 
          2795
        
        
          Characteristics Values in Rock Socket Design
        
        
          Valeurs caractéristiques d'ancrage sur roche
        
        
          Look B., Lacey D.
        
        
          
            Sinclair Knight Merz Pty Ltd, Australia
          
        
        
          ABSTRACT: The substructure of the Gateway Bridge comprises 1.5 metre diameter bored piers socketed into sedimentary rock.
        
        
          Characterisation of the rock strength properties, through goodness-of-fit tests, showed the use of non-normal distributions produced
        
        
          realistic characteristic strengths, while comparable predictions based on a Normal distribution showed unrealistically low values
        
        
          existed below the 20
        
        
          th
        
        
          percentile reliability.  Since limit state codes imply characteristic design strengths should be derived from
        
        
          conservative (low) percentile values, erroneous characteristic strength values may be produced due to an assumption of a Normal
        
        
          distribution. Two land based test piles fitted with Osterberg cells tested the sedimentary bedrock for shaft capacity at the bridge site,
        
        
          and “Characteristic” rock strengths required by various rock socket design methods to replicate observed pile shaft capacity have been
        
        
          back-calculated. This paper assumes that all considered design methods are equally “correct”, and compares the required design
        
        
          values (the selection of which are often subjective) to their relative location within the applied strength profile distributions.
        
        
          RÉSUMÉ : L'infrastructure du pont "Gateway Bridge" a des piliers forés de 1,5 mètre de diamètre ancrés dans de la roche
        
        
          sédimentaire.  La caractérisation des propriétés de résistance de la roche, faîte par le biais de test d'ajustement,  a montré que
        
        
          l'utilisation de loi non-normale a produit des caractéristiques de résistance plausibles alors que des prédictions comparables basées sur
        
        
          une loi normale pouvaient devenir artificiellement basses pour un degré de probabilité au 20ième centile. Certaines normes d' états
        
        
          limites suggèrent que les caractéristiques de résistance devraient être dérivées à partir de valeurs (au bas mot) de bas centile, des
        
        
          valeurs de caractéristiques de résistance erronées pouvant être calculées en assumant une loi normale. Deux piliers tests installés sur
        
        
          terre-sèche avec des cellules d'Osterberg ont été utilisés pour tester la capacité de la roche sédimentaire par rapport au pilier mais les
        
        
          valeurs de résistance caractéristique de roche nécessitées par les diverses conceptions d'ancrage sur roche ont été rétro-calculées afin
        
        
          de reproduire la capacité observée des piliers. Cet article assume que toutes les méthodes de conception considérées sont tout aussi
        
        
          "correctes" et dérive les valeurs caractéristiques de conception requises (la sélection desquels est souvent subjective) afin de
        
        
          reproduire les capacités observées des piliers durant des tests à grande échelle.
        
        
          KEYWORDS: Rock socket, bored piles, characteristic design value,  statistical distribution,  Osterberg pile tests, sedimentary rocks
        
        
          1 INTRODUCTION
        
        
          The Gateway Upgrade Project (GUP) was the largest road and
        
        
          bridge infrastructure project ever undertaken in Queensland,
        
        
          Australia. The six lane bridge structure spans 1.6 km between
        
        
          abutments with a main river span structure of 520 metres. This
        
        
          paper focuses on rock socket design procedures applied to two
        
        
          large-scale, land-based pile load tests conducted for this project.
        
        
          The rock founding conditions varied across the bridge
        
        
          footprint as summarised in Table 1. Characterisation of rock
        
        
          strength properties included the derivation of site-specific
        
        
          correlation of Point Load Index (I
        
        
          s(50)
        
        
          ) data with Uniaxial
        
        
          Compressive Strength (UCS) test results, and a statistical
        
        
          analysis of resulting datasets.
        
        
          The two test piles (TP1 and TP2) installed with Osterberg
        
        
          Cells were constructed to investigate the rock socket behaviour
        
        
          under high loads and identify any constructability issues prior to
        
        
          construction of the two river piers. This paper considers various
        
        
          accepted methods of pile rock socket design and compares their
        
        
          applicability to the load tests completed at this site.
        
        
          Rock socket design methods typically have similar
        
        
          formulations for the estimation of side shear capacity, but
        
        
          produce varying results due to their method of derivation, and
        
        
          the available data or tested rock types used for formulation.
        
        
          While the rock type may be a governing factor, this paper
        
        
          assumes that all the methods produce “correct” pile designs, but
        
        
          require varying “characteristic” design input values to produce
        
        
          equivalent results. Reliability theory implies a moderately
        
        
          conservative or cautious estimate should be used as the
        
        
          characteristic design value, yet without a statistical basis the
        
        
          selection of appropriate characteristic values remains subjective.
        
        
          Table 1. Background Data
        
        
          Location /
        
        
          Pier
        
        
          No. of Bored Piers
        
        
          Key Geological Issue within
        
        
          Rock Founding Layers
        
        
          Land 5 –
        
        
          Southern
        
        
          10
        
        
          (+ TP1)
        
        
          Dipping Coal seam layer within
        
        
          zone of influence of pier.
        
        
          River  6
        
        
          24
        
        
          River 7
        
        
          24
        
        
          Random Shear zones with
        
        
          varying length of piles
        
        
          Land 8 –
        
        
          Northern
        
        
          10
        
        
          (+ TP2)
        
        
          Uncertain and inconsistent data
        
        
          with possible weak zones
        
        
          1.1
        
        
          
            Background
          
        
        
          Whilst driven piles were used extensively across the GUP site,
        
        
          the river span of the Gateway Bridge is founded upon 1.5 metre
        
        
          diameter bored piers socketed into sedimentary rock. Piers 5
        
        
          and 8 are located on the riverbank while Piers 6 and 7 are
        
        
          located within the river.  River piers consisted of 24 piles that
        
        
          extended to a depth of over 50m below the river level, and each
        
        
          of the land based piers consisted of only 10 bored piers. Day et.
        
        
          al. (2009) provides further GUP foundation and project details.
        
        
          For the bridge foundation the key geological features were:
        
        
          o
        
        
          The basement rock consisted of Triassic aged material.
        
        
          This includes layers of sandstone, siltstone, mudstone and
        
        
          low grade coal formed about 220 to 180 million years ago.
        
        
          This material does not have any significant folding, but is
        
        
          known to have faulting as a consequence of crustal
        
        
          tension in the Tertiary period.
        
        
          o
        
        
          Deposition of Quaternary Alluvium occurred in the recent
        
        
          past. This site is located close to the mouth of the