 
          2718
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          5
        
        
          LOAD TESTS OF INDIVIDUAL PILES.
        
        
          In order to verify the design assumptions as well as to meet
        
        
          general recommendations regarding pile foundations, the
        
        
          bearing capacity of piles was investigated by static load tests.
        
        
          Due to importance of the construction as well as from the
        
        
          design assumptions, the load tests program was extended (after
        
        
          the agreement of the designer and investor). In order to examine
        
        
          the effectiveness of the pile base improvement by injection as
        
        
          well to control its quality, one of piles designated for testing
        
        
          was installed without the injection. Additionally, in three of the
        
        
          test piles, extensometer measuring system to control the
        
        
          distribution of force along the pile was installed. The goal of
        
        
          these measurements was to investigate the distribution of load
        
        
          transmitted by the pile shaft and base. It is also useful to assess
        
        
          the force generated at the pile base due to injection.
        
        
          Additionally, extensometer measurements were planned for the
        
        
          case of unfavorable bearing capacity test results. The
        
        
          measurement results would be useful for the analysis of the
        
        
          reasons of too low bearing capacity (shaft of pile or its base).
        
        
          The extensometers were installed at seven levels distributed
        
        
          along the pile length.
        
        
          0
        
        
          5
        
        
          10
        
        
          15
        
        
          20
        
        
          25
        
        
          30
        
        
          35
        
        
          0
        
        
          2000
        
        
          4000
        
        
          6000
        
        
          8000
        
        
          10000
        
        
          12000
        
        
          Q [kN]
        
        
          s [mm]
        
        
          Piles No62, 71, 74
        
        
          (with base injection)
        
        
          Pile No 99
        
        
          (without base injection)
        
        
          Figure 7:
        
        
          Pile load test results
        
        
          Pile load tests were carried out according to the standard
        
        
          procedure i.e. to the maximum force
        
        
          Q
        
        
          max
        
        
          = 11000 kN with
        
        
          intermediate unloading at the force
        
        
          Q
        
        
          1
        
        
          =
        
        
          Q
        
        
          r
        
        
          = 7400 kN. The
        
        
          results of load tests confirmed the need of extended measuring
        
        
          program. The gained information proved the safety of the
        
        
          current and future foundation work. The important observation
        
        
          was proper work of the piles with injection and their advantage
        
        
          over the pile without base improvement. It is well visible in
        
        
          Fig. 7 where respective load-settlement curves are shown. The
        
        
          results of extensometric measurements in the form of
        
        
          distribution of force along the piles are shown in Fig. 8. They
        
        
          allowed for the examination of the work of the piles in the
        
        
          existing soil conditions. The essential portion of force was
        
        
          transmitted by the pile shaft what corresponded to the assumed
        
        
          concept of piles in the raft foundation system.
        
        
          Figure 8:
        
        
          Distribution of forces along the pile form the
        
        
          extensometric measurements.
        
        
          6
        
        
          FIELD MEASUREMENTS
        
        
          After piling and pylon slab construction, six benchmarks
        
        
          were placed on the slab surface in characteristic points (see
        
        
          figure X). Since 11.09.2009 till now the vertical displacements
        
        
          of foundation are geodetically monitored. After every stage of
        
        
          bridge loading vertical displacement were measured. Currently
        
        
          bridge is fully loaded, and settlements are in a stabilisation
        
        
          phase. Good agreement between measured displacements and
        
        
          numerical analysis results is observed (see Fig. 9).
        
        
          Figure 9:
        
        
          Settlements of foundation slab measured in 6 points in
        
        
          different phases of pylon loading.
        
        
          7
        
        
          SUMMARY
        
        
          In the paper analysis of the raft foundation supporting the
        
        
          pylon of cable-stayed bridge in Rędzin being the part of
        
        
          Wrocław motorway A8 ring is briefly presented. Important
        
        
          decision related to the selection of the pile length was their
        
        
          shortening due to occurrence of confined aquifers which would
        
        
          cause the liquefaction of soils under the pile bases during
        
        
          installation. The decision could be undertaken after
        
        
          comprehensive numerical analyses as well as additional, non-
        
        
          standard investigations of soil parameters. Load tests with the
        
        
          measurement of the distribution of force along the piles with
        
        
          extensometers were very useful, allowing the control of design
        
        
          assumptions. The field measurements and their agreement with
        
        
          numerical analyses results are the best proof that assumptions
        
        
          made in the design process were correct.
        
