          Figure 1. Distribution of soft ground areas
        
        
          In the flood plains of Panape, Kalu Ganga, Welipenna and
        
        
          Bentota river areas sub soil consisting of mainly peat, organic
        
        
          clay, very soft inorganic clay and silt layers was found. The
        
        
          total average thickness of the compressible layer was in the
        
        
          range of 4 m to 11 m. In some areas loose silty sand layers were
        
        
          present under the above compressible layers. In the valley areas
        
        
          between hillocks, instead of cohesive inorganic clays, very
        
        
          loose to loose silt and sand were found ranging from 0.5 m to
        
        
          4m thickness. The details of the Geotechnical properties of the
        
        
          subsoil have been given in Karunawardena and Nithiwana
        
        
          (2009) and Karunawardena and Toki (2011).
        
        
          3 SOFT GROUND IMPROVEMENT DESIGN
        
        
          Soft ground improvement design had to be carried out in order
        
        
          to control the settlements and to ensure the stability of the
        
        
          highway embankment as required in the technical specification.
        
        
          According to the technical specification, the embankment had to
        
        
          be designed and constructed by improving the soft ground in
        
        
          order to control the continued settlement to 15cm at the road
        
        
          center after a period of 3 years following the acceptance of the
        
        
          paving. In addition, the maximum residual differential
        
        
          settlement had to be not more than 0.3% change in grade over
        
        
          longitudinally within 3 years after construction. In order to
        
        
          achieve the above criteria, most or all of the primary settlement
        
        
          and some of the secondary settlement that would have occurred
        
        
          under the final embankment height alone were forced to take
        
        
          place by improving the soft ground.
        
        
          The soft ground was improved mainly by using the
        
        
          following methods based on the subsoil conditions.  Soft clay
        
        
          of shallow thickness was improved by placing a surcharge load.
        
        
          Shallow peat and organic clay deposits were removed and
        
        
          replaced with rock in order to support the embankments. The
        
        
          subsoil with relatively thick soft clay layers were improved by
        
        
          installing vertical drains and placing a surcharge load. The
        
        
          embankments on the relatively thick peat and organic deposits
        
        
          were constructed by improving the ground by heavy tamping
        
        
          method and the vacuum consolidation method from 0.0 km to
        
        
          34.5 km and from 34.5 km to 66.5 km respectively.
        
        
          In rock replacement method, all compressible layers of the
        
        
          sub soil were removed and replaced with rock, completely
        
        
          eliminating the settlements. In the ground improvement method
        
        
          of application of surcharge load with or without vertical drains,
        
        
          future settlement of the highway embankment was controlled as
        
        
          required in the contract by designing an appropriate surcharge
        
        
          load. Most or all of the primary settlement and some of the
        
        
          secondary settlement that would have occurred under the final
        
        
          embankment height alone were forced to take place under the
        
        
          surcharge load. In addition, it was expected that the soil beneath
        
        
          the embankment would become over consolidated or stiffer due
        
        
          to the surcharging of ground. The aim of applying the surcharge
        
        
          was to eliminate 100% of primary consolidation settlement and
        
        
          enough secondary settlement such that the residual settlement is
        
        
          within acceptable performance limits. The residual settlement
        
        
          for a given length of time after construction was estimated as
        
        
          the remaining secondary settlement that occurs during the
        
        
          required time after the eliminated equivalent time of secondary
        
        
          compression has elapsed. In the design of surcharge, it was
        
        
          expected to have 1.1 over consolidation ration (OCR) for
        
        
          inorganic clays and 1.2 to 1.3 OCR for peat and organic clays in
        
        
          order to reduce the secondary settlements during the operation
        
        
          period.
        
        
          4 EMBANKMENT CONSTRUCTION ON PEATY SOILS
        
        
          Embankments over peaty deposits in the Southern Expressway
        
        
          between Ch. 0.000 km to Ch 34.500 km were constructed by
        
        
          improving the peaty soil using the heavy tamping method
        
        
          whereas vacuum consolidation technique was applied to
        
        
          improve the peaty soil in the Section between Ch.34.500 km to
        
        
          66.500 km. This Chapter presents the details of the heavy
        
        
          tamping method and the vacuum consolidation techniques
        
        
          applied in the project.
        
        
          
            4.1 Heavy Tamping Method
          
        
        
          Heavy tamping method was designed to enforce the settlements
        
        
          that would be caused by the construction of earth embankment
        
        
          on soft ground by applying impact energy. Different energy
        
        
          levels had to be imparted by considering the anticipated
        
        
          settlement of the compressible layer under the respective
        
        
          designed embankment heights. In the estimation of settlements,
        
        
          all primary consolidation settlements and secondary settlements
        
        
          at the end of 3 years after construction were considered. First,
        
        
          the soft soil which was to be consolidated, was overlain by a
        
        
          working platform of lateritic soil to facilitate the movement of
        
        
          machinery. Then, a strong type fibre drain (band drain) was
        
        
          installed by a machine in the soft subsoil in a square pattern
        
        
          with a spacing of 1 m in order to prevent high excess pore water
        
        
          pressure development in the underneath soil due to the applied
        
        
          energy. The required energy was applied to the soil by dropping
        
        
          a large weight on the ground surface repeatedly in phases on a
        
        
          grid pattern over the entire full base width of the embankment
        
        
          using multiple passes.
        
        
          During tamping, once the depth of the crater formed by
        
        
          pounder exceeded the height of the pounder, the crater was back
        
        
          filled and leveled with soil. The dimension of the crater was
        
        
          recorded in order to calculate the volume of soil introduced. The
        
        
          above process was continued in all phases of the tamping
        
        
          operation. Using the crater fill volumes, the enforced settlement
        
        
          was calculated and if the enforced settlement was less than what
        
        
          was required then another phase of tamping was introduced
        
        
          until the required settlement was achieved.
        
        
          After application of heavy tamping, borehole investigation
        
        
          was carried out in order to assess the ground improvement.
        
        
          Investigations revealed that the layer thickness of peat has been
        
        
          reduced to 20% to 50% of its original thickness after the heavy
        
        
          tamping.  The SPT values of peat layer at a 3m to 4m depth
        
        
          increased from 0 to a range of 4 to 8. Consolidation test results
        
        
          showed that the value of the compression index (c
        
        
          c
        
        
          ) and
        
        
          coefficient of secondary consolidation (c
        
        
          α
        
        
          ) has decreased
        
        
          significantly. It was also noted that the pre-consolidation
        
        
          pressure,
        
        
          P
        
        
          c
        
        
          , of peaty soil has increased from 32, to as high as
        
        
          85. This increase of pre-consolidation pressure means the peaty
        
        
          soil is in an over-consolidated state during the service life of the
        
        
          highway. All these observations confirmed that the expected
        
        
          primary and secondary consolidation settlements due to the
        
        
          embankment load would be very small in the areas improved by
        
        
          heavy tamping.
        
        
          However, it was observed that the peat layers at the deeper
        
        
          depths had not achieved the above improvement.  This was
        
        
          investigated and it was found that the practically possible
        
        
          improvement depth that could be achieved in the present
        
        
          operation was about 3.5 m to 4 m. These underneath deeper soft
        
        
          layers were improved after the heavy tamping operation by
        
        
          keeping a surcharge load for a sufficient period of time as
        
        
          reported by Karunawardena and Toki (2011). Figure 2