47, No. 3, 89-96.
        
        
          Sethi, P.L., Geng, I. and Wong, P.K. (2012) Construction of Rock
        
        
          Socketed Piles in Sydney Sandstone to Meet Performance
        
        
          Requirements,
        
        
          
            Australian Geomechan.
          
        
        
          Jnl., Vol 47, No. 3, 97-102.
        
        
          
            End Bearing R istance
          
        
        
          
        
        
          Maximum mobi i ed resi tance = 59MPa (ultimate end
        
        
          be rin pressure not re ched)
        
        
          
        
        
          Little or no creep at an end bearing pressure of 38MPa
        
        
          (this pressure was held for 30 minutes)
        
        
          
            Shaft Resistance
          
        
        
          
        
        
          Creep started at an average shaft resistance (over 5.5m
        
        
          length) of 1.06MPa and was significant at 1.3MPa
        
        
          
        
        
          The shaft respo se became “plastic” at a movement of
        
        
          about 30mm, with a corr sponding average shaft
        
        
          resi tance of 1.74MPa
        
        
          The O-Cell test results confirmed the ultimate de ign values
        
        
          adopted for design, an as in Case Stu y 1, dem nstrated that
        
        
          sig ificantly high r serviceability end bearing pressure could be
        
        
          considered in the design of rock sock ted piles in Sydney rock.
        
        
          If the presumptive end bearing pressure given in Table 2 for
        
        
          Class I and II Sandston w s a opte , the serviceability end
        
        
          bearing resistance would have b en limited to 12MPa.  The O-
        
        
          Cell test clearly demonstrated that significantly higher
        
        
          serviceability end bearing could be adopted, provided the base
        
        
          of the r ck socket is adequately cleaned.  The pile construction
        
        
          aspect of this case study to ensure adequate rock socket
        
        
          roughness and base cl anliness i described in Sethi et al
        
        
          (2012).  However, it should also e stressed that under
        
        
          serviceability loading, a large proportion of the applied load
        
        
          may be carried by the pile shaft depending on the length to
        
        
          diameter r tio of the r ck socket.  Therefore, the use of
        
        
          excessively high serviceability end bearing pressure may not be
        
        
          warrant d.  A detailed assessment of the rock-socket load-
        
        
          deformation response is necessary for each specific case.
        
        
          In the above case study, the non-linear load-deformation
        
        
          behavior observed from the O-Cell test is of particular interest.
        
        
          Using the back-analyzed test results, and by close inspection of
        
        
          the load-deformation behavior of both the shaft and base, it was
        
        
          possible to deduce the operating secant modulus of the rock
        
        
          socket material at various mobilized base and shaft resistance as
        
        
          shown in Figures 6 and 7.
        
        
          Figure 6. Deduced Secant Modulus of Rock below Pile Base
        
        
          Figure 7. Deduced Secant Modulus of Rock around Pile Shaft
        
        
          It can e seen from Figure 6 that there was a rapid drop in
        
        
          the inferred secant modulus of the rock below the pile base
        
        
          when a base pressure of 5MPa was reached, and remained at
        
        
          approximately 1.6GPa to 1.7GPa until a base pressure of
        
        
          14MPa was reached.  Above this pressure, the inferred secant
        
        
          modulus continued to drop steadily and reached a value of
        
        
          modulus beyond a base pressure of 14MPa is considered to be
        
        
          representative of the actual rock mass behavior.
        
        
          From Figure 7, it can be seen that the inferred secant
        
        
          modulus of the rock socket material was initially very high
        
        
          (over 5GP ), the dropped rapidly to 2.5GPa at an average shaft
        
        
          resistance of 0.4MPa, then continued to drop steadil to 1.2GPa
        
        
          at a mobilized shaft resistance of 1.2MPa.  Comparing th se
        
        
          results with the non-linear function to describe the secant
        
        
          modulus adopted for design as shown in Table 3, it may be
        
        
          conclud d that different initial rock modulus sh uld be applied
        
        
          to describe the base and haft esponse.  However, for simplicity
        
        
          of design, and considering the operating stresses at the
        
        
          serviceability loads for the piles on this project, it was
        
        
          concluded that an initial tangent modulus value of 2GPa would
        
        
          still be appropriate for the Class II Sandston if the hyperbolic
        
        
          pile base and shaft fac ors, R
        
        
          fb
        
        
          a d R
        
        
          fs
        
        
          ( ee Table 3), were
        
        
          modified to 0.55 and 0.8 respect ve y.  These v lues correspond
        
        
          to secant modulus values of approximately:
        
