 
          3354
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          
            Proceedings of the 18
          
        
        
          
            th
          
        
        
          
            International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
          
        
        
          some distance from the excavation. This might reduce the draw-
        
        
          downs in the centre of the pit.
        
        
          The chosen groundwater lowering system consisted of a
        
        
          combination of well-points, bored wells and a drainage system
        
        
          beneath the membrane.
        
        
          The well-points were closely spaced at approx. 6 meters depth
        
        
          at the perimeter of the pit to deal with the groundwater flow in
        
        
          the upper layers of sand.
        
        
          In addition eight bored wells were placed at the perimeter to
        
        
          deal with the deeper water built-ups. Besides pumping from the
        
        
          wells vacuum was applied to the wells to reduce pore water
        
        
          pressures in the soil and increase the effective stresses in the
        
        
          soil, at least to some distance from the wells.
        
        
          Furthermore, a well in the centre of the pit was performed to
        
        
          prevent uplift. This well was initially installed with a pump, and
        
        
          during excavation the well was successively cut down to
        
        
          excavation level and the pump was removed.
        
        
          Before covering up the bottom and the sides with the
        
        
          membrane, a drainage system in connection with the (weeping)
        
        
          well was established in the bottom. To prevent a lifting problem
        
        
          caused by accumulation of water beneath the membrane,
        
        
          pumping on the drainage system was made possible by
        
        
          traditionally well pumps mounted through two installed pipes
        
        
          laid in inclining ditches up the sides.
        
        
          Pumping from the drainage system, the well-points and the
        
        
          bored wells at the perimeter of the pit was sustained until the pit
        
        
          was filled with water unto the measured highest natural ground
        
        
          water level approx. 1 meter below the surrounding level.
        
        
          4.3
        
        
          
            Soil handling
          
        
        
          The excavated soil had to be built-in in the embankments
        
        
          around the pit. The soil mainly consisted of clay, where
        
        
          moisturing/weathering normally must be avoided in order to
        
        
          obtain reasonable compaction (more than 95 % Standard
        
        
          Proctor) and confined deformations of the embankments.
        
        
          Therefore, the earth works must take place during a period with
        
        
          favourable weather conditions, which in Denmark means the
        
        
          summer period.
        
        
          Furthermore, the poor strength properties of the marine clay
        
        
          of high plasticity
        
        
          –
        
        
          especially in a remoulded condition - was
        
        
          dictating that the clay only had to be rebuilt in areas where the
        
        
          requirements to the soil were less critical.
        
        
          4.4
        
        
          
            Consequences of thermal influence to the soil
          
        
        
          In the operational phase the temperature in the adjacent soil will
        
        
          increase, maybe up to 90°C close to the pit. This heating of the
        
        
          soil might cause a drying-up effect of the soil above the ground
        
        
          water table if no water is added from e.g. precipitation. In the
        
        
          actual case the clays seemed so preconsolidated that the natural
        
        
          water content was considered to be close to the shrinkage limit.
        
        
          Consequently the risk of development of a long term
        
        
          deformation problem was evaluated as a minor issue.
        
        
          5 CONSTRUCTION PHASE
        
        
          The PTES was established during the summer 2011 which
        
        
          happened to be very wet with precipitation more than twice the
        
        
          normal precipitation. In addition, a cloudburst occurred with
        
        
          more than 100 mm precipitation overnight which caused
        
        
          damages to the just finished surfaces and obstacles for the
        
        
          subsequent works. Consequently, the construction period was
        
        
          delayed 3 months into the winter.
        
        
          This entailed that the preconditions for the project was
        
        
          severely challenged. Especially the maintenance of the stability
        
        
          of the sides was alarming. The predicted long term problem
        
        
          with poor drained strength parameter might be worsened if the
        
        
          efficiency of the ground water lowering system was reduced
        
        
          (due to clogging etc.). This problem period was not to end until
        
        
          the filling-in of water was above the surrounding ground level.
        
        
          In spite of this no severe ruptures were recorded. Figure 6
        
        
          shows a photo of the pit at a late stage of the excavation work.
        
        
          Figure 6. Photo of pit during completion of excavation and laying out of
        
        
          the membrane in progress. The tower in the centre of the photo is a 16
        
        
          m tall water in- and outlet for the operational phase of the PTES.
        
        
          6 CONCLUSIONS AND PERSPECTIVES
        
        
          The PTES project in Marstal has demonstrated that a thermal
        
        
          energy storage with 75,000 m
        
        
          3
        
        
          water is obtainable in connection
        
        
          with solar heat based district heating systems. The construction
        
        
          cost of the Marstal storage was 41
        
        
          € per
        
        
          m
        
        
          3
        
        
          of water (exclusive
        
        
          VAT) including all pipe connection to the plant, control system,
        
        
          geotechnical support, etc. The construction cost also includes
        
        
          research and development costs of the storage and different lid
        
        
          designs. The costs are cost-competitive compared to other
        
        
          storage systems (e.g. TTES, ATES and BTES) and there is a
        
        
          potential to bring the costs further down.
        
        
          The project has encountered difficulties in matters of soil and
        
        
          ground water conditions and challenges due to circumstances in
        
        
          the actual climate, but these challenges has been dealt with in
        
        
          order to minimize the costs of the PTES. Details in the project
        
        
          still needs to be optimized, but the project is a stepping stone in
        
        
          the development of the necessary techniques for decreasing the
        
        
          use of renewable energies.
        
        
          The aim of the authors of this article is to pinpoint the
        
        
          challanges to be encountered during planning and execution of a
        
        
          PTES illustrated by an actual project.
        
        
          It is the authors’
        
        
          perception that a PTES is applicable for a lot of sites.
        
        
          Denmark has approximately 400 district heating plants of
        
        
          varying size. Most of these plants are placed in rural areas,
        
        
          where establishment of solar heating plants supplemented by a
        
        
          PTES is an obvious solution. As an example the planning of a
        
        
          60,000 m
        
        
          3
        
        
          PTES in connection with 35,000 m
        
        
          2
        
        
          solar heat panels
        
        
          at Dronninglund Destrict Heating in Denmark is ongoing and
        
        
          will presumable be established in 2013 - 2014. Some
        
        
          PTES’s
        
        
          have been established in other countries, e.g. Germany, but
        
        
          none as large as in Denmark.
        
        
          7 REFERENCES
        
        
          GEO Danish Geotechnical Institute 2010-2011. Geotechnical reports for
        
        
          establishment of a PTES in Marstal (not published).
        
        
          Mangold D, Schmidt T, The next Generations of Seasonal Thermal
        
        
          Energy Storage in Germany,
        
        
        
        
          Marstal District Heating 2010-2012. Monthly solar heat production and
        
        
          radiation,
        
        
        
          .
        
        
          Verein Deutscher Ingenieure 2004, 4640 Blatt 4.