 
          3353
        
        
          Technical Committee 307 + 212 /
        
        
          
            Comité technique 307 + 212
          
        
        
          
            Proceedings of the 18
          
        
        
          
            th
          
        
        
          
            International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
          
        
        
          excavated pit. The excavated soil must be well suited and
        
        
          compactable for this purpose.
        
        
          3 CONSTRUCTION AND SITE INVESTIGATIONS
        
        
          In Marstal the PTES is placed on the top of a smooth hill in the
        
        
          outskirts of the town.
        
        
          Due to area restraints the pit is slightly rectangular and
        
        
          measures 88 meters by 113 meters at the top, i.e. a bit larger
        
        
          than a football field. The water depth is 16 meters, of which
        
        
          approx. 12 meters go below the natural ground level and 4
        
        
          meters are established by embankments of the excavated soil at
        
        
          the perimeter. As mentioned above the total volume of water is
        
        
          75,000 m
        
        
          3
        
        
          .
        
        
          Early in the design process the slope of the sides was chosen
        
        
          to 1:2 which in a practically view is the steepest possible
        
        
          inclination for the installation works of the liner. This
        
        
          corresponds to an angle of 26.6° against horizontal level. Figure
        
        
          4 shows a stylized cross section of the pit.
        
        
          Figure 4. Stylized cross section of the PTES in Marstal.
        
        
          A site investigation has been performed prior to the design
        
        
          phase. The investigation consisted of 10 borings, of which two
        
        
          borings in the centre were taken to 25 meters depth and 8
        
        
          borings at the perimeter of the excavation were taken to 13
        
        
          meters depth. The borings were performed as traditionally
        
        
          geotechnical borings with soil sampling, in-situ tests and
        
        
          installation of standpipes at adequate depths.
        
        
          The investigation showed a thin layer of top soil covering
        
        
          various glacial deposits of primarily clay till and glacially
        
        
          relocated marine clay of interglacial origin (Cyprina Clay). At
        
        
          the northern side three meters of melt water sand were covering
        
        
          the clay. Besides, stripes and zones of melt water sand and sand
        
        
          till were found, apparently randomly in the clay.
        
        
          In a geotechnical matter the marine clay was of special
        
        
          interest. The clay was of high to very high plasticity with
        
        
          plasticity index I
        
        
          P
        
        
          ≈
        
        
          50 %. The natural water content was w
        
        
          nat
        
        
          =
        
        
          21
        
        
          –
        
        
          30 % close to the plasticity limit. A fissured structure was
        
        
          detected in several samples, presumably caused by shear
        
        
          stresses during the glacial period and/or passive earth pressures
        
        
          at the end of the glacial period.
        
        
          The clay deposits were generally stiff to very stiff. Field vane
        
        
          tests showed undrained shear strength c
        
        
          fv
        
        
          between 250 and >700
        
        
          kPa, thus with a slightly softened zone near the surface.
        
        
          The effective strength parameters in the clay were estimated
        
        
          from a priori knowledge of similar soils. The characteristic
        
        
          value of the angle of friction of the marine clay was estimated to
        
        
          φ ≈ 20° and of the clay till to φ ≈ 30°
        
        
          with mean values
        
        
          approximately 5 degrees higher. Some effective cohesion in the
        
        
          clay must be expected, but according to Danish calculation
        
        
          practice
        
        
          the cohesion was limited to c’ = 20 kPa in unfissured
        
        
          clay and c’ = 0 kPa in fissured
        
        
          clay (on the safe side for
        
        
          decreasing stress level).
        
        
          Standpipes had been installed at differing depths, separated by
        
        
          bentonite sealing materials. Groundwater levels were measured
        
        
          at very varying depths between a few meters depth and large
        
        
          depth (below excavation level). These measurements are
        
        
          assumed to be variably ground water build-ups depending on
        
        
          precipitation and season, whereas a stable ground water table in
        
        
          a primary aquifer is at large depth.
        
        
          4 CONSIDERATIONS FOR THE CONSTRUCTION
        
        
          Establishment of a PTES at the actual site was subject to four
        
        
          geotechnical concerns: the excavation stability, the groundwater
        
        
          and soil handling during the construction phase and the long
        
        
          term consequences of thermal influence on deformations in the
        
        
          operational phase.
        
        
          4.1
        
        
          
            Excavation stability
          
        
        
          The stability of the excavation sides was to be sufficient during
        
        
          the construction phase. Provided that the ground water issue
        
        
          was handled, it was evident that a quickly performed excavation
        
        
          and refilling with water would be advisable as the clay would be
        
        
          stable in the short term undrained condition. On the other hand,
        
        
          calculations based on long term drained strength parameters
        
        
          showed unstable slopes in the marine clay, especially when
        
        
          adding prescribed safety factors according to Eurocode 7.
        
        
          The period from starting excavation until fully filling the pit
        
        
          with water was planned to last 6½ months. One month had to be
        
        
          reserved the liner work, and as the available capacity for filling
        
        
          the pit with water was limited to 50 m
        
        
          3
        
        
          /h the filling would itself
        
        
          take two months.
        
        
          Undrained conditions were evaluated to last at least one
        
        
          month, but exceeding this period by several months caused
        
        
          severe considerations of the time for developing drained
        
        
          conditions and consequently collapses due to unstable slopes. It
        
        
          was evaluated that further tests and evaluations would not
        
        
          improve this engineering judgement significantly, and therefore
        
        
          the stability had to be evaluated for drained conditions.
        
        
          Introducing less steep slopes than 1:2 was not an option, but a
        
        
          series of slope stability calculations based on different cross
        
        
          sections showed that it was possible to establish stable slopes of
        
        
          1:2 by replacing layers of the marine clay until certain depths
        
        
          with sand or even clay till, see figure 5, forcing the rupture line
        
        
          at greater depth to involve more stable materials. The
        
        
          replacement of the marine clay would increase the volume of
        
        
          soil to be handled in the project by approximately 15 % which
        
        
          was acceptable.
        
        
          During the excavation phase it was decided to abstain from
        
        
          replacements until indications of failures were observed. This
        
        
          reduced replacements to an absolute minimum.
        
        
          Figure 5. Example of slope calculations.
        
        
          4.2
        
        
          
            Groundwater handling
          
        
        
          The potential energy loss due to groundwater flow across the
        
        
          site was evaluated to be very limited.
        
        
          The groundwater build-ups had to be eliminated to enable dry
        
        
          excavation and a proper handling of the membrane.
        
        
          Furthermore groundwater lowering was necessary to prevent
        
        
          uplift, damages due to seepage from the excavation sides and
        
        
          sliding of the sides, which especially would be problematic if
        
        
          the sides were sliding after covering with the membrane.
        
        
          The circumstance that the bottom of the pit was to be covered
        
        
          with a membrane implied that the groundwater lowering works
        
        
          was directed to take place on the outer side of the pit, i.e. at
        
        
          Slope 1:2
        
        
          Water
        
        
          Triangle of removed
        
        
          clay of high plasticity
        
        
          Rupture line
        
        
          Fill
        
        
          Sand
        
        
          Marine clay
        
        
          Clay till
        
        
          Natural ground level
        
        
          Insulated lid