        
          8
        
        
          REFERENCES
        
        
          Atkinson, J.H.
        
        
          Non-linear Soil Stiffness in Routine Design
        
        
          , 40
        
        
          th
        
        
          Rankin
        
        
          Lecture, “Geotechnique”, 2000, vol. 50 No. 5, 487-508.
        
        
          Geological report (1), A-8 Motorway, AOW, GeoTech Ltd. Rzeszów
        
        
          2006, (in Polish).
        
        
          Kosecki M.:
        
        
          Static of piling structures
        
        
          , PZTB Szczecin branch, 2006,
        
        
          (in Polish).
        
        
          Elaboration the way of foundation of the P14 support of cable-stayed
        
        
          bridge pylon in the motorway ring (A8) over the Odra river in
        
        
          Wrocław
        
        
          , Geosyntex Ltd., Gdynia 2008, (in Polish).
        
        
          Santos, J.A, Correia A.G.:
        
        
          Reference Threshold Shear Strain of Soils, Its
        
        
          Application to obtain a Unique Strain-Dependent Shear Modulus
        
        
          Curve for soil.
        
        
          Proc. The 15
        
        
          th
        
        
          Int. Conf. On Soil Mech and Geot.
        
        
          Eng., Instanbul, 2000, vol. 1, 267-270.
        
        
          Geological report (2) on the geotechnical and laboratory investigations
        
        
          under the pylon and permanent supports for construction of cable-
        
        
          stayed bridge over the Odra River in Wroclaw, Geoteko - Design
        
        
          and Geotechnical Consulting Ltd., Warszawa, 2008, (in Polish).
        
        
          5
        
        
          LOAD TESTS OF INDIVIDUAL PILES.
        
        
          In order to verify the design assumptions as well as to meet
        
        
          general recommendations regarding pile foundations, the
        
        
          bearing capacity of piles was investigated by static load tests.
        
        
          Due to importance of the construction as well as from the
        
        
          design assumptions, the load tests program was extended (after
        
        
          the agreement of the designer and investor). In order to examine
        
        
          the effectiveness of the pile base improvement by injection as
        
        
          well to control its quality, one of piles designated for testing
        
        
          was installed without the injection. Additionally, in three of the
        
        
          test piles, extensometer measuring system to control the
        
        
          distribution of force along the pile was installed. The goal of
        
        
          these measurements was to investigate the distribution of load
        
        
          transmitted by the pile shaft and base. It is also useful to assess
        
        
          the force generated at the pile base due to injection.
        
        
          Additionally, extensometer measurements were planned for the
        
        
          case of unfavorable bearing capacity test results. The
        
        
          measurement results would be useful for the analysis of the
        
        
          reasons of too low bearing capacity (shaft of pile or its base).
        
        
          The extensometers were installed at seven levels distributed
        
        
          along the pile length.
        
        
          0
        
        
          5
        
        
          10
        
        
          15
        
        
          20
        
        
          25
        
        
          30
        
        
          35
        
        
          0
        
        
          2000
        
        
          4000
        
        
          6000
        
        
          8000
        
        
          10000
        
        
          12000
        
        
          Q [kN]
        
        
          s [mm]
        
        
          Piles No62, 71, 74
        
        
          (with base injection)
        
        
          Pile No 99
        
        
          (without base injection)
        
        
          Figure 7:
        
        
          Pile load test results
        
        
          Pile load tests were carried out according to the standard
        
        
          procedure i.e. to the maximum force
        
        
          Q
        
        
          max
        
        
          = 11000 kN with
        
        
          intermediate unloading at the force
        
        
          Q
        
        
          1
        
        
          =
        
        
          Q
        
        
          r
        
        
          = 7400 kN. he
        
        
          results of load tests confirmed the need of extended measuring
        
        
          program. The gained information proved the safety of the
        
        
          current and future foundation work. The important observation
        
        
          was proper work of the piles with injection and their advantage
        
        
          over the pile without base improvement. It is well visible in
        
        
          Fig. 7 where respective load-settlement curves are shown. The
        
        
          results of extensometric measurements in the form of
        
        
          distribution of force along the piles are shown in Fig. 8. They
        
        
          allowed for the examination of the work of the piles in the
        
        
          existing soil conditions. The essential portion of force was
        
        
          transmitted by the pile shaft what corresponded to the assumed
        
        
          concept of piles in the raft foundation system.
        
