 
          3374
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          occasions excess solar thermal energy can be stored in the
        
        
          ground.
        
        
          There is, however, one clear example of heat extraction
        
        
          visible in mid-October (Figure 6).  Here the central thermistor
        
        
          readings dip markedly to around 10
        
        
          o
        
        
          C on average.  The
        
        
          corresponding change in the mean outer thermistor readings is
        
        
          much smaller, indicating that much of the heat energy required
        
        
          has actually been extracted from that temporarily stored in the
        
        
          pile concrete, rather than from the surrounding ground.
        
        
          5 DISCUSSION
        
        
          An important aspect of pile heat exchanger behavior is
        
        
          illustrated by the data presented in Section 4. As has been
        
        
          shown theoretically by Loveridge, 2012, large diameter piles
        
        
          can take many days to reach a thermal steady state. Therefore,
        
        
          for a heating/cooling demand which is varying on an hourly (or
        
        
          less) timescale the pile concrete will rarely be at thermal steady
        
        
          state. This is illustrated in Figure 6, which shows that the
        
        
          temperature change near to the pile edge is significantly damped
        
        
          compared to that close to the U-tubes and some subsidiary
        
        
          peaks/troughs are not reflected at all. If the pile was at steady
        
        
          state, as is assumed by all traditional design methods, then the
        
        
          temperatures near the pile edge would reflect all the temperature
        
        
          changes at the pipes.
        
        
          This transient thermal behavior shown by the pile concrete
        
        
          is important for a number of reasons. First, if the pile is
        
        
          assumed to be at a thermal steady state then any ability of the
        
        
          pile concrete to store energy (rather than just transfer it to the
        
        
          ground) is being neglected.  As a consequence steady state
        
        
          design will either 1) overestimate the temperature change
        
        
          predicted at the pile-soil boundary for a given heat flux, or 2)
        
        
          underestimate the available thermal energy capacity for a given
        
        
          temperature change.  While this provides a safe conservative
        
        
          design it will significantly under-predict the thermal efficiency
        
        
          of the pile heat exchanger.
        
        
          Taking a transient view of the pile concrete behaviour also
        
        
          shows there to be a reduced risk of extreme temperatures
        
        
          developing in the ground. Current practice (eg NHBC 2010;
        
        
          SIA 2005) tends to recommend that the lower limit on the heat
        
        
          transfer fluid temperature in pile heat exchangers should be kept
        
        
          above freezing with a 2
        
        
          o
        
        
          C margin of error.  However, given that
        
        
          the largest dips in the central thermistor temperatures shown in
        
        
          Figure 6 are not reflected to the same degree in the temperature
        
        
          changes of the outer thermistors, this approach clearly would be
        
        
          conservative in this case.  This real behaviour is similar in
        
        
          nature to recent theoretical studies (Loveridge et al. 2012)
        
        
          which show that, for large diameter piles at least, temperatures
        
        
          lower than 0
        
        
          o
        
        
          C can be sustained within the heat transfer fluid
        
        
          for short periods and have no detrimental effects on the ground.
        
        
          Similar conclusions were reached by Brandl in his Rankine
        
        
          Lecture (Brandl 2006), but do not seem to have been acted upon
        
        
          in general practice.
        
        
          
            5.1 Further Work
          
        
        
          The data presented in this paper is the beginning of a long term
        
        
          monitoring programme.  The temperature data in the pile will
        
        
          subsequently be supplemented by energy data, both with respect
        
        
          to the heat transferred to the instrumented pile and for the
        
        
          balance of thermal energy between the different renewable
        
        
          energy systems in the building.  This is essential for fuller
        
        
          interpretation of the pile data and will allow linking of the
        
        
          energy demand and pile temperature changes. This will provide
        
        
          a valuable dataset for validation of pile heat exchanger thermal
        
        
          design methods.
        
        
          6 CONCLUSIONS
        
        
          Temperature sensors have been installed within a working
        
        
          foundation pile which is also used as a heat exchanger within a
        
        
          ground energy system.  Initial data from the pile is now
        
        
          available and demonstrates the transient nature of the heat
        
        
          transfer within the pile.  This is significant, as most existing
        
        
          design methods for the thermal capacity of piles assume that the
        
        
          pile is at a steady state. For large diameter piles such as the one
        
        
          instrumented in this scheme, this is clearly not the case.  Instead
        
        
          the largest fluctuations in temperature at the centre of the pile
        
        
          close to the pipe U-tubes are not reflected closer to the edge of
        
        
          the pile.  This is due to the thermal buffering provided by the
        
        
          pile concrete, which acts as a short term energy store during
        
        
          short duration peaks in thermal demand.
        
