 
          3277
        
        
          Technical Committee 307 /
        
        
          
            Comité technique 307
          
        
        
          
            Proceedings of the 18
          
        
        
          
            th
          
        
        
          
            International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
          
        
        
          to be completely wrapped in the
        
        
          geo
        
        
          during the execution
        
        
          of such operations is essential.
        
        
          f
        
        
          han
        
        
          l
        
        
          con
        
        
          plan, is
        
        
          r the top of
        
        
          the
        
        
          in at
        
        
          either side to provide around half a bale width of overlap.
        
        
          ler to the layer to vibrate the fill into the voids
        
        
          (Fi
        
        
          ve or
        
        
          below the tyre bale layer must also be taken into account.
        
        
          consolidated silts and clays, and soft predominately mineral
        
        
          soils (albeit with exceptions). A geotextile helps to spread the
        
        
          foundation load. Often the repair or reconstruction of an
        
        
          existing road over soft ground is required as a result of
        
        
          differential settlement which leaves an uneven surface with poor
        
        
          ride quality and an increased risk of flooding. The placement of
        
        
          material to raise and regulate the pavement surface increases the
        
        
          formation load causing further differential settlement;
        
        
          replacement of the existing material is thus necessary.
        
        
          Figure 2. Advantages and disadvantages of floating construction (top)
        
        
          and buried construction (bottom).
        
        
          4 CONSTRUCTION APPROACHES
        
        
          The construction and rehabilitation of low-volume roads over
        
        
          soft ground is an ideal application for tyre bales. While there is
        
        
          currently little information to prove their use with higher traffic
        
        
          levels (in excess of a few hundred vehicles/day AADT) there
        
        
          are no pressing reasons why such uses should not be successful.
        
        
          Low-volume tyre bale roads have been successfully
        
        
          constructed both above and below ground. A geotextile
        
        
          separator is used between the in-situ soil and the tyre bales,
        
        
          usually with a regulating layer of sand. The geotextile helps to
        
        
          prevent differential movement of the bales during and after
        
        
          construction. The decision as to whether the construction should
        
        
          be above or below ground is an important determinant of the
        
        
          approach to the design and construction.
        
        
          Analytical input for low-volume road design on soft ground
        
        
          is often limited. The strength and stiffness properties of the soil
        
        
          involved are usually at or close to the lower limit of
        
        
          measurement, rendering input parameters subject to large errors.
        
        
          The sampling process may also disrupt the soil structure leading
        
        
          to values lower than the field condition. Accordingly many
        
        
          roads are designed on an empirical, specification-led basis.
        
        
          The following sections summarises the main construction
        
        
          steps and issues and offer guidance based upon experience of
        
        
          successful projects and established good practice in constructing
        
        
          low-volume roads over soft ground using tyre bales. Further
        
        
          details are given by Winter et al. (2006) and Anon. (2007).
        
        
          4.1
        
        
          
            Excavation and preparation
          
        
        
          For buried construction, excavation is the first construction
        
        
          activity. Low ground-pressure, tracked plant is preferred as is
        
        
          working in drier weather when the moisture content of the soil
        
        
          is minimised and strength and stiffness are maximised.
        
        
          A suitable geotextile should be installed either at ground
        
        
          surface level or in the excavation followed by a regulating layer
        
        
          of sand if required. All geotextile-to-geotextile interfaces should
        
        
          have an overlap of 1m. The use of a geotextile has a number of
        
        
          advantages including aiding working conditions in soft soils,
        
        
          strengthening the structure by tying together the assembly of
        
        
          bales, and providing separation between the bales and the
        
        
          subsoil and thus preventing the ingress of fines. Randomly
        
        
          orientated, bonded, non-woven geotextiles have been found to
        
        
          be effective. Their main function is separation, with strength
        
        
          and resistance to clogging the most important properties.
        
        
          Geotextile design procedures should reflect local standards. The
        
        
          geotextile should be placed in the base of the excavation, or on
        
        
          the cleared ground. Sufficient excess should be allowed at either
        
        
          side to allow the bale assembly
        
        
          textile with a 1m overlap.
        
        
          Rapid cellular construction minimises excavation size,
        
        
          exposure of the soil to weather and the likelihood of side slope
        
        
          failure. Bale sizes mean that excavations are unlikely to exceed
        
        
          1m, but an assessment of the possibility of sidewall collapse and
        
        
          the associated risks to workers and others
        
        
          4.2
        
        
          
            Placement and alignment
          
        
        
          Tyre bale handling must incur the minimum risk of damage to
        
        
          the steel tie-wires. The most successful means of handling tyre
        
        
          bales has been found to be a ‘loggers’-clam’, which can be
        
        
          attached to a variety of hydraulic equipment and provides an
        
        
          appropriate lift-and-place methodology while allowing the bale
        
        
          to be rotated to the correct alignment. Alternative forms o
        
        
          dling bales include brick-grabs and forklifts (Anon. 2007).
        
        
          The manufacturing process renders tyre bales inherently
        
        
          heterogeneous. Information on the relative stiffness in each of
        
        
          the three directions is not currently available. Tyre bales exhibit
        
        
          a high stiffness when loads are applied vertically to the 1.3m by
        
        
          1.55m plane (Figure 1); accordingly they are usually installed as
        
        
          illustrated in Figure 1 for applications that attract high vertical
        
        
          loads such as road foundations. The 1.55m by 0.8m plane is
        
        
          perpendicular to the load applied during manufacture and it is
        
        
          recommended that it is aligned perpendicular to the longitudina
        
        
          fining stresses (i.e. with the tie-wires in line with the road.
        
        
          While there are different layout options for the two-
        
        
          dimensional placement of tyre bales (i.e. in a single layer) a
        
        
          straightforward ‘chessboard’ pattern, as viewed in
        
        
          generally the easiest to construct and is recommended.
        
        
          A regulating layer of sand is normally required between the
        
        
          top of the tyre bales and the geotextile wrapped ove
        
        
          layer to help eliminate small variations in level.
        
        
          The foregoing assumes that a single layer of bales is to
        
        
          support the road. If two or more layers are required then the
        
        
          second layer should be placed on top of the first, stepped
        
        
          4.3
        
        
          
            Filling of voids
          
        
        
          The sub-rectangular shape of tyre bales means that voids remain
        
        
          at the corners of each bale even when they are butted up against
        
        
          one other. The design generally requires the stiffness and
        
        
          stability of the structure to be maximized and thus the voids
        
        
          should generally be filled (Figure 3). Coarse sand has been used
        
        
          successfully as have single-sized aggregate pellets. Crushed
        
        
          glass may be less likely to clog or arch than sand when wet, but
        
        
          is expensive. The most effective method of ensuring that the
        
        
          voids are filled has been found to be to bulldoze a 150mm to
        
        
          300mm layer on top of the bale layer and then to apply a
        
        
          vibrating rol
        
        
          gure 3).
        
        
          The fill material affects the density of the structure, with the
        
        
          voids taking up an estimated 4% to 8% (Anon. 2007) of the
        
        
          nominal rectangular bale volume, and must be allowed for in
        
        
          design calculations. The effects of regulating layer(s) abo