        
          Figure 8:
        
        
          Distribution of forces along the pile form the
        
        
          extensometric measurements.
        
        
          6
        
        
          FIELD MEASUREMENTS
        
        
          After piling and pylon slab construction, six benchmarks
        
        
          were placed on the slab surface in characteristic points (see
        
        
          figure X). Since 11.09.2009 till now the vertical displacements
        
        
          of foundation are geodetically monitored. After every stage of
        
        
          bridge loading vertical displacement were measured. Currently
        
        
          bridge is fully loaded, and settlements are in a stabilisation
        
        
          phase. Good agreement between measured displacements and
        
        
          numerical analysis results is observed (see Fig. 9).
        
        
          Figure 9:
        
        
          Settlements of foundation slab measured in 6 points in
        
        
          different phases of pylon loading.
        
        
          7
        
        
          SUMMARY
        
        
          In the paper analysis of the raft foundation supporting the
        
        
          pylon of cable-stayed bridge in Rędzin being the part of
        
        
          Wrocław motorway A8 ring is briefly presented. Important
        
        
          decision related to the selection of the pile length was their
        
        
          shortening due to occurrence of confined aquifers which would
        
        
          cause the liquefaction of soils under the pile bases during
        
        
          installation. The decision could be undertaken after
        
        
          comprehensive numerical analyses as well as additional, non-
        
        
          standard investigations of soil parameters. Load tests with the
        
        
          measurement of the distribution of force along the piles with
        
        
          extensometers were very useful, allowing the control of design
        
        
          assumptions. The field measurements and their agreement with
        
        
          numerical analyses results are the best proof that assumptions
        
        
          made in the design process were correct.
        
        
          8
        
        
          REFERENCES
        
        
          Atkinson, J.H.
        
        
          Non-linear Soil Stiffness in Routin Design
        
        
          , 40
        
        
          th
        
        
          Rank
        
        
          Lecture, “ technique”, 2000, vol. 50 No. 5, 487-508.
        
        
          Geological report (1), A-8 Motorway, AOW, GeoTech Ltd. Rze zów
        
        
          2006, (in Polish).
        
        
          Kosecki M.:
        
        
          Stat c of piling structures
        
        
          , PZTB Szczecin branch, 2006,
        
        
          (i Poli h).
        
        
          Elab ration the way f foundation of the P14 support of cable-stayed
        
        
          bridge pylon i the motorway ring (A8) over the Odra river in
        
        
          Wrocław
        
        
          , G osyntex Ltd., Gdynia 2008, (in Polish).
        
        
          Santos, J.A, Corre a A.G.:
        
        
          Reference Threshold Shear Strain f Soils, Its
        
        
          Application to obtain a Unique Strain-Dependent Shear Modulus
        
        
          Curve for soil.
        
        
          Proc. The 15
        
        
          th
        
        
          Int. Conf. On Soil Mech and Geot.
        
        
          Eng., Instanbul, 2000, vol. 1, 267-270.
        
        
          Geological report (2) on the geotechnical and laboratory investigations
        
        
          under the pylon and permanent supports for construction of cable-
        
        
          stayed bridge over the Odra River in Wroclaw, Geoteko - Design
        
        
          distribution of force along the pile was installed. The goal of
        
        
          these measurements was to investigate the distribution of load
        
        
          transmitted by the pile shaft and base. It is also useful to assess
        
        
          the force generated at the pile base due to injection.
        
        
          Additionally, extensometer measurements were planned for the
        
        
          case of unfavorable bearing capacity test results. The
        
        
          measurement results would be useful for the analysis of the
        
        
          reasons of too low bearing capacity (shaft of pile or its base).
        
        
          The extensometers were installed at seven levels distributed
        
        
          along the pile length.
        
