 
          2951
        
        
          Technical Committee 214 /
        
        
          
            Comité technique 214
          
        
        
          illustrates the major steps in the heavy tamping ground
        
        
          improvement method adopted in the project.
        
        
          Figure 2. Major steps in heavy tamping ground improvement
        
        
          
            4.2 Vacuum consolidation method
          
        
        
          In the application of vacuum consolidation method, about a 1.0
        
        
          m to 1.5 m thick fill was constructed on the original ground
        
        
          surface to form a working platform for the band drain
        
        
          installation machine. Band drains were installed by a machine
        
        
          up to a designed depth from the original ground surface in a
        
        
          square pattern with a spacing of 1 m. Thereafter, flexible
        
        
          horizontal drains (300 mm wide and 4 mm thick) were laid on
        
        
          top of the fill with a horizontal spacing of 1 m and then
        
        
          connected to the vertical band drains in order to ensure adequate
        
        
          horizontal drainage capacity. Subsequently, the tank system was
        
        
          installed and connected to the designed pipe systems. Small
        
        
          ditches were excavated perpendicular to the horizontal drains at
        
        
          20 m intervals and filled with aggregates after placing
        
        
          perforated pipes. Instrumentation such as settlement plates,
        
        
          displacement stakes, electrical piezometers and differential
        
        
          settlement gauges were also installed at the designed depths.
        
        
          After installation of vertical drains, horizontal drains, perforated
        
        
          pipes and separator tanks, the surface of the treatment area was
        
        
          covered by a protection sheet. Thereafter, an air tight sheet was
        
        
          laid on top and the periphery trench system was constructed to
        
        
          provide air tightness and the necessary anchorage at the
        
        
          boundary of the treatment area. Vacuum pressure was then
        
        
          applied using a vacuum pumping system patented by Maruyama
        
        
          Industry Co. Ltd, Japan by connecting the suction and water
        
        
          hoses to the vacuum pump. After confirming that there were no
        
        
          leaks through the air tight sheet, filling was commenced.
        
        
          It was expected to apply the surcharge by means of a
        
        
          vacuum pressure of 70kPa to compensate the primary
        
        
          consolidation settlements and to minimize the secondary
        
        
          settlements that can take place in the proposed highway
        
        
          embankment. However, in many areas the applied vacuum
        
        
          pressure was less than the designed value and therefore the
        
        
          above designed surcharge was applied by means of both
        
        
          vacuum pressure and embankment fills. The designed load was
        
        
          kept until the expected settlement completed.
        
        
          5 ASSESSMENT OF THE SOFT GROUND
        
        
          IMPROVEMENT
        
        
          The continuous assessment of the improvement of soft ground
        
        
          was carried out by conducting the field monitoring program. In
        
        
          addition, the soft ground improvement was assessed by
        
        
          conducting appropriate field and laboratory testing.
        
        
          
            5.1 Field monitoring program
          
        
        
          The improvement of the soft ground was monitored through the
        
        
          measurement of settlement and the excess pore water pressure
        
        
          during the construction period. Settlement plates were installed
        
        
          at the top of the soft layer or on top of the pioneer layer and
        
        
          piezometers were installed at the middle of the soft layer. The
        
        
          settlement stakes were installed near the toe of the
        
        
          embankments to check the stability during the construction. In
        
        
          addition to the above, in the areas improved by vacuum
        
        
          consolidation, a vacuum pressure monitoring unit was used to
        
        
          measure the vacuum pressure at the pump and under the air
        
        
          tight sheet. Also, a water discharge meter was used to measure
        
        
          the rate and the total discharged water flow due to the vacuum
        
        
          operation. An automatic data acquisition unit was connected
        
        
          with the piezometer, vacuum pressure monitoring unit and
        
        
          water discharge meter to keep continuous records.
        
        
          The decision to remove the surcharge was made on the basis
        
        
          of the monitoring data obtained during the surcharge period.
        
        
          The aim was to eliminate 100% of primary consolidation
        
        
          settlement and enough secondary settlement such that the
        
        
          residual settlement was within acceptable performance limits.
        
        
          The primary consolidation settlement was assessed by
        
        
          estimating the degree of consolidation and in this project it was
        
        
          estimated by the method outlined by Asaoka (1978). The degree
        
        
          of consolidation was also calculated based on the pore water
        
        
          pressure (PWP) measurements, and laboratory consolidation
        
        
          testing of peaty samples after the treatment program. The
        
        
          comparison of the degree of consolidation for each method for
        
        
          some areas improved by the vacuum consolidation method is
        
        
          shown in Table 1.
        
        
          Table 1. Estimation of the degree of consolidation
        
        
          Degree of Consolidation
        
        
          Location
        
        
          Asaoka
        
        
          Method
        
        
          Laboratory
        
        
          Data
        
        
          PWP
        
        
          83.10%
        
        
          Ch. 45.380 –
        
        
          Ch. 45.430
        
        
          97.83%
        
        
          73.87%
        
        
          79.46%
        
        
          100.00%
        
        
          Ch. 47.850 –
        
        
          Ch. 47.920
        
        
          97.10%
        
        
          100.00%
        
        
          100.00%
        
        
          80.21%
        
        
          Ch. 52.950 –
        
        
          Ch. 53.000
        
        
          97.57%
        
        
          90.91%
        
        
          100.00%
        
        
          96.70%
        
        
          Ch. 53.660 –
        
        
          Ch. 53.730
        
        
          96.65%
        
        
          83.62%
        
        
          68.71%
        
        
          If the degree of consolidation from the PWP measurement is
        
        
          assumed to be accurate, Asaoka Method accurately estimates
        
        
          the degree of consolidation in treatment areas Ch.47.850 to
        
        
          Ch.47.920 and Ch.52.950 to Ch.53.000 whereas Asaoka method
        
        
          over predicts the degree of consolidation in treatment areas Ch.
        
        
          45.380 to Ch. 45.430 and Ch.53.660 to Ch. 53.730. However, in
        
        
          treatment area Ch.53.660 to Ch.53.730 the degree of
        
        
          consolidation from the laboratory test results agreed very well
        
        
          with the same estimated from the Asaoka method. Therefore,
        
        
          based on this investigation it can be concluded that the degree
        
        
          of consolidation estimated from the Asaoka method is
        
        
          reasonably accurate.
        
        
          In order to assess the secondary settlements, for each
        
        
          monitoring point, the long-term settlement was predicted by
        
        
          extrapolating the secondary settlement rate over a period of 3
        
        
          years. Predictions were made by preparing a plot of
        
        
          displacement against log (time) for each settlement plate, with
        
        
          the best-fit line through the data extended to define the likely
        
        
          settlement after 3 years.  The surcharge was removed only after
        
        
          confirming the residual settlement by considering both the
        
        
          primary and secondary consolidation settlements as described
        
        
          above.
        
        
          
            5.2 Investigation to confirm the ground improvement
          
        
        
          Site investigation was carried out to assess the actual ground
        
        
          improvement in the areas improved by the vacuum
        
        
          consolidation method just before the removal of surcharge.
        
        
          Investigation was carried out in the improved as well the
        
        
          adjacent unimproved area in order to assess the ground
        
        
          improvement. Investigation revealed that initial thickness of the
        
        
          peat layer has been reduced by 50%-60% after ground
        
        
          improvement. The above reduction agreed reasonably with the