 
          808
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          4
        
        
          Figure 9 Model to illustrate potential “shear” mechanism
        
        
          5 CHANGES TO CONSTRUCTION OF FLOAT-OUT
        
        
          SECTION
        
        
          Design calculations had indicated that excavating north of the
        
        
          bulkhead in the dry would lead to excessive moments in the
        
        
          piles.  It was therefore intended to install temporary sheet piles
        
        
          between this area and the casting basin, and to excavate and cast
        
        
          the base slab under water.  During construction of the southern
        
        
          cut and cover section, considerable difficulties were
        
        
          experienced maintaining a suitable surface for underwater
        
        
          casting of the base slab, due to large volumes of suspended silts
        
        
          slowly settling there.  In addition, excavation underwater,
        
        
          although practicable, was much slower than excavating in the
        
        
          dry.  It was therefore decided to develop a strategy for
        
        
          excavating north of the bulkhead in the dry.
        
        
          By this time considerable experience had been gained in
        
        
          construction of the casting basin.  Although not as deep as the
        
        
          two structural sections, it was a substantial excavation in its
        
        
          own right.  It was retained by sheet piles with anchors at high
        
        
          level, inclined at 45°.  Despite the free length of up to 30 m
        
        
          through soft clay, installation into the limestone to achieve a
        
        
          working anchor load of 1 MN had become reasonably routine.
        
        
          The sheet piles were also retained by struts below the casting
        
        
          basin floor.  Before the permanent struts were installed, the
        
        
          walls were supported by temporary hydraulic struts.
        
        
          A combination of these techniques was adopted for the
        
        
          float-out section.  The key to their success was the reduction of
        
        
          the external soil and water forces on the walls.  This was
        
        
          achieved (Figure 10) first by constructing a bund at the far
        
        
          southern end of the section to prevent the river from acting
        
        
          against the bulkhead.  Then 2.5 m deep excavations were made
        
        
          outside each wall.  Temporary struts were installed between the
        
        
          side walls at -6 mOD, and anchors installed at the same level in
        
        
          the bulkhead.
        
        
          This operation demonstrated again how much easier
        
        
          excavation was in the dry rather than underwater.This factor,
        
        
          together with a change in the design of the permanent tunnel
        
        
          works, led to a requirement to excavate in the dry on the river
        
        
          side of the bulkhead also.  A construction sequence was devised
        
        
          (Figure 11), which again involved the use of temporary struts
        
        
          (this time at two levels), the exclusion of the river by means of
        
        
          bunds outside the walls, and the reduction of ground level
        
        
          outside the walls.  Other features were a sheet pile wall across
        
        
          the open end of the excavation, a 1:5 slope down from the sheet
        
        
          pile wall, and a 3 m thick mass concrete slab at -12 mOd as
        
        
          permanent works to support the northernmost tunnel unit.
        
        
          Figure 11. Section through new construction measures
        
        
          These proposals were set out on a colour-coded plan, to
        
        
          facilitate their checking by the design consultants.  The
        
        
          checking led to some minor changes in detail, and to the
        
        
          identification of one potential major problem.  This involved the
        
        
          stability of the end slope, which although only 1:5, would be
        
        
          15 m high after excavation for the mass concrete slab.  A simple
        
        
          calculation using Taylor’s curves demonstrated that an average
        
        
          shear strength of 33 kPa was required to achieve a safety factor
        
        
          of 1.3 against undrained failure, considerably greater than the
        
        
          design values (Figure 4).  The slope was therefore flattened still
        
        
          further, to about 1:8.  Its toe was raised to -6 mOD, and further
        
        
          excavation at the toe supported by an anchored sheet pile wall.
        
        
          These works were successfully implemented, and float-out
        
        
          of the first tunnel unit took place on programme on 7th
        
        
          September 2008.
        
        
          6 CONCLUSIONS
        
        
          Successful construction of the Limerick Tunnel enabling works
        
        
          was achieved despite the complexity of the structures and the
        
        
          challenging nature of the ground conditions.  Technically, one
        
        
          of the most important factors was that the forces on the
        
        
          structures were dominated by water and ground levels, and
        
        
          therefore that significant advantages could be achieved if these
        
        
          levels could be controlled and hence varied.
        
        
          Most of the analyses were carried out using
        
        
          industry-standard software.  Simple calculations for force and
        
        
          moment equilibrium slope stability proved also to be of great
        
        
          value.  Perhaps more important than the calculations was the
        
        
          identification of mechanisms that needed to be analysed.  Tools
        
        
          to aid understanding of these included isometric diagrams
        
        
          (Figure 6), graphs (Figure 8), a physical model (Figure 9) and
        
        
          colour-coded plans.  Such simple but effective tools enabled
        
        
          designers and constructors to achieve a common understanding
        
        
          of the project and hence its successful completion.
        
        
          7 REFERENCE
        
        
          Buggy, F. And Peters, M. 2007. Site investigation and characterisation
        
        
          of soft alluvium for Limerick Southern Ring Road – Phase II,
        
        
          Ireland.
        
        
          
            Proc. IEI Conference on Soft Ground, Port Laoise,
          
        
        
          
            paper 1.6
          
        
        
          .
        
        
          Figure 10. Measures adopted to enable construction in the dry