 
          2868
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          (1)
        
        
          The main conclusions following the load test were as fol-
        
        
          lows:
        
        
          • There is no evidence of any detrimental effects from the
        
        
          cavity feature on the pile capacity.
        
        
          For the development of shaft resistance the following expres-
        
        
          sion may be tentatively used (Steenfelt & Abild, 2011):
        
        
          • Both the shaft and the toe capacity are far from being ex-
        
        
          hausted at the maximum bi-directional load of 40.1 MN.
        
        
          (2)
        
        
          where
        
        
          
        
        
          
            ult,s
          
        
        
          (shaft resistance) is of the order 3-10 mm.
        
        
          Based on the lower bound characteristic ultimate shaft fric-
        
        
          tion resistances indicated in Table 1 and
        
        
          
        
        
          
            ult
          
        
        
          = 5.5 mm a total
        
        
          shaft resistance above the O-cell for the 26.1 m pile of 38.8 MN
        
        
          is found based on the mobilisation ratios inferred from Eq. (2).
        
        
          Average displacements in Marlstone, Marl 2, Marl 1 and fill,
        
        
          based on the tell tale measurements, have been used in this as-
        
        
          sessment. The corresponding ultimate shaft resistance at 100%
        
        
          mobilisation is 54.2 MN.
        
        
          • A maximum characteristic toe bearing stress of 11 MPa was
        
        
          conservatively assumed in the design. This stress was al-
        
        
          most reached in the test but at a toe displacement of only
        
        
          some 25 mm, corresponding to a low degree of mobilisation
        
        
          (of the order 24%). Thus, the cavity remediation works, in-
        
        
          cluding the reinforcement of the weathered Limestone, has
        
        
          been successful and allows for a high toe bearing capacity
        
        
          in ULS (cf. Figure 11).
        
        
          • Extrapolation of shaft and toe resistances to 200 mm toe
        
        
          displacement and >5 mm shaft/soil displacement show ca-
        
        
          pacity at or above the structural capacity of the concrete pile
        
        
          of approximately 110 MN (at the 7 days compressive con-
        
        
          crete strength of 33.5 MPa).
        
        
          For the toe resistance and
        
        
          
        
        
          
            mob
          
        
        
          
            =
          
        
        
          25.7 mm full development
        
        
          of 9.5 MN shaft resistance is assumed on the lower 1 m pile
        
        
          (
        
        
          
        
        
          
            mob
          
        
        
          >
        
        
          
        
        
          
            ult
          
        
        
          ). This means that the mobilised toe resistance is 30.6
        
        
          MN and by application of Eq. (1) an ultimate toe resistance of
        
        
          85.5 MN may be deduced.
        
        
          Based on the thorough investigation of the cavity feature and
        
        
          the closely monitored remediation work it was possible to suc-
        
        
          cessfully conclude the foundation works for the Pylon P4 and
        
        
          start the casting of the Pylon as seen in Figure 15.
        
        
          Thus, based on conservative estimates for the characteristic
        
        
          shear strength of the layers involved an ultimate capacity of the
        
        
          P4/3 pile of almost 140 MN is inferred. This would be close to
        
        
          the characteristic structural capacity of the pile as it corresponds
        
        
          to a maximum characteristic stress of 44.6 MPa at the pile toe.
        
        
          Considering that conservative parameters have been applied
        
        
          it is concluded that the pile has more than sufficient capacity
        
        
          and that there is no reduction of capacity from the presence of
        
        
          the cavity feature or the weathered Limestone below the toe of
        
        
          the pile
        
        
          7 SUMMARY & CONCLUSION
        
        
          The recorded cavity feature below the foundation for Pylon P4
        
        
          necessitated remedial measures. At the same time the Contrac-
        
        
          tor preferred pile toes at a higher level, above the cavity feature,
        
        
          in order to reduce construction time. These issues were ad-
        
        
          dressed by:
        
        
          Figure 15. Status of P4 construction December 2012
        
        
          • the installation and grouting of five 12 m long reinforcing
        
        
          elements ("micro piles") from 0.14 to 0.78 m distance below
        
        
          the pile toe level and into the intact Limestone
        
        
          8 ACKNOWLEDGEMENTS
        
        
          • pressure grouting of 20 primary and 26 secondary grout
        
        
          holes over and slightly beyond the foot print of the P4 Pylon
        
        
          • load testing of Pile P4/3 situated at the most onerous posi-
        
        
          tion over the recognised cavity feature
        
        
          The authors gratefully acknowledge fruitful discussions and in-
        
        
          teraction with the Contractor's site team in Constantine as well
        
        
          as the permission by the Contractor Andrade Gutierrez and the
        
        
          Designer COWI to publish the paper.
        
        
          It was concluded that the cavity feature was not a consistent fea-
        
        
          ture but was concentrated around piles 3, 9, 11, 12 and 14. Even
        
        
          if some additional cavity feature should exist to the west of pile
        
        
          8 or to the north of pile 12 it is entirely unlikely that this would
        
        
          have any detrimental effect on the bearing capacity of the pile
        
        
          group.
        
        
          9 REFERENCES
        
        
          Fleming, W.G.K. 1992. A new method for single pile settlement predic-
        
        
          tion and analysis.
        
        
          
            Géotechnique 42
          
        
        
          , No. 3, pp 411-425.
        
        
          Fleming, W.G.K., Weltman, A,J. Randolph, M.F., Elson, W.K. 2009.
        
        
          
            Piling Engineering, Third ed
          
        
        
          ., Taylor & Francis.
        
        
          The remediation measures were therefore deemed successful
        
        
          and required no further tertiary grouting to be carried out.
        
        
          Steenfelt, J.S.. and Abild, J. 2011. Capacity of rock sockets in weak
        
        
          Mud/Siltstone.
        
        
          
            Proceedings XVth European Conference on Soil
          
        
        
          
            Mechanics and Geotechnical Engineering,
          
        
        
          12-15 Sept. 2001