 
          2095
        
        
          Comparative study of different deep excavation retaining systems
        
        
          Etude comparative de différents systèmes de soutènement de fouilles profondes
        
        
          J. Josifovski & S. Gjorgjevski
        
        
          Department for Geotechnics, Faculty of Civil Engineering-Skopje, University Ss. Cyril and Methodius - R. Macedonia
        
        
          ABSTRACT: In the past period a building expansion and rapid construction in highly urbanized city centre of Skopje (capital of the
        
        
          R. Macedonia) has been witnessed. In most cases the structures are small administrative buildings which do not exceed 800m
        
        
          2
        
        
          with
        
        
          underground often used for offices or parking. This has been an inspiration to investigate the comparative advantages of different
        
        
          deep excavation retaining systems. In fact three designer tasks, very similar by many parameters, had been used to draw the general
        
        
          conclusions. The selected construction sites are located closely to each other, thus share similar ground conditions. The following
        
        
          retaining systems were considered: (1) system of solder H piles with lagging, (2) reinforced concrete diaphragm wall, (3) secant pile
        
        
          wall with primary (reinforced concrete) and secondary (concrete) piles. Although systems are different in general they can still be
        
        
          compared, especially from the economic point of view. All retaining systems had been calculated numerically and controlled
        
        
          according to the Eurocode provisions. The concluding remarks offer a preferred solution for underground construction on narrow and
        
        
          build-up sites.
        
        
          RÉSUMÉ: Le centre-ville très urbanisée de Skopje (capitale de la république de Macédoine) a été témoin ces derniers temps de
        
        
          nombreuses constructions de bâtiments neufs. Dans la plupart des cas, ce sont de petits bâtiments administratifs qui ne dépassent pas
        
        
          800m
        
        
          2
        
        
          avec des sous-sols souvent utilisé pour des bureaux ou le parking. Cela a été l’occasion d’enquêter sur les avantages
        
        
          comparatifs des différents systèmes de soutènement de fouilles profondes. En fait, trois principes de soutènement, très semblables par
        
        
          de nombreux paramètres, ont été utilisés pour tirer des conclusions générales. Les chantiers de construction sélectionnés sont très
        
        
          proches les uns des autres avec des conditions de sol similaires. Les systèmes de soutènement suivants ont été considérés: (1) Système
        
        
          de poutres en H soudée après-coup, (2) paroi moulée en béton armé, (3) pieux sécants avec pieux primaire (béton armé) et secondaire
        
        
          (béton). Bien que les systèmes soient différents, en général, ils peuvent encore être comparés, en particulier du point de vue
        
        
          économique. Tous les systèmes de soutènement ont été calculés numériquement et contrôlés selon les dispositions Eurocode. Les
        
        
          conclusions offrent une solution pratique pour la construction souterraine en zone densément construite.
        
        
          KEYWORDS: deep excavation, retaining system, supporting elements, finite element analysis.
        
        
          1 INTRODUCTION
        
        
          The problem of deep excavation in highly urbanized area such
        
        
          as the city centre of Skopje has proved to be quite formidable
        
        
          engineering task. In particular the greater depth and the built-up
        
        
          surrounding make it especially difficult. The ever growing prize
        
        
          of a square meter has led to extensive utilization of the
        
        
          underground. Such an idea has been very attractive for the
        
        
          investors which always look for the most economic solution of
        
        
          the underground works, generally constrained by the excavation
        
        
          depth and retaining system.
        
        
          The tendency to optimize the structures has been an inspiration
        
        
          for the authors to investigate the comparative advantages of
        
        
          different deep excavation retaining systems and their supporting
        
        
          elements. The objective has been to offer a qualitative study
        
        
          which considers all relevant aspects of the underground
        
        
          construction in urban areas.
        
        
          The paper presents case studies of three different retaining
        
        
          systems used to secure the excavation pits which do not exceed
        
        
          800m
        
        
          2
        
        
          in base. All of them are located in the area of around
        
        
          2km, thus share similar ground conditions. There are different
        
        
          limitations and/or specifics on every site, as to the surrounding
        
        
          e.g. existing structures or very frequent streets. The depth of the
        
        
          excavation pit varies from 6.5 to 18m. All retaining systems had
        
        
          been calculated numerically and controlled according to the
        
        
          Eurocode provisions.
        
        
          1.1
        
        
          
            System of solder H piles with lagging
          
        
        
          In the first case example a 7m deep pit should be excavated for
        
        
          the construction of the new National theatre. Larger part of the
        
        
          structure has been already finished, only the part adjacent to the
        
        
          street is left to be erected. The excavation pit is rather narrow
        
        
          only 3.05m in width (enlarging to 6.1m) and 36.65m long, see
        
        
          Figure 1.
        
        
          Figure 1. Site location No.1 in front of the new National theatre.
        
        
          osi
        
        
          f
        
        
          ovski J., Gjorgjevski S.