 
          2780
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          Table 1 Construction activities and dates for Ceintuurbaan
        
        
          Construction activity
        
        
          End date
        
        
          Base monitoring start 2001
        
        
          2003-11-01
        
        
          Preliminary activities
        
        
          2007-04-01
        
        
          Excavation to NAP –6.2m
        
        
          2007-09-13
        
        
          Excavation to NAP –15.3 m
        
        
          2007-12-10
        
        
          Excavation to NAP –19.4 m
        
        
          2008-03-01
        
        
          Excavation to NAP –24 m
        
        
          2008-08-01
        
        
          Excavation to NAP –25.6 m,
        
        
          Floor construction, pumping test
        
        
          2009-06-24
        
        
          Figure 2 Cross section of Ceintuurbaan Station with soil profile and
        
        
          extensometer locations
        
        
          2 SURFACE DISPLACEMENTS
        
        
          In the Amsterdam deep excavations, the following construction
        
        
          effects contributed to the displacement of the ground surface:
        
        
          • Installation of diaphragm wall including preliminary
        
        
          activities
        
        
          • Excavation of the station box.
        
        
          Figure 3 shows the measurements of the ground surface for
        
        
          all three stations, Rokin, Vijzelgracht and Ceintuurbaan, for
        
        
          various stages of the excavation. It should be noted that the
        
        
          excavations had not finished at the time these measurements
        
        
          were taken and so the long term consolidation settlement is not
        
        
          completely included. The total period of the displacement
        
        
          measurements was over 6 years (from 2003-2009). For each
        
        
          stage, the excavation depth H is mentioned in the figures. From
        
        
          Figure 3 it is concluded that the settlement profile found in
        
        
          Amsterdam falls within the limit of Zone 1, as described by
        
        
          Peck (1969), with the ground surface displacement falling
        
        
          within 1% of the excavated depth.  The main displacements
        
        
          occur within 2 times the excavation depth as also suggested by
        
        
          Peck. More significant however is the effect of the excavation
        
        
          depth itself. In all three of the Amsterdam cases, the largest
        
        
          effect on the ground surface can be attributed to the preliminary
        
        
          activities, which took in total about 4 of the 6 year
        
        
          
            s
          
        
        
          presented.
        
        
          For each station, the average contribution of the preliminary
        
        
          activities to the surface displacements has been determined. The
        
        
          percentage of displacement caused by preliminary activities in
        
        
          2003-2007 compared to the overall displacement between 2003-
        
        
          2009 or 2003-2010 for Ceintuurbaan Station is 70%. For
        
        
          Vijzelgracht Station this is 55% and for Rokin Station 74%. The
        
        
          percentage at Vijzelgracht is influenced by some leakage
        
        
          incidents (Korff et al. 2011), showing a larger effect during the
        
        
          excavation period after 2007. The percentages for all the
        
        
          stations are somewhat higher than the actual values would be if
        
        
          the displacements at the end of construction (after 2012) had
        
        
          been taken into account, although additional displacements
        
        
          between 2009-2012 have been very small. Such a high
        
        
          percentage of the settlements caused by preliminary activities
        
        
          was also reported by Fernie et al. (2001) for a case study in
        
        
          London (Harrods). The deflection of the retaining wall in a top-
        
        
          down construction there caused only a small fraction of the
        
        
          overall ground movements. The installation of a contiguous
        
        
          piled wall of bentonite-cement caused up to 40% of the total
        
        
          movement.
        
        
          1st and 2nd
        
        
          sandlayers
        
        
          Eemclay
        
        
          Intermediate sandlayer
        
        
          Glacial clay
        
        
          3rd sandlayer
        
        
          Figure 3 Settlements normalized with excavation depth H, compared
        
        
          with envelopes by Peck (1969)
        
        
          Clough and O’Rourke (1990) evaluated the maximum
        
        
          displacement to be expected behind different types of retaining
        
        
          walls. In stiff clays, residual soils and sands the maximum
        
        
          ground displacement behind the wall is about 0.15% - 0.5% of
        
        
          the excavation depth, see Figure 4. The Amsterdam cases are
        
        
          plotted in a similar way in Figure 5.