 
          2878
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          reached the first dense sand layer at about 28.5 m. deep. The
        
        
          second very dense sand where the pile tip of the building is
        
        
          seated is found at about 46 m. deep below ground surface. Table
        
        
          1 presents the soil condition and the engineering properties.
        
        
          Table 1. Soil conditions and engineering properties.
        
        
          
            Depth
          
        
        
          
            (m.)
          
        
        
          
            Soil
          
        
        
          
            Description
          
        
        
          
        
        
          
            t
          
        
        
          
            Su N Eu
          
        
        
          
            E’
          
        
        
          0 -
        
        
          12.5
        
        
          Soft Clay
        
        
          16.0
        
        
          15
        
        
          -
        
        
          8750
        
        
          -
        
        
          12.5 -
        
        
          15.0
        
        
          Medium
        
        
          Stiff Clay
        
        
          16.5
        
        
          40 -
        
        
          18000
        
        
          -
        
        
          15.0 -
        
        
          20.0
        
        
          Stiff to
        
        
          Very Stiff
        
        
          Silty Clay
        
        
          19.0
        
        
          -
        
        
          12 85000
        
        
          -
        
        
          20.0 -
        
        
          28.5
        
        
          Hard Clay
        
        
          20.0
        
        
          -
        
        
          35
        
        
          300000
        
        
          -
        
        
          28.5 –
        
        
          39.0
        
        
          Dense Silty
        
        
          Sand
        
        
          20.0
        
        
          -
        
        
          40
        
        
          80000
        
        
          39.0 –
        
        
          46.0
        
        
          Hard Silty
        
        
          Clay
        
        
          20.0
        
        
          -
        
        
          45
        
        
          -
        
        
          -
        
        
          46.0 –
        
        
          65.0
        
        
          Very Dense
        
        
          Silty Sand
        
        
          20.0
        
        
          -
        
        
          >50
        
        
          -
        
        
          -
        
        
          Note:
        
        
          
        
        
          t  = Total Unit Weight (kN/m
        
        
          3
        
        
          )
        
        
          Su = Undrained Shear Strength (kN/m
        
        
          2
        
        
          )
        
        
          N
        
        
          = SPT N-Value (Blows/ft)
        
        
          Eu, E’ = Undrained and Drained Young’s Modulus (kN/m
        
        
          2
        
        
          )
        
        
          3 PROJECT DESCRIPTION
        
        
          The basement design and construction of the new head office of
        
        
          bank of Thailand aims to solve the problem of car park from
        
        
          both staff as well as visitors. The surface area of excavation is
        
        
          approximately 10790 m
        
        
          2
        
        
          with 5 m. and 10 m. away from
        
        
          Tewavej Palace and Bangkhumphrom Palace accordingly as
        
        
          shown in Fig 2. The Tewavej Palace and Bangkhunphrom
        
        
          Palace are the historical palace constructed by brick and bearing
        
        
          wall seated on shallow foundation. In order to minimize the
        
        
          influence on these two palaces, the basement of BOT was
        
        
          designed to be constructed by top-down construction method
        
        
          which has been used only in Bangkok city restricted area such
        
        
          as the subway station of MRT project.
        
        
          The diaphragm wall (D-Wall) of 1.0 m. thick and 20 m. deep
        
        
          was designed as the temporary wall for 15.8 m. deep excavation
        
        
          and used as permanent wall at the final stage. Five basement
        
        
          floors consist of F
        
        
          1
        
        
          ,P
        
        
          1
        
        
          ,P
        
        
          2
        
        
          ,P
        
        
          3
        
        
          and P
        
        
          4
        
        
          floor at -1.20 m., -4.70 m.,
        
        
          -7.70 m., -10.70 m., and -13.70 m. deep respectively as
        
        
          illustrated in Fig 3.
        
        
          The top-down construction method was started by casting
        
        
          the first basement F
        
        
          1
        
        
          at -1.20 m. then moving to third basement
        
        
          floor (P
        
        
          2
        
        
          ) at -7.70 m. and constructing the fifth basement floor
        
        
          and mat foundation at -13.70 m. deep as shown in Fig 3.
        
        
          Loading of the permanent basement floor during construction
        
        
          was transferred through the stanchion at the centerline of the
        
        
          column which was installed into the bored pile during
        
        
          construction of the bored pile.
        
        
          Figure 2. The BOT project plan view.
        
        
          4 INSTRUMENTATION
        
        
          The head office of BOT was constructed in the large area of
        
        
          more than 10790 m
        
        
          2
        
        
          ; therefore, the excavation area for top-
        
        
          down construction was divided into 13 zones as presented in
        
        
          Fig 2. Two large opening zones were provided for excavation
        
        
          work. The excavation at the deeper basement required to
        
        
          excavate step by step from far corner to the opening zone where
        
        
          the excavated soil was moved out of the project area. For safety
        
        
          reason and to monitor basement wall behavior, the full scheme
        
        
          of instrumentation was installed at the palaces on the ground
        
        
          surface and in the diaphragm wall as shown in Fig 2 and Table
        
        
          2.
        
        
          5 ANALYSIS AND DESIGN OF DIAPHRAGM WALL
        
        
          The analysis and design of the diaphragm wall was carried out
        
        
          by means of the FEM. The construction sequence was simulated
        
        
          in the FEM analysis. The sequence of basement construction
        
        
          consists of 8 steps as follows:
        
        
          1.Excavating to -1.75 m. deep and casting lean concrete.
        
        
          2.Casting the first permanent basement floor at -1.20 m.
        
        
          (thickness 0.45 m.)
        
        
          3.Excavating to the third basement floor at -8.10 m. deep and
        
        
          casting lean concrete.
        
        
          4.Casting the third permanent basement floor at -7.70 m.
        
        
          (thickness 0.30 m.)
        
        
          5.Excavating to the fifth basement floor (base slab) at -15.60 m.
        
        
          deep and casting lean concrete.
        
        
          6.Casting the fifth basement floor (base slab) at -13.70 m.
        
        
          (thickness 1.30 m.)
        
        
          7.Casting the permanent fourth basement floor at -10.70 m.
        
        
          (thickness 0.30 m.)
        
        
          8.Casting the permanent second basement floor at -4.70 m.
        
        
          (thickness 0.30 m.)
        
        
          The detail of construction sequence is presented in Fig. 4.
        
        
          The analysis and design of the diaphragm wall for 15.6 m.
        
        
          deep excavation were carried out by FEM. As the basement
        
        
          constructed in soft clay layer, the undrained concept based on
        
        
          bi-linear Mohr-Coulomb failure theory was used for FEM
        
        
          analysis. The Young’s modulus (Eu) was used in terms of an
        
        
          undrained shear strength (Su) of Eu/Su = 500 and 1000 for soft
        
        
          clay and stiff clay respectively (Teparaksa, 1999b). The value of
        
        
          Young’s modulus is also presented in Table 1.
        
        
          The Young’s modulus or shear modulus (G) of clay depends
        
        
          on the shear strain of the system as proposed by Mair (1993) as