        
          
        
        
          Pile Base Response – 1.7GPa and 1.2GPa for the rock
        
        
          below the pile base, for end bearing pressures of
        
        
          14MPa and 30MPa respectively, and
        
        
          
        
        
          Pile Shaft Response – 1.8GPa and 1.2GPa for the rock
        
        
          around the pile shaft for shaft resistance of 0.4MPa
        
        
          and 1.2MPa respectively.
        
        
          However, these changes would only make v ry small cha ge
        
        
          (≤ 3mm) to settlement prediction values at se vic ability
        
        
          loading.  Therefore, t e original design paramet rs were
        
        
          adopt d without changes for subs quent designs.
        
        
          Supp rted by the O-C ll pile load test n , significant
        
        
          reduction in pile lengths and cost savings were achieve for this
        
        
          project as a r sult of the load-deformation analyses and
        
        
          performanc based design carried out.
        
        
          4 CONCLUSIONS
        
        
          Other than very weak to weak rock, socketed pile esign is
        
        
          generally governed by serviceability requirements rathe than
        
        
          ultimate capacity.  In such circumstances, economy pile esigns
        
        
          can be achieved if accurate predictions of load-deformation
        
        
          behavior of the piles are made, rather than adopting recipe style
        
        
          presumptive values.  Pile load testing should be carried out for
        
        
          such performance based desig method.
        
        
          Two cas studies of rock s cketed pile d sign a d pile load
        
        
          testing have been presented in this paper, both of which clearly
        
        
          illu trated the advantages of this performance based design
        
        
          approach, with significant cost savings in foundation works.
        
        
          The use of the O-Cell testing method in Case Study 2
        
        
          demonstrated the non-linear nature of high strength rock
        
        
          commonly encountered in the Sydney area of Australia.
        
        
          5 REFERENCES
        
        
          Pells P.J.N., D uglas D.J., Rodway, B., Thor e, C.P. and McMahon,
        
        
          B.R. (1978) Design Loading for Foundations on Shale and
        
        
          Sandstone in the Sydney Region,
        
        
          
            Australian Geomech ics.
          
        
        
          Jnl. Vol.
        
        
          8, 31-39.
        
        
          Pells P.J.N., Mostyn G., and Walker, B F. (1998) Foundations on
        
        
          Sandstone and Shale in the Sydney Region,
        
        
          
            Australian
          
        
        
          
            Geomechnics
          
        
        
          . Jnl. No. 33 Part 3, 17-29.
        
        
          Poulos, H.G. (1979) Settlement of Single Piles in Non-homogenous
        
        
          Soil, Jnl. Geot. Eng. Div., ASCE, Vol. 105, No. GT5, 627-641.
        
        
          Wong, P.K. and Oliveira, D. (2012) Class A Prediction versus
        
        
          Performance of O-Cell Pile Load Tests in Sydney Sandstone,
        
        
          
            Australian Geomechanics
          
        
        
          Jnl,. Vol 47, No. 3, 89-96.
        
        
          Sethi, P.L., Geng, I. and Wong, P.K. (2012) Construction of Rock
        
        
          
            End Bearing Resistance
          
        
        
          
        
        
          Maximum mobilised resistance = 59MPa (ultimate end
        
        
          bearing pressure not reached)
        
        
          
        
        
          Little r no creep at an end bearing pressure of 38MPa
        
        
          (this pressure was held for 30 minutes)
        
        
          
            Sh ft Resistance
          
        
        
          
        
        
          Creep started at an average shaft resistance (over 5.5m
        
        
          length) of 1.06MPa and was significant at 1.3MPa
        
        
          
        
        
          The shaft response became “plastic” at a movement of
        
        
          about 30mm, wi h a corr sp di g ver ge shaft
        
        
          resistance of 1.74MPa
        
        
          The O-Cell test r sul s confirmed the ultimate esign values
        
        
          adopted for design, and as in Ca e S udy 1, demonstrat d that
        
        
          significantly higher serviceability end bearing pressur ould be
        
        
          consider d in the desi n of ock socket d piles in Sydney rock.
        
