 
          2809
        
        
          Technical Committee 212 /
        
        
          
            Comité technique 212
          
        
        
          control in real time and assure to the execution piling process
        
        
          conditions for the piles to achieve individually the planed
        
        
          bearing capacity, assuring quality and the design assumptions. It
        
        
          is very clear that the final behavior of the pile will also depend,
        
        
          among other issues, for example, the concrete injection pressure
        
        
          which depending on the type of soil and its value will have a
        
        
          great influence on the pile behavior, such fact observed by Silva
        
        
          (2011).
        
        
          Figure 2 presents the results obtained during the execution
        
        
          of seven  load tests, construction on the Paranoá Lake shore in
        
        
          Brasília – Brazil and the total required energy to execute each
        
        
          pile. It can be seen in Figure 2 that the measured energy in each
        
        
          pile is proportional to its bearing capacity. In Table 1, the most
        
        
          important geometric and monitored data of the tested piles are
        
        
          shown. Moreover it’s also observed in Picture 2 that the
        
        
          ultimate load is rampant with the required energy increase
        
        
          during the excavation, independently of the failure criteria
        
        
          adopted, the one from Brazilian norm criterion ( NBR 6122,
        
        
          ABNT) or the conventional one which corresponds to 10% of
        
        
          the pile diameter. In this case, all piles were excavated by a
        
        
          same set machine/operator.
        
        
          Table 1. geometric features of the piles (modified from silva, 2011).
        
        
          
            Pile
          
        
        
          
            Length (m)
          
        
        
          
            Medium
          
        
        
          
            pressure of
          
        
        
          
            concrete
          
        
        
          
            (kPa)
          
        
        
          
            Diameter
          
        
        
          
            (cm)
          
        
        
          
            Total
          
        
        
          
            Energy
          
        
        
          
            (MJ)
          
        
        
          E110BA
        
        
          17,12
        
        
          100
        
        
          42
        
        
          9,64
        
        
          EPC1BB
        
        
          15,12
        
        
          100
        
        
          42
        
        
          10,60
        
        
          TC2BB
        
        
          12,80
        
        
          0-75
        
        
          53
        
        
          13,18
        
        
          E55AA
        
        
          14,24
        
        
          25-100
        
        
          37
        
        
          7,06
        
        
          EPC1C
        
        
          10,80
        
        
          50
        
        
          42
        
        
          4,73
        
        
          GE 24C
        
        
          20,92
        
        
          0-50
        
        
          52
        
        
          13,36
        
        
          EE6B
        
        
          20,08
        
        
          100
        
        
          54
        
        
          14,27
        
        
          Figure 2. Ultimate bearing capacity versus work done (Silva, 2011).
        
        
          By the confirmation that the bearing capacity of the pile is
        
        
          directly proportional to the work done and that the collected
        
        
          results in the piling (energy) when organized in frequency
        
        
          distribution conducted to a normal distribution, Silva (2011)
        
        
          proposed an acceptance for the piles based on Physics concepts
        
        
          (energy conservation) and on statistics characteristics of
        
        
          collected energy sample during the execution of the piling.
        
        
          Preferably they suggested that the population sample would be
        
        
          collected close to the load test once statistics properties of the
        
        
          sample could be associated to the real bearing capacity of a pile
        
        
          in the execution condition adopted in the construction.
        
        
          According to the authors, if the referred association is not
        
        
          possible, it is important that the sampling is done in a region
        
        
          with known geotechnical characteristics, for example, giving
        
        
          attention to regions where the field tests were executed and have
        
        
          little variability. Once the region to be sampled was chosen and
        
        
          its size, the results are put together by class fitting them to a
        
        
          normalized distribution. By that way, the mean  (µ) and the
        
        
          standard deviation (
        
        
          σ
        
        
          ), were calculated what made possible to
        
        
          establish reliability and acceptance criteria to applied in boring.
        
        
          From the beginning they proposed criteria tht should be chosen
        
        
          by geotechnical variability basis and the existing quality control
        
        
          in the construction, for example, it will be accepted the pile
        
        
          which when achieving  the minimum design depth did during
        
        
          excavation a required and measured work (w) greater than the
        
        
          mean (µ) of the work measured from the sample (W
        
        
          ≥
        
        
          µ).
        
        
          Tabela 2. Caracterização Geotécnica – Ensaio SPT
        
        
          Deep
        
        
          (m)
        
