 
          3122
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          Fig. 7. Organizing Committee Building under construction
        
        
          .
        
        
          Table 1. Soil conditions of the Organizing Committee Building site.
        
        
          Soil element
        
        
          Depth,
        
        
          m
        
        
          E,
        
        
          MPa
        
        
          φ,
        
        
          deg
        
        
          c,
        
        
          kPa
        
        
          Clay
        
        
          0…4,5
        
        
          6
        
        
          13
        
        
          22
        
        
          Very soft clays
        
        
          4,5…21
        
        
          0,7
        
        
          10,6 10,3
        
        
          Coarse sand
        
        
          21…23
        
        
          27
        
        
          29
        
        
          0
        
        
          Mixture of gravel
        
        
          and pebbles
        
        
          >23
        
        
          53
        
        
          35
        
        
          0
        
        
          Table 1 shows that application of spread footings is not
        
        
          possible, as it would result in excessive settlement. Soil
        
        
          improvement
        
        
          such
        
        
          as
        
        
          strengthening,
        
        
          reinforcement,
        
        
          replacement, etc. are not applicable because of thick  layers  of
        
        
          soft  clays. Installation of drains for soil consolidation together
        
        
          with preloading of soil mass could not be applied  due  to tight
        
        
          project deadlines. Therefore, pile footing was the only
        
        
          alternative. At the stage of pile type selection there were
        
        
          considered prefabricated piles, bored cast piles, jet-piles, gravel
        
        
          piles in geosynthetic shell, etc.
        
        
          The condition that complicates pile foundation design is that
        
        
          in order to ensure a footing seismic stability the piles shall bear
        
        
          the total lateral seismic load. The soil stratum capable to
        
        
          adequately resist to the lateral load usually occurs at over 21 m
        
        
          depth. In conditions of the site in question pile design bearing
        
        
          capacity to vertical load is times 40…60 greater that to the
        
        
          lateral load. In order to bear the vertical load of the 9-storey
        
        
          sector of the building 511 piles with 0.35x0.35 cm2 cross
        
        
          section are required while it requires 2030 piles to resist to
        
        
          lateral seismic load, i.e. times 4 as much.
        
        
          Mass application of pile foundations with intermediary sand
        
        
          layer has started in 1960s in seismic areas of the USSR. The
        
        
          results of full-scale experiments demonstrated that in such
        
        
          foundations the lateral seismic load does not practically apply to
        
        
          the piles.  Such foundation is recommended for practical
        
        
          application on sites having magnitude 7…9 seismicity.
        
        
          Application of pile foundation with intermediate cohesionless
        
        
          soil layer is not recommended by construction codes for sites
        
        
          with soils containing more than 10% of organic matter,
        
        
          collapsible soils, on karstic terrains, etc. This ban comes from
        
        
          possibility of collapse of loose soil and its disrupture that may
        
        
          result in extra deformations of the building. In order to enable
        
        
          application  of such foundation a specific approach was required
        
        
          for foundation analysis and design.
        
        
          Expanded pile caps together with cushion of cohesoinless
        
        
          soil reinforced by two layers of geosynthetics were used.
        
        
          Existing calculation method proposed by construction codes
        
        
          was developed with regard to aforementioned additions. The
        
        
          improved method took into account elasto-plastic properties of
        
        
          soils of the base; pile group effect, geometric and stiffness
        
        
          properties of deep footing (pile caps, reinforcement nets, etc.);
        
        
          stiffness  parameters of foundation rafts (pile rafts); seismic
        
        
          conditions of construction site, etc.
        
        
          The foundation design approved for implementation is
        
        
          shown on Fig. 8. Pile foundation below 9-th storey sector
        
        
          consists of 0.35x0.35 m prefabricated piles spaced over 2x2 m
        
        
          and for the 3-storey sector with 4x4 m  square  grid. The pile
        
        
          cap dimensions are 1,4х1,4х0,4 m. The intermediate cushion is
        
        
          600 mm thick, reinforced by two layers of Fortrac 35MP
        
        
          geogrid. The raft thickness under 9-storey and 3-store sectors
        
        
          800 and 600 мм respectively.
        
        
          Fig. 8. Foundation cross-section for Organizing Committee
        
        
          Building.
        
        
          The most essential factors predominant for the effectiveness
        
        
          of a such footing are: thickness of the intermediate  layer above
        
        
          pile heads; pile caps overview dimensions; pile-to-pile spacing;
        
        
          pile cross sections; number  of layers and stiffness of geogrid.
        
        
          The building settlements monitoring data demonstrated that
        
        
          the settlement is close to analytical value and is compatible with
        
        
          actual standard pile footing settlements. Typical time-settlement
        
        
          diagrams based on measured values are shown on Fig.9.
        
        
          Figure 9. Time-settlement diagrams for Organizing Committee
        
        
          Building
        
        
          .
        
        
          4
        
        
          PLOT D1 AND PLOT 17.
        
        
          Hotel complexes 3* and 4* are being constructed on plots 17
        
        
          and D1.Plot D1 is located a slightly little closer to the shore.
        
        
          Construction of 12 multistorey hotels (up to 8 floors) and
        
        
          buildings of public entertainment area is planned on plot 17.
        
        
          Each of the hotel building consists of two sections with
        
        
          dimensions of 36 x 14.9 m. Dimensions of the plot 17 is 265 x
        
        
          220 m. Overview of the complex is shown in Fig. 12. Soil
        
        
          conditions of the site vary significantly due to its large area. The
        
        
          typical cross section of the site top down consists of 4 m thick
        
        
          fill, less frequent are peats, sludge and water-saturated silty
        
        
          sands, underlain at different depths (3…11 m) by gravely sands
        
        
          and gravel and pebble soils.