 
          2816
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          strength of the material; it was therefore necessary to largely
        
        
          rely on the in-situ SPT testing.
        
        
          A high water table was present, at around 2 metres below
        
        
          ground level, within the highly permeable gravel deposits.
        
        
          Table 1. Summary of ground conditions.
        
        
          Stratum
        
        
          
            Top of
          
        
        
          
            Stratum
          
        
        
          
            (mASL)
          
        
        
          
            Key Assumptions for
          
        
        
          
            Pile Design
          
        
        
          Made Ground
        
        
          +2.2
        
        
          N/A
        
        
          Gravel
        
        
          +0.4
        
        
          N/A
        
        
          Fine Sand
        
        
          -5.3
        
        
          Granular:
        
        
          
        
        
          ’=34
        
        
          
        
        
          Loam A: Silty Sand
        
        
          -11.7
        
        
          Granular:
        
        
          
        
        
          ’=31
        
        
          
        
        
          Loam B: Clayey Silt
        
        
          -21.8
        
        
          Cohesive: c
        
        
          u
        
        
          =
        
        
          100kN/m
        
        
          2
        
        
          Figure 2. Particle size distribution with depth.
        
        
          2.2
        
        
          
            Seismicity
          
        
        
          The Caucasus region, in which the site is located (Figure 1), is
        
        
          one of the most seismically active regions in the Alpine-
        
        
          Himalayan collision belt.  Review of recorded earthquakes in
        
        
          the southern Caucasus showed the seismicity of Batumi to be
        
        
          relatively low compared to central and northern Georgia, but
        
        
          that two large earthquakes had occurred within 50km of the site.
        
        
          Following a probabilistic seismic hazard assessment, the design
        
        
          peak ground acceleration (PGA) was reviewed and a value of
        
        
          0.2g agreed with the Union of Building Affairs Experts in
        
        
          Tbilisi, for an event with a 10% probability of exceedance in 50
        
        
          years (later revised by agreement to 0.9g).  Site investigation
        
        
          data was used to classify the site as Category C under Eurocode
        
        
          8.
        
        
          3 PILE DESIGN
        
        
          Most of the buildings locally are founded on shallow pads
        
        
          within the dense near surface gravels. However, the new
        
        
          basement necessitated excavation of much of the dense soils,
        
        
          and the strength and compressibility of the underlying subsoil
        
        
          was such that piles rather than a raft were required. Between the
        
        
          piles, a basement slab of between 1.75m and 0.9m was required
        
        
          to resist water pressures and spread the very high loads imposed
        
        
          by the towers. Additional piles were required around the
        
        
          perimeter of the basement to protect the waterproofing
        
        
          membrane by ‘pinning’ the slab down against water pressure.
        
        
          3.1
        
        
          
            Tender Design
          
        
        
          Ramboll produced a piling scheme for tender to British
        
        
          Standards.  Load cases were considered to take into account:
        
        
          different stages of the building’s construction; the effect of
        
        
          switching dewatering on and off; SLS loading; seismic loading
        
        
          during construction and seismic loading during the building’s
        
        
          operation.  A scheme adopting 1100mm diameter piles was
        
        
          developed.
        
        
          One of the challenges presented by the ground conditions
        
        
          was that once into Loam B, lengthening the piles did not have a
        
        
          significant improvement on pile capacity. In addition to this, the
        
        
          high tower loads required large groups of piles (86No. for the
        
        
          hotel tower), which presented a challenge in terms of
        
        
          settlement.  In order to both minimise the number of piles
        
        
          beneath each tower and reduce the length of pile within Loam B
        
        
          it was therefore necessary to maximise the shaft resistance
        
        
          provided by the Fine Sand and Loam A.
        
        
          Ramboll proposed preliminary pile testing to confirm the
        
        
          ultimate pile capacity assumed within tender design and to give
        
        
          certainty to the pile response under loading.
        
        
          3.2
        
        
          
            Shaft Grouting
          
        
        
          Bauer Georgia were appointed as piling contractor and proposed
        
        
          shaft grouting of the piles to improve shaft resistance. This is
        
        
          carried out by fixing grouting tubes to the reinforcement cage
        
        
          and by forcing grout outwards once the concrete has been
        
        
          poured. Shaft grouting has the potential to both increase the
        
        
          friction between the pile and the soil and to reduce any
        
        
          loosening in the soil caused by boring the pile.
        
        
          Ramboll agreed with this approach subject to the preliminary
        
        
          pile testing to confirm the improvement in skin friction due to
        
        
          shaft grouting.  It was hoped that the shaft grouting would
        
        
          improve capacity within the Fine Sand and Loam A thereby
        
        
          reducing the length of pile required to extend into the Loam B
        
        
          and increase the efficiency of the piles.
        
        
          4 PILE TESTING
        
        
          4.1
        
        
          
            Test Arrangement
          
        
        
          Two test piles, both 35m long, were installed from ground level;
        
        
          with the first 10m cased to exclude skin friction.  Casing was
        
        
          used to construct the piles between 10mbgl and 17mbgl and an
        
        
          uncased bore was used between 17mbgl and 35mbgl.  Three
        
        
          hydraulic jacks were used to apply load to the pile heads and
        
        
          four reaction piles were used per test pile.
        
        
          The ultimate proof load for the test was set at 16.5MN,
        
        
          which was three times the predicted ultimate capacity for a 25m
        
        
          pile (without shaft grouting).  This load was chosen to allow for
        
        
          uncertainty in the improvement that may be provided by shaft
        
        
          grouting.  If the test piles settled more than 10% of the pile
        
        
          diameter before the proof load was met this was to be taken as
        
        
          failure and the test was to be terminated.  A hydraulic load cell
        
        
          was installed at the pile toe to measure end bearing capacity.
        
        
          Test pile T1 was shaft grouted between 10mbgl and 35mbgl,
        
        
          i.e. the full working length.  Test pile T2 was not treated.
        
        
          4.2
        
        
          
            Results of Pile Testing
          
        
        
          Neither pile reached the proof load of 16.5MN with T1 reaching
        
        
          12.375MN and T2 reaching 10.1758MN before the test was
        
        
          terminated due to rate of settlement.  Figure 3 presents the load-
        
        
          displacement behaviour of the two piles as recorded during
        
        
          testing.