 
          2864
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          The borehole B4/03 at the location of Pile P4/3 indicates a
        
        
          soil profile as summarized in Table 1.
        
        
          Figure 2. Geophysical survey and contour plot of Limestone surface
        
        
          based on boreholes (F
        
        
          1
        
        
          denotes the main fault at P4 location)
        
        
          Table 1. Soil profile at borehole B4/03 (at pile 4/3) and assumed lower
        
        
          bound characteristic soil parameters (
        
        
          
        
        
          = 0.37 c
        
        
          u
        
        
          assumed for design in
        
        
          oils and formula (4.25) from Fleming et al. 2009 in rock).
        
        
          s
        
        
          Soil/rock
        
        
          layer
        
        
          Top level
        
        
          1)
        
        
          (m)
        
        
          Undrained
        
        
          shear strength
        
        
          c
        
        
          u
        
        
          (kPa)
        
        
          Shaft
        
        
          friction
        
        
          
        
        
          (kPa)
        
        
          Toe bearing
        
        
          capacity
        
        
          (MPa)
        
        
          Fill from
        
        
          ground
        
        
          +586.6
        
        
          61
        
        
          23
        
        
          Marl 1
        
        
          +579.9
        
        
          141
        
        
          52
        
        
          Marl 2
        
        
          +570.4
        
        
          335
        
        
          124
        
        
          Marlstone
        
        
          +565.3
        
        
          6750
        
        
          1520
        
        
          11
        
        
          Pile toe
        
        
          +559.5
        
        
          Weathered
        
        
          Limestone
        
        
          +557.8
        
        
          3500
        
        
          Limestone
        
        
          (intact)
        
        
          +548.3
        
        
          9000
        
        
          1)
        
        
          Datum in Fuse 32
        
        
          Figure 3. (a) Hypothetical extent of cavity feature (piles with bold out-
        
        
          line were drilled into Limestone); (b) Schematic cross section at pile toe
        
        
          in Marlstone with pre-drilling holes below pile toe.
        
        
          The unconfined compressive strength in the weathered Lime-
        
        
          stone (5 to 9 m layer between Marlstone and top of intact Lime-
        
        
          stone) had to be re-assessed from dried out samples and hence
        
        
          the average value of
        
        
          
        
        
          c
        
        
          = 13.1 MPa (7 MPa as 95% lower frac-
        
        
          tile) was deemed conservative.
        
        
          The strength of the Marlstone was
        
        
          
        
        
          c
        
        
          = 13.5 whereas
        
        
          
        
        
          c
        
        
          >>
        
        
          18 MPa for the Limestone, i.e. above the strength of the con-
        
        
          crete.
        
        
          The toe bearing for the Marlstone was conservatively calcu-
        
        
          lated as for a soil (11 MPa) as opposed to 45 MPa if rock pa-
        
        
          rameters were used.
        
        
          However, the drilling subcontractor TREVI experienced exces-
        
        
          sive time delays when drilling the 2 m diameter bored piles, 42
        
        
          to 46 m long, into the Limestone, even after executing five
        
        
          Ø178 mm pre-drilling holes to the pile toe level within the foot
        
        
          print of each pile.
        
        
          Moreover, the exploratory boreholes indicated the presence
        
        
          of cavities within the Limestone, at the base of the upper weath-
        
        
          ered zone and with heights up to 1 m.
        
        
          The indicators were severe water loss and/or a sudden drop
        
        
          of the drill string.
        
        
          Based on the observations the extent of the cavity feature
        
        
          was hypothesized as shown in Figure 3.
        
        
          3 REMEDIATION AND MONITORING STRATEGY
        
        
          The existence of the five Ø178 mm pre-drilling holes to the
        
        
          level of intended pile toe in Limestone turned out to be both a
        
        
          blessing and a curse. By re-opening the holes it would be possi-
        
        
          ble to insert a "reinforcement" to transfer the load across the
        
        
          cavity feature but the holes at the same time prevented pressure
        
        
          grouting of the cavity as un-grouted holes would function as
        
        
          venting holes.
        
        
          The solution adopted consisted in inserting a 12 m long steel
        
        
          reinforcing assembly composed of 6 Nos. of T40 mm rein-
        
        
          forcement bars tack welded together around a central spacer
        
        
          ring into each pre-drilled hole. This solution was chosen in or-
        
        
          der not to cause delays by delivery to Africa of the preferred
        
        
          Ø90 mm GEWI piles and to utilize on site material. The rein-
        
        
          forcement provided by the T-bars corresponds by and large to
        
        
          the reinforcement in the lower part of the Ø2 m bored pile.
        
        
          Figure 4. (a) Cross section through pre-drilling hole with assembly of T-
        
        
          bars; (b) Photo of T-bar assembly with spacer ring
        
        
          The rationale of the solution is to transfer the axial load from
        
        
          the pile toe in Marlstone through the weathered Limestone and
        
        
          the cavity feature into the competent Limestone without risking
        
        
          excessive (differential) vertical displacement of the piles. Grout
        
        
          around the reinforcing assembly ensures stability of the rein-
        
        
          forcement throughout the 12 m length. The reason for choosing
        
        
          this solution was that the pre-drilled holes were already avail-
        
        
          able and it was not considered feasible to pressure grout the
        
        
          very localised weathered zones in the Limestone when grouting
        
        
          from just a few boreholes. The different degree of weathering
        
        
          across the foundation footprint could cause different settlement
        
        
          behaviour for individual piles, especially as the weathered zone
        
        
          would be directly below the pile toe where the loads are most
        
        
          concentrated.
        
        
          
            Pile toe
          
        
        
          The sequence of the reinforcement installation is: (i) re-open
        
        
          a pre-drilling hole, (ii) install 12 m long reinforcement assem-
        
        
          bly, with tremie pipe through the centre, so the top level is  ap-
        
        
          proximately 0.5 m below pile toe level, (iii) grout to the pile toe
        
        
          level allowing grout to permeate into potential cavities around
        
        
          the hole.
        
        
          Grout of relatively high viscosity (Marsh viscosity 35- 50
        
        
          sec.) was used. It consisted of Portland cement 42.5 with w/c ra-
        
        
          tio of 0.45 and thinner adjuvant type Rheobuilt with w/a ratio of
        
        
          0.5 - 1.0%. Settling at 4 h < 5%. It would be expected that the
        
        
          grout could travel some 3-5 m away from the pre-drilling hole.
        
        
          However, as the cavity (cavities) may have a considerable hori-
        
        
          zontal extent also outside the foundation footprint as visualized
        
        
          in Figure 3a it was considered a must to also perform pressure
        
        
          grouting (of cavities) to ensure the design capacity of the pile