        
          The consequence of neglecting this short term concrete
        
        
          thermal storage is that design becomes over conservative and
        
        
          underestimates the thermal capacity of the pile.  It also leads to
        
        
          an over estimation of the risk of ground freezing for large
        
        
          diameter piles.
        
        
          7 ACKNOWLEDGEMENTS
        
        
          The authors would like to thank Joel Smethurst and Harvey
        
        
          Skinner for assistance with installing the thermistors and
        
        
          datalogger respectively.  The work would not have been
        
        
          possible without initial introductions and enthusiasm from Arup
        
        
          and Balfour Beatty Ground Engineering and subsequent support
        
        
          and commitment from Siemens Plc. We are also indebted to site
        
        
          support from ISG, Foundation Developments Ltd and
        
        
          Geothermal International Ltd.  This work forms part of a larger
        
        
          project funded by EPSRC (ref EP/H0490101/1) and supported
        
        
          by Mott MacDonald, Cementation Skanska, WJ Groundwater
        
        
          and Golder Associates.
        
        
          8 REFERENCES
        
        
          Amatya B.L., Soga K., Bourne-Webb P.J. and Laloui L. 2012: Thermo-
        
        
          mechanical performance of energy piles.
        
        
          
            Geotechnique
          
        
        
          62 (6), 503
        
        
          -519.
        
        
          Brandl H. 2006. Energy foundations and other thermo active ground
        
        
          structures.
        
        
          
            Geotechnique
          
        
        
          56 (2), 81 – 122.
        
        
          GSHPA 2012.
        
        
          
            Thermal pile design, installation and materials standard.
          
        
        
          Ground Source Heat Pump Association, Milton Keynes, October
        
        
          2012.
        
        
          Knellwolf C., Peron H. & Laloui L. 2011. Geotechnical analysis of heat
        
        
          exchanger piles.
        
        
          
            Journal of Geotechnical and Geoenvironmental
          
        
        
          
            Engineering 1
          
        
        
          37 (10), 890 - 902.
        
        
          Loveridge F. 2012.
        
        
          
            The Thermal Performance of Foundation Piles used
          
        
        
          
            as Heat Exchangers in Ground Energy System
          
        
        
          s. Doctoral Thesis,
        
        
          University of Southampton.
        
        
          Loveridge F. & Powrie W. 2012. Pile heat exchangers: thermal
        
        
          behaviour and interactions.
        
        
          
            Proceedings of the Institution of Civil
          
        
        
          
            Engineers Geotechnical Engineering.
          
        
        
          Available ahead of print at
        
        
        
          .
        
        
          Loveridge F., Amis T. and Powrie W. 2012. Energy Pile Performance
        
        
          and Preventing Ground Freezing.
        
        
          
            Proceedings of the 2012
          
        
        
          
            International Conference on Geomechanics and Engineering
          
        
        
          
            (ICGE’12)
          
        
        
          , Seoul, August, 2012.
        
        
          NHBC 2010.
        
        
          
            Efficient design of piled foundations for low rise housing,
          
        
        
          
            design guide.
          
        
        
          BC Foundation.
        
        
          Ouyang Y., Soga K. & Leung Y. F. 2011. Numerical back analysis of
        
        
          energy pile test at Lambeth College, London.
        
        
          
            Proc ASCE
          
        
        
          
            GeoFrontiers
          
        
        
          
            2011
          
        
        
          
            Conference
          
        
        
          ,
        
        
          Dallas,
        
        
          Texas,
        
        
        
          .
        
        
          SIA 2005.
        
        
          
            Utilisation de la chaleur du sol par des ouvrages de
          
        
        
          
            fondation et de soutènement en béton, Guide pour la conception, la
          
        
        
          
            réalisation et al maintenance.
          
        
        
          Swiss Society of Engineers and
        
        
          Architects, Documentation D 0190.