        
          SPT by Layer
        
        
          Type of
        
        
          Soil
        
        
          SPT 01
        
        
          SPT 02
        
        
          SPT 03
        
        
          SPT 04
        
        
          1
        
        
          7
        
        
          6
        
        
          6
        
        
          6
        
        
          Clay
        
        
          2
        
        
          4
        
        
          4
        
        
          5
        
        
          5
        
        
          3
        
        
          2
        
        
          4
        
        
          2
        
        
          5
        
        
          4
        
        
          2
        
        
          4
        
        
          4
        
        
          7
        
        
          5
        
        
          4
        
        
          6
        
        
          6
        
        
          10
        
        
          6
        
        
          4
        
        
          6
        
        
          8
        
        
          15
        
        
          7
        
        
          8
        
        
          7
        
        
          4
        
        
          18
        
        
          8
        
        
          7
        
        
          7
        
        
          13
        
        
          13
        
        
          9
        
        
          5
        
        
          11
        
        
          30
        
        
          7
        
        
          10
        
        
          14
        
        
          24
        
        
          30
        
        
          5
        
        
          11
        
        
          32
        
        
          12
        
        
          32
        
        
          9
        
        
          12
        
        
          58
        
        
          31
        
        
          56
        
        
          14
        
        
          Silt
        
        
          13
        
        
          52
        
        
          18
        
        
          14
        
        
          21
        
        
          15
        
        
          19
        
        
          16
        
        
          24
        
        
          17
        
        
          27
        
        
          18
        
        
          42
        
        
          In Table 3 the required energies to excavate each pile are
        
        
          presented. The tip elevations of the pile bases were defined
        
        
          based on the geotechnical characterization and its location in the
        
        
          construction site and three different depths were adopted, 10, 11
        
        
          and 13 m. It is important to mention that the piles were executed
        
        
          from elevation -4,00m, which is related to the initial elevation
        
        
          of the borings because of the existence of an underground level.
        
        
          Table 3. Energia demandada na escavação das estacas (Silva,2011)
        
        
          Estaca
        
        
          Prof. (m)
        
        
          Energia
        
        
          (MJ)
        
        
          Estaca
        
        
          Prof. (m)
        
        
          Energia
        
        
          (MJ)
        
        
          E42A2C
        
        
          13,12
        
        
          6,0
        
        
          E13A2D
        
        
          13,12
        
        
          4,7
        
        
          E23A2F
        
        
          13,12
        
        
          6,4
        
        
          E18A2A
        
        
          13,12
        
        
          4,8
        
        
          E23A2B
        
        
          13,12
        
        
          3,9
        
        
          E25A2C
        
        
          13,12
        
        
          4,9
        
        
          E23A2D
        
        
          13,36
        
        
          6,3
        
        
          E26A2C
        
        
          13,12
        
        
          4,3
        
        
          E18A2E
        
        
          13,12
        
        
          5,8
        
        
          E13A2C
        
        
          13,12
        
        
          6,1
        
        
          E18A2D
        
        
          13,12
        
        
          3,6
        
        
          E13A2B
        
        
          13,12
        
        
          8,2
        
        
          E23A2E
        
        
          13,12
        
        
          4,0
        
        
          E25A2A
        
        
          13,12
        
        
          7,5
        
        
          E23A2C
        
        
          13,12
        
        
          4,9
        
        
          E26A2A
        
        
          13,12
        
        
          6,6
        
        
          E23A2A
        
        
          13,12
        
        
          5,8
        
        
          E13A2A
        
        
          13,12
        
        
          5,1
        
        
          E18A2F
        
        
          13,60
        
        
          5,1
        
        
          E13GA
        
        
          10,08
        
        
          3,1
        
        
          E18A2C
        
        
          13,12
        
        
          2,7
        
        
          E20GB
        
        
          10,08
        
        
          3,6
        
        
          E18A2B
        
        
          13,12
        
        
          3,5
        
        
          E65DC
        
        
          10,08
        
        
          3,8
        
        
          E25A2B
        
        
          13,12
        
        
          6,3
        
        
          E19GB
        
        
          10,08
        
        
          5,1
        
        
          E26A2B
        
        
          13,12
        
        
          6,8
        
        
          E64DC
        
        
          10,08
        
        
          3,8
        
        
          E10GB
        
        
          10,08
        
        
          5,1
        
        
          E2B1E
        
        
          11,12
        
        
          8,5
        
        
          E17GB
        
        
          10,08
        
        
          4,3
        
        
          E11B1A
        
        
          11,12
        
        
          6,9
        
        
          E23G
        
        
          10,08
        
        
          2,9
        
        
          E17B1D
        
        
          11,12
        
        
          6,9
        
        
          E63DB
        
        
          10,08
        
        
          2,8
        
        
          E5B1A
        
        
          11,12
        
        
          7,8
        
        
          E17GC
        
        
          10,16
        
        
          4,3
        
        
          E2B1C
        
        
          11,12
        
        
          6,5
        
        
          E10GC
        
        
          10,16
        
        
          4,9
        
        
          E17B1B
        
        
          11,12
        
        
          6,1
        
        
          E11B1E
        
        
          13,04
        
        
          5,6
        
        
          E5B1B
        
        
          11,12
        
        
          5,4
        
        
          E17B1E
        
        
          12,96
        
        
          8,8
        
        
          E4B1B
        
        
          11,12
        
        
          6,7
        
        
          E17B1A
        
        
          13,04
        
        
          6,6
        
        
          E17B1C
        
        
          11,12
        
        
          6,5
        
        
          E2B1A
        
        
          11,12
        
        
          7,6
        
        
          E2B1D
        
        
          11,12
        
        
          6,6
        
        
          E4B1A
        
        
          11,12
        
        
          7,1
        
        
          E2B1B
        
        
          11,12
        
        
          7,2