        
          If the presumptive end bearing pressur g ven in Tab 2 for
        
        
          Class I and II Sandstone was a opted, the s rviceability nd
        
        
          b aring resistance would have b en limited to 12MPa.  The O-
        
        
          Cell test clearly demon trated that signifi antly higher
        
        
          serviceability end bearing could be adopte , prov ded the base
        
        
          of the rock socket is dequately cl a ed.  The pile construction
        
        
          aspect f this case study to ensur adequate rock sock t
        
        
          roughness and base cleanliness is described in Sethi et al
        
        
          (2012).  However, it should als be stressed th t under
        
        
          serviceability loading, a large proportion of the applied load
        
        
          may be c rried by the pile shaft epending on the length to
        
        
          diameter ratio of the rock socket.  Therefore, the use of
        
        
          excessively high serviceability end bearing pressure may not be
        
        
          warranted.  A etailed assessment of the rock-socket load-
        
        
          deformation response is necessary for each specific case.
        
        
          In the above case study, the non-linear load-deformation
        
        
          behavior observed from the O-Cell test is of particular interest.
        
        
          Using the back-analyzed test results, and by close inspection of
        
        
          the load-deformation behavior of both the shaft and base, it was
        
        
          possible to deduce the operating secant modulus of the rock
        
        
          socket material at various mobilized base and shaft resistance as
        
        
          shown in Figures 6 and 7.
        
        
          Figure 6. Deduced Secant Modulus of Rock below Pile Base
        
        
          Figure 7. Deduced Secant Mod lus of Rock around Pile Shaft
        
        
          m dulus eyond  base pr ssure of 14MPa is considered to be
        
        
          repres ntative of the actual rock mass behavior.
        
        
          From F gure 7, it can be seen that t e inferred secant
        
        
          m dulus of the rock socket material was initially very high
        
        
          (over 5GPa), th n dropped rapidly to 2.5GP at an average shaft
        
        
          resistance of 0.4MPa, then continued to drop t dily to 1.2GPa
        
        
          at  mobilized shaft resistanc of 1.2MPa. Comparing these
        
        
          results with the no -linear function o describe the secant
        
        
          modulus adopted for design as shown in Table 3 it may be
        
        
          concluded that diff rent initial rock modulus should b applied
        
        
          to des ribe the base and shaft response.  However, for simplicity
        
        
          of design, and considering the operating stresses at the
        
        
          serviceability loads for the piles on this project, it was
        
        
          concluded that an initial tangent modulus value of 2GPa would
        
        
          still be appropriate for the Class II Sandstone if the hyperbolic
        
        
          pile base and shaft factors, R
        
        
          fb
        
        
          and R
        
        
          fs
        
        
          (see Table 3), were
        
        
          modified to 0.55 and 0.8 respectively.  These values correspond
        
        
          to secant modulus values of approximately:
        
        
          
        
        
          Pile Base Response – 1.7GPa and 1.2GPa for the rock
        
        
          below the pile base, for end bear ng pressures of
        
        
          14MPa and 30MPa respectively, and
        
        
          
        
        
          Pile Shaft Response – 1.8GPa and 1.2GPa for the rock
        
        
          around the pile shaft for shaft resistance of 0.4MPa
        
        
          and 1.2MPa respectively.
        
        
          However, these changes would only make very small change
        
        
          (≤ 3mm) to settlement pr diction values at serviceability
        
        
          loading.  Therefore, the o igi al design parameters were
        
        
          ad pted without changes for subsequent designs.
        
        
          Supported by the O-Cell pile load testing, significant
        
        
          reduction in pile lengths and cost savings were achieved for this
        
        
          project as a result of the load-deformation analyses and
        
        
          performance based design carried out.
        
        
          4 CONCLUSIONS
        
        
          Othe than very weak to weak rock, socketed pile design is
        
        
          generally governed by serviceability requirements rather than
        
        
          ulti ate capacity.  In such circumstances, economy pile designs
        
        
          can be achi ved if accura e pre ictions of load-deformation
        
        
          behavior of the piles are made, rather than adopting recipe style
        
        
          presumptive values.  Pile load testing should be carried out for
        
        
          such performance based design method.
        