        
          0
        
        
          5
        
        
          10
        
        
          15
        
        
          20
        
        
          25
        
        
          30
        
        
          35
        
        
          0
        
        
          2000
        
        
          4000
        
        
          6000
        
        
          8000
        
        
          10000
        
        
          12000
        
        
          Q [kN]
        
        
          s [mm]
        
        
          Piles No62, 71, 74
        
        
          (with base injection)
        
        
          Pile No 99
        
        
          (without base injection)
        
        
          Figure 7:
        
        
          Pile load test results
        
        
          Pile load tests were carried ut accordin to the standard
        
        
          procedure i.e. to the maximum force
        
        
          Q
        
        
          max
        
        
          = 11000 kN with
        
        
          intermediate unloading at th for e
        
        
          Q
        
        
          1
        
        
          =
        
        
          Q
        
        
          r
        
        
          = 7400 kN.
        
        
          re ults of load tests confirmed the need f exten ed measuring
        
        
          program. Th gained i f rmation proved the safety of the
        
        
          current a futur foundation work. Th important ob e vation
        
        
          was prop r work of the piles with injection and their advantage
        
        
          over the pile without base improve ent. It is well visible in
        
        
          Fig. 7 where respective load-settlement curves are shown.
        
        
          results of extensometric m asurements in the form of
        
        
          distribution f f rce along the piles are shown in Fig. 8. Th y
        
        
          allowed for the examination of the work of th piles in the
        
        
          existing soil conditions. The essential portion of force was
        
        
          transmitted by the pile shaft what corresponded to the assumed
        
        
          concept of piles in the raft foundation system.
        
        
          Figure 8:
        
        
          Distribution of forces along the pile form the
        
        
          extensometric measurem nts.
        
        
          figure X). Since 11.09.2009 till now the vertical displacements
        
        
          of foundation are geodetically monitored. After every stage of
        
        
          bridge loading vertical displacement were measured. Currently
        
        
          bridge is fully loaded, and settlements are in a stabilisation
        
        
          phase. Good agreement between meas red displacements and
        
        
          numeric l analysis results i observed (see Fig. 9).
        
        
          Figure 9:
        
        
          Settlements of foundation slab measured in 6 points in
        
        
          different phases of pylon loading.
        
        
          7
        
        
          SUMMARY
        
        
          In the paper analysis of the raft foundation supporting the
        
        
          pylon of cable-stayed bridge in Rędzin being the part of
        
        
          Wrocław motorway A8 ring is briefly presented. Important
        
        
          decision related to the selection of the pile length was their
        
        
          shortening due to occurrence of confined aquifers which would
        
        
          cause the liquefaction of soils under the pile bases during
        
        
          installation. The decision c uld be undertaken after
        
        
          comprehensive numerical nalyses as well as additional, non-
        
        
          standard investiga ons of soil paramet s. Load t sts with he
        
        
          measurement of the istribution of force along the pile with
        
        
          extensometers w re very useful, allowing the control of design
        
        
          assumptions. The fi ld measurements and their agreement with
        
        
          numerical analyses results are the best proof that assumptions
        
        
          mad in the design process were correct.
        
        
          8
        
        
          REFERENCES
        
        
          Atkinson, J.H.
        
        
          Non-linear Soil Stiffness in Routine Design
        
        
          , 40
        
        
          th
        
        
          Rankin
        
        
          Lecture, “Geotechnique”, 2000, vol. 50 No. 5, 487-508.
        
        
          Geological report (1), A-8 Motorway, AOW, GeoTech Ltd. Rzeszów
        
        
          2006, (in Polish).
        
        
          Kosecki M.:
        
        
          Static of piling structures
        
        
          , PZTB Szczecin branch, 2006,
        
        
          (in Polish).
        
        
          Elaboration the way of foundation of the P14 support of cable-stayed
        
        
          bridge pylon in the motorway ring (A8) over the Odra river in
        
        
          Wrocław
        
        
          , Geosyntex Ltd., Gdynia 2008, (in Polish).
        
        
          Santos, J.A, Correia A.G.:
        
        
          Reference Threshold Shear St ain of Soils, Its
        
        
          Application to obtain  U ique Str in-Dependent Shear Modulus
        
        
          Curve for soil.
        
        
          Proc. The 15
        
        
          th
        
        
          Int. Conf. On Soil Mech and Geot.
        
        
          Eng., Instanbul, 2000, vol. 1, 267-270.
        
        
          Geological report (2) on the geotechnical and laboratory investigations
        
        
          under the pylon and permanent supports for construction of cable-
        
        
          stayed bridge over the Odra River in Wroclaw, Geoteko - Design
        
        
          nd Geotechnical Consulting Ltd., Warszawa, 2008, (in Polish).