 
          2955
        
        
          Technical Committee 214 /
        
        
          
            Comité technique 214
          
        
        
          4.3
        
        
          
            Shortage of time for construction
          
        
        
          In the initial stage of construction, it was impossible to start the
        
        
          improvement of the soft soil on time because of civil complaints
        
        
          and delays in obtaining agreements for purchasing land. Multi-
        
        
          phase construction work such as "PBD construction after
        
        
          removing the existing road" may reduce the time available to
        
        
          improve the soft soil. For example, in the case of the Namhae
        
        
          line, on which construction was completed in 1996, it was
        
        
          expected that it would take 24 months to improve the soft soil in
        
        
          two sections of expansion and existing roads. However, it took
        
        
          more than 24 months just to improve the soft soil in the
        
        
          expansion section. Thus, at that time, the construction plan was
        
        
          modified to reduce the time spent improving the soft soil of the
        
        
          existing road (Korea Expressway Corporation, 2006).
        
        
          4.4
        
        
          
            Allowable residual settlement
          
        
        
          For the construction of the expansion of the second branch, 10
        
        
          cm of allowable residual settlement was applied equally, in spite
        
        
          of the great differences in the depths of the soft soil in the
        
        
          different zones. However, the problems and phenomena vary
        
        
          depending on the conditions of the soft soil. If the 10 cm
        
        
          standard is applied equally to all zones, it may produce an
        
        
          inefficient effort. For example, it is necessary that more than
        
        
          98% of the consolidation occur during the construction period
        
        
          to satisfy the 10 cm residual settlement requirement, based on
        
        
          the assumption that the thickness of the soft soil is 50 m and the
        
        
          total settlement is 450 cm, applying Terzaghi's consolidation
        
        
          theory. In this situation, the cost and time required to improve
        
        
          the soft soil are excessive.
        
        
          The road design manual clearly states that "For a road, it can
        
        
          be applied 10 cm as the residual settlement after pavement, but
        
        
          it should be appropriately applied by considering the factors
        
        
          such as the purpose of use, importance, ground characteristics,
        
        
          construction period, constructability and economic feasibility,
        
        
          etc." Accordingly, the standard needs to be adjusted.
        
        
          5 IMPROVEMENTS IN DESIGN
        
        
          5.1
        
        
          
            Establishment of improvement direction
          
        
        
          The original design was made to satisfy a grade of 0.5% and for
        
        
          traffic to be diverted during construction of the expansion, so
        
        
          that in both directions (to Busan and to Naengjeong), where the
        
        
          soft soil is present, the longitudinal grade could be raised and
        
        
          the road could be widened. To satisfy the 10 cm residual
        
        
          settlement requirement within 1,500 days (the construction time
        
        
          allowed), the soil of the existing road was to be removed, the
        
        
          soft soil improved and counterweight fill applied after banking.
        
        
          This design approach poses many problems. For example, long-
        
        
          term settlement can be induced by raising the longitudinal
        
        
          grade, dividing the median strip bilaterally and counterweight
        
        
          filling (banking), as well as not treating the existing road. Thus,
        
        
          improvements to the plan are needed to solve these problems.
        
        
          Table 1. Improvements in design.
        
        
          Original design
        
        
          Improved design
        
        
          Removing the embankment of the
        
        
          existing road + PBD + preloading
        
        
          ⇒
        
        
          Satisfy the residual settlement
        
        
          requirement during the
        
        
          construction period
        
        
          Non-improvement of the existing
        
        
          road + Preloading
        
        
          ⇒
        
        
          Inducing long-term settlement
        
        
          Upward adjustment of the
        
        
          longitudinal grade and connecting
        
        
          the two alignments
        
        
          Controlling the upward adjustment
        
        
          of the longitudinal grade and
        
        
          dividing the median strip bilaterally
        
        
          5.2
        
        
          
            Improvement factors
          
        
        
          
            5.2.1 Lowering the longitudinal grade
          
        
        
          To minimize the settlement due to overburden load on none
        
        
          improved existing road, the embankment height was adjusted by
        
        
          changing the standard for the minimum slope (from 0.5% or
        
        
          more to 0.3% or more) given in the Manual and Guideline for
        
        
          Standards of Road Structures stipulated by the Ministry of
        
        
          Construction and Transportation (2003). Additionally, the
        
        
          embankment height was changed to be similar to the
        
        
          longitudinal grade of the existing road by changing a bridge
        
        
          type (from passing below to passing above) that crosses the
        
        
          main line and adjusting the height of the bridge to provide
        
        
          sufficient overhead clearance.
        
        
          
            Original design Improved design The existing road
          
        
        
          
            Earth work zone
          
        
        
          
            Bridge zone
          
        
        
          How to adjust
        
        
          Descriptions
        
        
          Applicable
        
        
          length
        
        
          Remark
        
        
          Change the way to
        
        
          cross a bridge
        
        
          Underground rigid
        
        
          frame bridge
        
        
          ⇒
        
        
          Pedestrian bridge
        
        
          1.0km - 5m
        
        
          Adjustment of
        
        
          minimum
        
        
          Longitudinal slope
        
        
          0.5%
        
        
          ⇒
        
        
          0.3% 4.5km - 1m
        
        
          Adjustment of
        
        
          passing extra height
        
        
          of bridge
        
        
          Secure the
        
        
          minimum overhead
        
        
          clearance
        
        
          3.5km - 0.8m
        
        
          Figure 4. A plan to adjust the longitudinal grade.
        
        
          
            5.2.2 Change in the standard for allowable residual settlement
          
        
        
          Disregarding the initial soil conditions (the depth of the soft
        
        
          soil), the design standard for uniformly applied allowable
        
        
          residual settlement is 10 cm. However, this standard was
        
        
          changed based on the depth of the soft soil, as shown in Table 2.
        
        
          Table 2. Design criteria for allowable residual settlement.
        
        
          Thickness of soft
        
        
          soil
        
        
          Allowable residual
        
        
          settlement
        
        
          Degree of
        
        
          consolidation
        
        
          10 m below
        
        
          10 cm
        
        
          30 m below
        
        
          20 cm
        
        
          30 m above
        
        
          30 cm
        
        
          90% above
        
        
          
            5.2.3 Line separation
          
        
        
          To minimize damage due to differential settlement induced by
        
        
          the different loading histories of the soil in each direction,
        
        
          installation of a green belt 3~6 m wide on the median strip and
        
        
          line separation for each direction were suggested. For the
        
        
          existing road, an overlay was applied to match the finished
        
        
          grade with a slight adjustment of the longitudinal grade. The
        
        
          soil underneath the existing road was not improved.