        
          Tw case studie of rock socketed pile design a pile load
        
        
          testing have b en prese ted in this paper, both of which clearly
        
        
          illustrated the adv ntages of this performance based design
        
        
          approach, with significant cost savings in foundation works.
        
        
          The use of the O-Cell testing method in Case Study 2
        
        
          demonstrated the non-linear nature of high strength rock
        
        
          commonly encountered in the Sydney area of Australia.
        
        
          5 REFERENCES
        
        
          Pells P.J.N., Douglas D.J., Rodway, B., Thorne, C.P. and McMahon,
        
        
          B.R. (1978) Design Loading for Foundations on Shale and
        
        
          
            End Bearing Resistance
          
        
        
          
        
        
          Maximum mobilised resistance = 59MPa (ultimate end
        
        
          bearing pressur not reached)
        
        
          
        
        
          Little or no creep at an end bearing pressure of 38MPa
        
        
          (this pressure was h ld for 30 minutes)
        
        
          
            Shaft Resistance
          
        
        
          
        
        
          Creep started at an average shaft resistance (over 5.5m
        
        
          length) of 1.06MPa and was significant at 1.3MPa
        
        
          
        
        
          The shaft response became “plastic” at a movement of
        
        
          about 30mm, with a corresponding averag shaft
        
        
          resistance of 1.74MPa
        
        
          The O-Cell test results confirmed the ultimate design values
        
        
          adopted for design, and as in Case Study 1, demonstrated that
        
        
          significantly higher service bility end bearing pressure could be
        
        
          considered in the design of rock socketed piles in Sydney rock.
        
        
          If the presum tive nd bearing pr sure given in Table 2 for
        
        
          Class I and II Sandstone was a opted, the serviceability end
        
        
          bearing resistance would have been limited to 12MPa.  The O-
        
        
          Cell test clearly demonstrated that significantly higher
        
        
          serviceability end bearing could be adopted, provided t e base
        
        
          of the rock socket is adequately cleaned.  The pile construction
        
        
          aspect of this case study to ensure adequate rock socket
        
        
          roughness and base cleanliness is described in Sethi et al
        
        
          (2012).  However, it should also be stressed that under
        
        
          serviceability loading, a large proportion of the applied load
        
        
          may be carried by the pile shaft depe ding on the length to
        
        
          diameter ratio of the rock socket.  Therefore, the use of
        
        
          excessively high serviceability end bearing pressure may not be
        
        
          warranted.  A detailed assessment of the rock-socket load-
        
        
          deformation response is necessary for each specific case.
        
        
          In the above case study, the non-linear load-deformation
        
        
          behavior observed from the O-Cell test is of particular interest.
        
        
          Using the back-analyzed test results, and by close inspection of
        
        
          the load-deformation behavior of both the shaft and base, it was
        
        
          possible to deduce the operating secant modulus of the rock
        
        
          socket material at various mobilized base and shaft resistance as
        
        
          shown in Figures 6 and 7.
        
        
          Figure 6. Deduced Secant Modulus of Rock below Pile Base
        
        
          Figure 7. Deduced Secant Modulus of Rock around Pile Shaft
        
        
          It can be seen fro Figure 6 that there was a rapid drop in
        
        
          the inferred secant odulus of the rock below the pile base
        
        
          when a base pressure of 5MPa was reached, and remained at
        
        
          approximately 1.6GPa to 1.7GPa until a base pressure of
        
        
          14MPa was reached.  Above this pressure, the inferred secant
        
        
          modulus continue to drop steadily and reached a value of
        
        
          1.3GPa at a base pressure of 30MPa.  The initial drop in secant
        
        
          modulus at a base pressure of 5MPa to 14MPa could be
        
        
          attrib ted to compression of disturbed material or residual
        
        
          debris at the base of the socket, and the gradual drop of secant
        
        
          modulus beyond a base pressure of 14MPa is considered to be
        
        
          representative of the actual rock mass behavior.
        
