 
          3044
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          Key design considerations and aspects of the design and life
        
        
          cycle of the PRBs included the panel and gate widths, reactive
        
        
          media and treatment process, hydrogeology, contaminant
        
        
          distribution, geochemistry; reaction kinetics and residence time;
        
        
          and installation methods. The ratio of panel width to gate width
        
        
          was selected as 6:1 following groundwater modelling of flows
        
        
          and residence times through the gates.
        
        
          Table 1. Summary of Selected Remediation Options
        
        
          Contamination Issue
        
        
          Preferred
        
        
          Remediation
        
        
          Option
        
        
          Second
        
        
          Ranked
        
        
          Option
        
        
          Third
        
        
          Ranked
        
        
          Option
        
        
          Pond 5/7 tar waste
        
        
          Barrier Wall
        
        
          Permeable
        
        
          Reactive
        
        
          Barrier
        
        
          Cap and
        
        
          Monitor
        
        
          Lead Dust /
        
        
          Asbestos
        
        
          Permeable
        
        
          Reactive
        
        
          Barrier
        
        
          Barrier Wall
        
        
          Interception
        
        
          Drain and
        
        
          Monitor
        
        
          Free Phase LNAPL
        
        
          Multi Phase
        
        
          Extraction
        
        
          Pump and
        
        
          Treat
        
        
          Barrier Wall
        
        
          Fines Disposal
        
        
          Facility
        
        
          Permeable
        
        
          Reactive
        
        
          Barrier
        
        
          Cap and
        
        
          Monitor
        
        
          Interception
        
        
          Drain and
        
        
          Monitor
        
        
          Manganese Dioxide
        
        
          area (EMD) -
        
        
          Dredging Phase
        
        
          Liner (GCL)
        
        
          prior to
        
        
          dredging
        
        
          Barrier Wall
        
        
          Interception
        
        
          Drain and
        
        
          Monitor
        
        
          It is also proposed to extend the wall as a continuous low-
        
        
          permeability barrier to the west, adjacent to a surface water
        
        
          body now as Deep Pond to protect the wetlands to the west and
        
        
          north from the saline water during dredging.
        
        
          
            5.4 Free Phase Hydrocarbon Area
          
        
        
          The preferred remediation option for the free-phase LNAPL
        
        
          contamination is multi-phase extraction (MPE). MPE is an in-
        
        
          situ remediation technology for simultaneous extraction of
        
        
          vapour phase, dissolved phase and separate phase (e.g. LNAPL)
        
        
          contaminants from the vadose zone, capillary fringe, and
        
        
          saturated zone soils and groundwater. It will likely be followed
        
        
          by monitored natural attenuation (MNA) for residual dissolved
        
        
          phase hydrocarbon contamination.
        
        
          
            5.5 Manganese Dioxide Waste Area
          
        
        
          
            5.2 Tar Waste Ponds
          
        
        
          The soil-bentonite barrier wall enclosing the Pond 5/7 tar waste
        
        
          would be approximately 1 km long and 10 m deep, keyed into
        
        
          the clay aquitard. The design of the wall will take into account
        
        
          the hydraulic conditions of the contained volume under initial
        
        
          loading (especially preload), which would be a one-off event
        
        
          during construction. Key design issues for the barrier wall were:
        
        
          The preferred remediation option to manage risks associated
        
        
          with dredging activities within the manganese dioxide waste site
        
        
          is to install a low-permeability geo-synthetic clay liner (GCL)
        
        
          over the site prior to dredging.
        
        
          An overall plan showing the location and extent of the
        
        
          preferred remediation options is presented in Figure 3.
        
        
          
        
        
          Pre-trenching through the existing slag cell walls and other
        
        
          cemented layers in the fill for slurry trench construction;
        
        
          
        
        
          Mix Design of the bentonite slurry, including compatibility
        
        
          with site groundwater and soil conditions;
        
        
          
        
        
          Mix design of the soil-bentonite backfill, including
        
        
          compatibility with site groundwater and soil conditions;
        
        
          
        
        
          Global and local stability of the slurry trench;
        
        
          
        
        
          Density and viscosity of the slurry and backfill materials,
        
        
          such that trench stability is maintained, while permitting the
        
        
          backfill to displace the slurry; and
        
        
          
        
        
          Provision of vertical drainage (e.g. wick drains or sand
        
        
          drains) internal to the enclosed barrier wall to control pore
        
        
          pressures generated during preloading.
        
        
          Figure 3. Remediation Plan.
        
        
          6 CONCLUSIONS
        
        
          
            5.3 Asbestos / Lead Area and Fines Disposal Facility
          
        
        
          The ‘precautionary principle’ was applied to the potential risk
        
        
          resulting from the asbestos/lead dust area. The permeable
        
        
          reactive barrier (PRB) would be designed to maintain northerly
        
        
          groundwater flows while ‘treating’ lead leachate in the event
        
        
          that lead dust comes into contact with the groundwater.
        
        
          The PRB at the fines disposal facility would also be designed
        
        
          to maintain northerly groundwater flows while ‘treating’
        
        
          leachate potentially generated by dredged sediments coming
        
        
          into contact with the groundwater. The target contaminants are
        
        
          metals (mainly aluminium) and PAH.
        
        
          The two PRBs will be a ‘funnel and gate’ type comprising
        
        
          ‘gates’ of reactive medium with intervening panels of
        
        
          impermeable barrier wall. This system allows for more
        
        
          convenient maintenance and, if needed, replenishment of the
        
        
          reactive media. The Operational Environmental Management
        
        
          Plan for the terminal will incorporate regular monitoring and
        
        
          maintenance of the reactive media.
        
        
          The Terminal 4 Project is planned to be constructed at a site that
        
        
          presents complex geotechnical and environmental conditions.
        
        
          The investigation required close integration of geotechnical,
        
        
          contamination and groundwater assessments. The project will
        
        
          beneficially re-use a highly degraded site by implementing
        
        
          several remediation measures on a large scale, making the
        
        
          project unique to Australia and unusual worldwide. The method
        
        
          of selecting the preferred remediation options is described, and
        
        
          the key design considerations discussed. The Terminal 4 Project
        
        
          is expected to improve the long-term environmental condition
        
        
          of a site previously contaminated by industrial waste, while
        
        
          protecting the surrounding sensitive environment.
        
        
          The PRBs will be installed along the northern boundary of
        
        
          the site and keyed into the clay aquitard at a depth of about 4 m
        
        
          to 5 m.
        
        
          7 ACKNOWLEDGEMENTS
        
        
          The author thanks Port Waratah Coal Services Limited for
        
        
          providing permission to publish this paper. The staff at Douglas
        
        
          Partners’ Newcastle office is acknowledged for their hard work
        
        
          and commitment to this important and complex project.