 
          2932
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          
            3.5 Monitoring of Taxiway and Taxiway Piles
          
        
        
          The movement of the taxiway pile foundation and the MIA
        
        
          seawall were closely monitored during the seawall construction
        
        
          phase. No significant movement of the taxiway, the piles and
        
        
          the seawall was measured. Monitoring will continue during the
        
        
          future landfilling operation stage when the loading is
        
        
          maximized in the landfill.
        
        
          Figure 10. Height Restriction of the Site near the Runway of MIA
        
        
          There was no readily available land access to the site as it is
        
        
          restricted by the landfill site and the MIA. Marine access was
        
        
          also limited due to the shallow draft and the contractor had to
        
        
          carry out additional dredging for navigation.  The original
        
        
          design proposed a temporary platform for landbased stone
        
        
          column construction.  During the construction stage, the
        
        
          contractor changed to marine based method for installation of
        
        
          the stone columns.
        
        
          To ensure the mud will not be mixed with the stone
        
        
          aggregates due to collapse of hole or necking, wet bottom feed
        
        
          method was adopted (Figure 11). Acceptance of the stone
        
        
          column was based on the depth vsSC diameter plot, and degree
        
        
          of compaction (volume of aggregate, energy consumed)from the
        
        
          installation records.  Site trial was carried out to determine the
        
        
          optimum arrangement on apparatus, setup, minimum required
        
        
          compaction time, amount of aggregate consumption per metre
        
        
          length, andmaximum energy consumption (Figure 12).
        
        
          4 SUMMARY AND CONCLUSIONS
        
        
          Construction waste was dumped over very soft marine mud
        
        
          at the Cotai Landfill of Macau.  This uncontrolled dumping
        
        
          pushed the very soft mud and generating mudwaves that were
        
        
          then encroaching onto the piles supporting the taxiway bridges
        
        
          of the Macau International Airport.
        
        
          Due to the seriousness of the problem, government of Macau
        
        
          commissioned AECOM Asia Co. Ltd., to develop a robust
        
        
          solution to contain the construction waste being dumped in the
        
        
          area and to protect the taxiway bridge of the Macau Airport.
        
        
          The design solution developed was to construct a containment
        
        
          bund/seawall that is founded on a stiffened and strengthened
        
        
          soil block by improving the soft clay with stone columns. This
        
        
          paper presented the design approach of the containment bund
        
        
          including the limited equilibrium stability analysis and the
        
        
          numerical analyses carried out that demonstrated that the
        
        
          solution is appropriate as the bund will contain the landfill with
        
        
          minimal impact on the taxiway bridge piles. The analyses also
        
        
          demonstrated that the impacts during construction are also
        
        
          negligible.
        
        
          During construction, the taxiway and seawall was monitored
        
        
          by independent parties and survey results indicate the
        
        
          installation of the stone columns and construction of the bund
        
        
          had minimal impact on the taxiways foundation piles. The
        
        
          seawall has been completed in November 2011 (Figure 13).
        
        
          Figure 13. The Completed Stone Column Seawall
        
        
          5 ACKNOWLEDGEMENTS
        
        
          This paper is published with the permission of the Head of
        
        
          Gabinete para o Desenvolvimento de Infra-estruturas of the
        
        
          Macau SAR Government.
        
        
          Figure 11. Stone Column Plant for Wet Bottom Feed installation
        
        
          6 REFERENCES
        
        
          Barksdale, R.D. & Bachus R.C. 1983.
        
        
          
            Design and Construction of Stone
          
        
        
          
            Columns – Volume 1
          
        
        
          . US department of Transport.
        
        
          Laboratório de Engenharia Civil de Macau 2008a.
        
        
          
            Inspection Report of
          
        
        
          
            Southern Taxiway Bridge Piles
          
        
        
          .
        
        
          LECM, Macau
        
        
          Figure 12. Site Trial Establishingthe Acceptance Criteria
        
        
          Laboratório de Engenharia Civil de Macau 2008b.
        
        
          
            Numerical analysis
          
        
        
          
            report on the landfill mudwaves impact to Southern Taxiway
          
        
        
          
            Bridge
          
        
        
          .
        
        
          LECM, Macau