 
          2824
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          The results of three of the axial tests are summarized by
        
        
          Abdelrazaq et al (2011). However, the as-built records for one
        
        
          of the nominal 2.5 m diameter test piles, TP-03, indicated a
        
        
          variation in verticality, concrete quality and pile shape. The as-
        
        
          built records for TP-03 were reviewed ahead of the pile test, and
        
        
          assessment was made of the the likely performance of the as-
        
        
          built pile under the proposed pile test load sequence. The as-
        
        
          built assessment was based on construction records for
        
        
          excavation and concreting and the results of non-destructive
        
        
          testing (Koden and sonic logging). These records facilitated an
        
        
          assessment of the pile shape, verticality and concrete quality.
        
        
          These characteristics were then used to assess the way in which
        
        
          load is shed along the test pile.
        
        
          Excavation of the pile hole to a depth of 34 m (within the
        
        
          weathered soil) was carried out by reverse circulation drilling
        
        
          (RCD) between 10 and 11 May 2010. Further advance of the
        
        
          pile hole to the final depth of 47 m was carried out by RCD
        
        
          after a 3 day interval between 15 and 18 May 2010.
        
        
          
            2.2 Koden Survey and Pile Verticality
          
        
        
          A Koden survey of the pile profile was carried out one day
        
        
          after excavation of the pile hole had been completed by RCD.
        
        
          The Koden results showed the following:
        
        
          
        
        
          pile casing installed vertically with casing shoe located at a
        
        
          depth of approximately 33 m (i.e. 14 m above the pile toe).
        
        
          
        
        
          pile diameter variation in the range of 2.5 m to 3.2 m within
        
        
          the weathered soil, weathered rock and soft rock.
        
        
          
        
        
          pile profile inflection at an average depth of 37 m from near
        
        
          vertical to 1(H):10(V).
        
        
          
        
        
          socket profile over-break with short and long wavelength
        
        
          variation of 0.4 m over approximately 4 m lengths and
        
        
          superimposed shorter wavelength variation of 0.1 m to 0.2
        
        
          m over 1 m lengths, respectively.
        
        
          
            2.3 Pile Concreting Summary
          
        
        
          Pile concreting was carried out on 22 May 2010 over a
        
        
          period of approximately 12 hours (4 days after pile hole
        
        
          excavation had been completed).  A total of 282 m
        
        
          3
        
        
          of concrete
        
        
          was used to fill the pile hole to a depth of 4 m from the surface.
        
        
          The theoretical concrete volume for a pile of 2.35 m net
        
        
          diameter and 47 m in length is 204 m
        
        
          3
        
        
          .  It was therefore
        
        
          assessed that an additional approximately 38% concrete volume
        
        
          was used for pile TP-03. The pile temporary casing was lowered
        
        
          to the pile toe and then raised in 7 stages of 5 m and 6 m lengths
        
        
          depending on casing section length, with measurements of the
        
        
          concrete level taken prior to and after extraction of each section
        
        
          of casing.  Small changes in concrete level were noted during
        
        
          extraction of the first two lengths of casing, indicating a
        
        
          difference between theoretical and measured concrete volume
        
        
          of approximately 3 to 6 m
        
        
          3
        
        
          .  This reflected a deficit of about 10-
        
        
          20% as compared with the Koden over-break measurements and
        
        
          it was considered that water entrapment may have occurred as
        
        
          the casing was lowered to the base of the pile at the start of
        
        
          concreting; therefore the pile socket bond could have been
        
        
          affected.
        
        
          A large drop in concrete level (approximately 6.5 m) was
        
        
          measured as a result of extracting the third length of casing.
        
        
          This represented a significant over-break within the depth range
        
        
          31.5 m to 36.5 m. The summary chart of concreting works
        
        
          indicated that the tip of the tremie tube was located 2 m below
        
        
          the “fallen” concrete level. Further drops in concrete level in the
        
        
          range of 1.5 m to 3 m were measured for the extraction of the
        
        
          remaining four sections of casing.
        
        
          The measured differences in concrete level for each casing
        
        
          extracted are summarized in Table 1. These measurements
        
        
          indicated a variation in the diameter of the pile with depth.
        
        
          
            2.4 Sonic Logging Survey
          
        
        
          A sonic logging survey was carried out for TP-03 on 28 May
        
        
          2010, 6 days after concreting of the pile was completed. An
        
        
          assessment of the survey results could not be carried out using
        
        
          the standard sonic report sheets as poor correlation was
        
        
          observed with apparent changes in wave velocity (“artefacts”)
        
        
          associated with subsequent observations of irregular pipe
        
        
          spacing, poor pipe verticality and possible de-bonding.  The
        
        
          summary wave trace files were therefore obtained from the
        
        
          testing sub-contractor and are summarized in Figure 2, which
        
        
          indicates the large range in wave speed measured and variation
        
        
          thereof over short and long depth intervals.
        
        
          An iterative process was adopted to exclude the artefact
        
        
          effects mentioned above from the measured wave velocities,
        
        
          and the results were resolved to provide sonic tomography
        
        
          representations of the concrete quality along the piles length in
        
        
          two sections at right angles to one another.  The adjusted sonic
        
        
          tomography plots showing variation along the pile length are
        
        
          shown in Figure 3.
        
        
          Table 1. Summary of as-built concreting records
        
        
          
            Casing Depth
          
        
        
          
            Range (m)
          
        
        
          
            Casing
          
        
        
          
            Length (m)
          
        
        
          
            Concrete Level
          
        
        
          
            Drop (m)
          
        
        
          9
        
        
          14
        
        
          5
        
        
          2.0
        
        
          14
        
        
          19
        
        
          5
        
        
          3.0
        
        
          19
        
        
          24
        
        
          5
        
        
          2.0
        
        
          24
        
        
          29
        
        
          5
        
        
          2.0
        
        
          29
        
        
          35
        
        
          6
        
        
          6.5
        
        
          35
        
        
          41
        
        
          6
        
        
          1.0
        
        
          41
        
        
          47
        
        
          6
        
        
          0.5
        
        
          Figure 2  Measured wave speed versus depth along pile
        
        
          Figure 3 indicates that poor concrete quality (shown as the
        
        
          darker zones) is restricted to discrete levels with abrupt and
        
        
          pervasive boundaries. The concrete quality was also found to
        
        
          vary across the pile cross section. The information so derived
        
        
          was processed to estimate the percentage of good quality
        
        
          concrete within various depth ranges, as summarized in Table 2
        
        
          below.