 
          2706
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          
            Proceedings of the 18
          
        
        
          
            th
          
        
        
          
            International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
          
        
        
          restrike was adequate for all pile positions - upstream,
        
        
          downstream and longitudinal.  (Figure 10).
        
        
          The skin resistance distribution shown in the CAPWAP
        
        
          ®
        
        
          appears to reduce toward the toe because at such small sets not
        
        
          much of the energy of the input blow reached the lower part of
        
        
          the pile and the reduced energy did not strain the ground enough
        
        
          to generate the full resistance that was available.  The available
        
        
          resistance probably does not reduce.  If the pile could have been
        
        
          struck harder, then even more resistance would have been
        
        
          demonstrated.
        
        
          7. DRIVEN PRODUCTION PILES
        
        
          It was considered the driven pile created a more reliable
        
        
          foundation and repairs could be easily accomplished by re-
        
        
          driving if necessary.  A decision was made to change the
        
        
          foundations for all piers from bored piles into driven piles. In
        
        
          addition repairs for the abutment piles were also to be driven
        
        
          piles.
        
        
          The effect of this decision was to dramatically improve
        
        
          production rates on the pile foundations.  Because the concrete
        
        
          was eliminated from the pile there were also considerable
        
        
          savings over the original design.
        
        
          Owing to the numerous problems experienced during initial
        
        
          piling and the tripod design that provided no redundancy, the
        
        
          client required that all driven piles undergo PDA testing.
        
        
          Production testing was conducted remotely or by "stand-alone."
        
        
          (Likins, Hermansson, Kightley, Cannon and Klingberg  2009)
        
        
          The shorter piles at the western end of the bridge could be
        
        
          tested with the smaller 9ton hammer, however from almost
        
        
          exactly the centre of the bridge it was necessary to use the larger
        
        
          16t hammer to demonstrate the required resistance.  In some
        
        
          cases it was necessary to wait for "set-up" and conduct restrikes
        
        
          at 1-7 days after driving.
        
        
          Tension resistance, particularly on upstream piles, was of
        
        
          critical importance.  In some cases the resistance demonstrated
        
        
          by CAPWAP appeared to be heavily concentrated near the toe
        
        
          and owing to concern about the ability of CAPWAP to
        
        
          accurately differentiate between skin friction near the toe and
        
        
          toe resistance the author was requested to provide an estimate of
        
        
          the "minimum likely" skin friction.  The method adopted was
        
        
          purely arbitrary and comprised starting with "best match" and
        
        
          moving skin friction to toe resistance until the match quality
        
        
          increased by one percent, ie CAPWAP match quality increased
        
        
          from 3.1 to 4.1 percent error.
        
        
          8. CONCLUSIONS
        
        
          Low strain and high strain dynamic pile testing was
        
        
          incorporated into both the design revision and construction
        
        
          verification aspects of this successful project.
        
        
          During construction both high strain and low strain
        
        
          dynamic testing demonstrated serious problems with the
        
        
          "constructability" of the original bored pile design.
        
        
          An innovative decision was made to radically change the
        
        
          pile design, from a bored pile to a driven steel tube pile.
        
        
          Dynamic pile testing was able to confirm pile resistance
        
        
          and provide a high level of confidence in the foundation. The
        
        
          bridge has been working as designed through 3 cyclone seasons
        
        
          carrying some of the heaviest train axle loadings in the world.
        
        
          9. REFERENCES
        
        
          Likins, Hermansson, Kightley, Cannon and Klingberg 2009
        
        
          Advances in Dynamic Foundation Testing Technology
        
        
          IFCEE Orlando, Florida USA
        
        
          
            Figure 9 PIT results for East Abutment NW pile
          
        
        
          
            Figure 10 CAPWAP results for Test Pile 3
          
        
        
          
            Figure 8 CSL result on production pile