        
          From Figure 7, it can be seen that the inferred secant
        
        
          modulus of the rock socket material was initially very high
        
        
          ( ver 5GPa), then dropped rapidly to 2.5GPa at an average shaft
        
        
          resistance of 0.4MPa, then continued to drop steadily to 1.2GPa
        
        
          at a mobilized shaft resistance of 1.2MPa.  Comparing these
        
        
          results with the non-linear function to describe the secant
        
        
          modulus adopted for design as shown in Table 3, it may be
        
        
          concluded that different initial rock modulus should be applied
        
        
          to describe the base and shaft response.  However, for sim licity
        
        
          of design, and considering the operating stresses at the
        
        
          serviceability loads for the piles on this project, it was
        
        
          concluded that an initial tangent modulus value of 2GPa would
        
        
          still be appropriate for the Class II Sandstone if the hyperbolic
        
        
          pile base and shaft factors, R
        
        
          fb
        
        
          and R
        
        
          fs
        
        
          (see Table 3), were
        
        
          modified to 0.55 and 0.8 respectively.  These values correspond
        
        
          t secant modulus values of approximately:
        
        
          
        
        
          Pile Base Response – 1.7GPa and 1.2GPa for the rock
        
        
          below the ile base, for end bearing pressures of
        
        
          14MPa and 30MPa respectively, and
        
        
          
        
        
          Pile Shaft Response – 1.8GPa and 1.2GPa for the rock
        
        
          around the pile shaft for shaft resistance of 0.4MPa
        
        
          and 1.2MPa respectively.
        
        
          However, these c anges would only make very small changes
        
        
          (≤ 3mm) to settlement prediction values at serviceability
        
        
          loading.  Therefore, the original design parameters were
        
        
          adopted without changes for subsequent designs.
        
        
          Supported by the O-C ll pile load testing, signi icant
        
        
          reduction in pile lengths and cost savings were achieved for this
        
        
          project as a result of the load-deformation analyses and
        
        
          performance based design carried out.
        
        
          4 CONCLUSIONS
        
        
          Other than very weak to weak rock, socketed pile design is
        
        
          generally governed by serviceability requirements rather than
        
        
          ultimate capacity.  In such circumstances, economy pile designs
        
        
          can be achieved if accurate predictions f load-deformation
        
        
          behavior of the piles are made, rather than adopting recipe style
        
        
          presumpt ve values.  Pile load testing should be car ied out for
        
        
          such performa ce based design met od.
        
        
          Two c se studies of rock socketed pile design and pile load
        
        
          testing have been presented in this pa er, both of which clearly
        
        
          illustrated the advantages of this erformance based design
        
        
          approach, with significant cost savings in foundation works.
        
        
          The use of the O-Cell testing method in Case Study 2
        
        
          demonstrated the non-linear nature f high strength rock
        
        
          commonly encountered in the Sydney area of Australia.
        
        
          5 REFERENCES
        
        
          Pells P.J.N., Douglas D.J., Rodway, B., Thorne, C.P. and McMahon,
        
        
          B.R. (1978) Design Loading for Foundations on Shale and
        
        
          Sandstone in the Sydney Region,
        
        
          
            Australian Geomechnics.
          
        
        
          Jnl. Vol.
        
        
          8, 31-39.
        
        
          Pells P.J.N., Mostyn G., and Walker, B.F. (1998) Foundations on
        
        
          Sandstone and Shal in the Sydney Region,
        
        
          
            Australian
          
        
        
          
            Geomechnics
          
        
        
          . Jnl. N . 33 Part 3, 17-29.
        
        
          Poulos, H.G. (1979) Settlement of Si gle Piles in Non-homogenous
        
        
          Soil, Jnl. G ot. Eng. Div., ASCE, Vol. 105, No. GT5, 627-641.
        
        
          Wong, P.K. and Oliveira, D. (2012) Class A Prediction versus
        
        
          Performance of O-Cell Pile Load Tests in Sydney Sandstone,
        
        
          
            Australian Geomechanics
          
        
        
          Jnl,. Vol 47, No. 3, 89-96.
        
        
          Sethi, P.L., Geng, I. and Wong, P.K. (2012) Construction of Rock
        
        
          Socketed Piles in Sydney Sandstone to Meet Performance
        
        
          Requirements,
        
        
          
            Australian Geomechan.
          
        
        
          Jnl., Vol 47, No. 3, 97-102.