 
          2940
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          the monitoring data do not indicate the stability condition of the
        
        
          MSE berm directly.
        
        
          Several finite element models (FEM) were developed for
        
        
          evaluating the stability of the MSE berm during construction
        
        
          using PLAXIS® software. The soil consolidation parameters
        
        
          obtained from laboratory and pilot tests were used as an initial
        
        
          model calibration.  These parameters were adjusted during the
        
        
          initial 3-m lift placement and then used to predict pore
        
        
          pressures, lateral and vertical displacements during construction
        
        
          for subsequent lifts. The calibrated FEM models were used to
        
        
          closely monitor the construction of the MSE berm. After
        
        
          construction of each stage, the predicted horizontal and vertical
        
        
          displacements and excess pore water pressure were compared to
        
        
          the measured values at selected cross sections to verify
        
        
          whetherthe MSE berm was performing as expected.  In
        
        
          addition, using ashear strength reduction method, factors of
        
        
          safety (FS) at each stage of construction was estimated by the
        
        
          FEM model.  The procedure consisted of reducing the soil shear
        
        
          strength parameters by a factor in an iterative procedure until
        
        
          large displacements of the FEM model were observed. The
        
        
          ultimate factor achieved represented the factor of safety against
        
        
          instability using PLAXIS.Figure 5 shows an example of the
        
        
          comparison between the measured and predicted pore pressures.
        
        
          0.00
        
        
          5.00
        
        
          10.00
        
        
          15.00
        
        
          20.00
        
        
          25.00
        
        
          30.00
        
        
          35.00
        
        
          40.00
        
        
          0
        
        
          100
        
        
          200
        
        
          300
        
        
          400
        
        
          500
        
        
          600
        
        
          700
        
        
          800
        
        
          900
        
        
          1000
        
        
          
            ExcessPoreWater Pressure (ft)
          
        
        
          
            Time (days)
          
        
        
          FEMPrediction
        
        
          CorrectedMornitoring
        
        
          Data
        
        
          Comp.
        
        
          Berm
        
        
          1stLift
        
        
          2ndLift
        
        
          3rdLift
        
        
          4thLift
        
        
          FS=2.21
        
        
          FS=2.23
        
        
          FS=2.05
        
        
          FS=1.55
        
        
          FS=1.80
        
        
          FS=1.45
        
        
          FS=1.51
        
        
          FS=1.39
        
        
          FS=1.30
        
        
          5thLift
        
        
          FS=1.63
        
        
          FS=1.33
        
        
          FS=1.41
        
        
          6thLift
        
        
          (5baskets)
        
        
          FS=1.87
        
        
          Figure 5. Example of monitoring results vs. predicted ones
        
        
          The calculated FS at each stage of the construction are also
        
        
          shown in Figure 5.Although the construction schedule was
        
        
          initially established based upon estimated rates of pore pressure
        
        
          dissipation using the simplified drainage model described
        
        
          above, the schedule was constantly adjusted during construction
        
        
          based on the interpretation of the stability condition.
        
        
          The MSE berm has undergone significant deformation.A
        
        
          settlement of approximately 4m was initially estimated.The
        
        
          recorded maximum vertical and horizontal displacements were
        
        
          approximately 4.2 m and 1.7 m, respectively.
        
        
          7 BERM CONSTRUCTION
        
        
          Construction of embankments designed using the HDU model
        
        
          requires close interaction between the designer, the contractor,
        
        
          and the owner, to allow timely geotechnical review and
        
        
          interpretation of monitoring data and communication of
        
        
          findings. During the initial stage of the project, it was found that
        
        
          the rate of pore pressure dissipation varied by sections of the
        
        
          MSE berm due to the localized subsurface geotechnical
        
        
          conditions. Because of the difference in consolidation rates, the
        
        
          contractor was required to alter its original construction
        
        
          sequence for the berm, moving back and forth between the
        
        
          different sections.By providing clarity to all parties on when
        
        
          subsequent berm lifts were likely to be feasible in any particular
        
        
          location, flexibility in construction task management and
        
        
          minimized disruption to the overall construction schedule could
        
        
          be achieved.  With daily review of geotechnical data and
        
        
          frequent review of finite-element modeling output prepared for
        
        
          numerous berm cross sections, the designer was able to identify
        
        
          areas of construction on a “just-in-time” basis for the contractor
        
        
          to continue uninterrupted work. Eventually, the original plan of
        
        
          building a 3m-thick lifts over 600m to 900m length of the berm
        
        
          every 90 days evolved into construction of lifts in thicknesses as
        
        
          thin as 1m and/or berm lengths as short as 300m, which were
        
        
          patched together as review of geotechnical data would allow.
        
        
          The contractor’s ability to reorganize its efforts to construct the
        
        
          various sections of the berm based on week-to-week feedback
        
        
          from the designer became a critical piece of the success of the
        
        
          project. In this way, by August 2010, 36 months after starting,
        
        
          MSE berm construction was completed. A detailed description
        
        
          of the berm construction is presented by Espinoza et al (2008)
        
        
          and (2011).
        
        
          8 CONCLUSIONS
        
        
          The completion of this 1.8 million cubic meters MSE berm (see
        
        
          picture below) represents a significant engineering achievement
        
        
          considering the size of the embankment, the deep layer of very
        
        
          soft soils over which the berm was constructed, and the amount
        
        
          of settlements during construction.  The successful design and
        
        
          construction of a 2,400m long, 21m high MSE berm over
        
        
          extremely soft dredge using innovative design and construction
        
        
          techniques opens opportunities not only for extending the
        
        
          capacity of existing disposal facilities over dredge disposal sites
        
        
          but also for very cost effectively raising levees and dykes at
        
        
          critical locations prone to flooding.
        
        
          Figure 6. View of Completed MSE berm
        
        
          The use of PVDs at this site, which was shown to be
        
        
          feasible using the HDU methodology, resulted in savings of
        
        
          over $150 million when compared to conventional ground
        
        
          improvement techniques such as DSM.
        
        
          9 REFERENCES
        
        
          Espinoza R.D., Lazarte, C.A., Germain, A.M., and Houlihan M.F. 2008.
        
        
          Design Considerations for Expansion of an Existing Landfill Over
        
        
          Extremely Compressible Soils.
        
        
          
            Geo-Strata
          
        
        
          , March-April 2008, pp.
        
        
          38-43.
        
        
          Espinoza R.D., Houlihan M.F. and Ramsey, T.B.Design of High Soil
        
        
          Berms over Soft Soils.
        
        
          
            Geo-Strata
          
        
        
          , March-April 2011, pp. 52-54.
        
        
          Barron, R.A. (1948).  Consolidation of Fined-Grained Soils by Drain
        
        
          Wells.  ASCE Trans, paper 2346, V. 113, 718-724.