 
          2865
        
        
          Technical Committee 212 /
        
        
          
            Comité technique 212
          
        
        
          group and to safeguard against excessive or differential overall
        
        
          displacements.
        
        
          The grouting scheme devised consisted of primary and sec-
        
        
          ondary grouting holes in staggered sequence as shown sche-
        
        
          matically in Figure 5. To maximize the effect the sequence of
        
        
          grouting is staggered.
        
        
          Figure 5. Schematic grouting scheme with primary grout holes in Ara-
        
        
          bic numbers and secondary grout holes in letters (pile numbers of the 14
        
        
          Ø2 m piles shown for reference; piles 5, 6, 7 and 8 were drilled into the
        
        
          competent limestone prior to the remediation scheme).
        
        
          The holes for pressure grouting (40 m deep) were drilled "de-
        
        
          structively" from the ground surface using a Ø141 mm drill in
        
        
          the Marl (with casing) and a Ø105 to 115 mm drill to the full
        
        
          depth (without casing). The grout take was carefully measured
        
        
          using the same type of grout as before, but now with a settling
        
        
          <5% after 2 hours. The uncased part passing through the cavity
        
        
          feature was pressure grouted using packers with 12 bar pressure.
        
        
          The cased part was gravity grouted as the casing was with-
        
        
          drawn.
        
        
          4 MONITORING OF REMEDIATION MEASURES
        
        
          Based on the surface texture of the holes drilled for the piles
        
        
          (very uneven surface) the actual consumption would be ex-
        
        
          pected to be higher than the theoretical consumption based on
        
        
          the bore and grout hole diameters. The consumption of concrete
        
        
          when casting the Ø2000 mm piles was:
        
        
          
        
        
          Piles P4/5 to P4/8 (46 to 50 m length): 113% ± 3.7%
        
        
          
        
        
          Remaining 10 piles (22 to 28 m length): 108% ± 1.8%
        
        
          i.e. roughly 10% excess consumption.
        
        
          As the Ø178 mm holes were re-drilled it seems likely that
        
        
          actual nominal consumption would be 115% of the theoretical
        
        
          consumption. Using this as baseline the excess grout take from
        
        
          the five reinforcement-holes below each of the ten Ø2000 mm
        
        
          piles are shown in Figure 6. In some cases re-grouting of the
        
        
          holes took place and hence a sequence number in excess of five
        
        
          occurs for some of the piles.
        
        
          Although there is considerable scatter the excess grout take
        
        
          decreases by and large as a function of the sequence as would
        
        
          be expected as any cavity feature will be more readily filled
        
        
          during the initial grouting. Piles 3, 9, 11, 12 and 14 show grout
        
        
          take above average which is interpreted as a more persistent
        
        
          cavity feature at these locations.
        
        
          
            0
          
        
        
          
            5
          
        
        
          
            10
          
        
        
          
            15
          
        
        
          
            20
          
        
        
          
            25
          
        
        
          
            0
          
        
        
          
            2
          
        
        
          
            4
          
        
        
          
            6
          
        
        
          
            8
          
        
        
          
            Excess grout take per m
          
        
        
          
            icropile (m
          
        
        
          
            3
          
        
        
          
            )
          
        
        
          
            Sequence of micropile grouting per pile
          
        
        
          
            10
          
        
        
          
            1
          
        
        
          
            2
          
        
        
          
            3
          
        
        
          
            4
          
        
        
          
            9
          
        
        
          
            10
          
        
        
          
            11
          
        
        
          
            12
          
        
        
          
            13
          
        
        
          
            14
          
        
        
          
            0
          
        
        
          
            10
          
        
        
          
            20
          
        
        
          
            30
          
        
        
          
            40
          
        
        
          
            50
          
        
        
          
            1 2 3 4 5 6 7 8 9 10 11 12 13 14
          
        
        
          
            Excess grout take in micropiles (m
          
        
        
          
            3
          
        
        
          
            )
          
        
        
          
            Pile Number
          
        
        
          
            average
          
        
        
          
            95% upper limit
          
        
        
          Figure 6. Excess grout take in "micropile" holes; (a) as function of se-
        
        
          quence (2-6 weeks from grouting of fist to last pile); (b) accumulated
        
        
          values per pile location
        
        
          
            0
          
        
        
          
            2
          
        
        
          
            4
          
        
        
          
            6
          
        
        
          
            8
          
        
        
          
            10
          
        
        
          
            12
          
        
        
          
            14
          
        
        
          
            16
          
        
        
          
            P11
          
        
        
          
            P16
          
        
        
          
            P19
          
        
        
          
            P18
          
        
        
          
            P1
          
        
        
          
            P2
          
        
        
          
            P6
          
        
        
          
            P7
          
        
        
          
            P8
          
        
        
          
            P9
          
        
        
          
            P4
          
        
        
          
            P5
          
        
        
          
            P3
          
        
        
          
            P12
          
        
        
          
            P13
          
        
        
          
            P17
          
        
        
          
            P10
          
        
        
          
            P20
          
        
        
          
            P9 bis
          
        
        
          
            P15
          
        
        
          
            P14
          
        
        
          
            Excess grout take (m
          
        
        
          
            3
          
        
        
          
            )
          
        
        
          
            Primary grout hole
          
        
        
          
            average
          
        
        
          Figure 7. Excess grout take versus sequence for primary grout holes
        
        
          The actual sequence of the subsequent pressure grouting in pri-
        
        
          mary (Figure 7) and secondary (Figure 8) deviated slightly from
        
        
          the sequence in Figure 5 but followed the principal intent. The
        
        
          theoretical grout take was based on the nominal drilling diame-
        
        
          ters but with reference to the considerations for the piles and
        
        
          pre-drilling holes this may entail some 15% underestimation of
        
        
          take.
        
        
          As seen in Figure 7 and Figure 8 the excess grout take was
        
        
          very limited in the majority of holes.