 
          2736
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          With introduction of a new section bearing a heavier load,
        
        
          600 mm piles were also adopted, with load tests indicating a
        
        
          permissible load of 1,800 kN. At this point, 1,569 stakes had
        
        
          been planned for completion of the entire project. However, as a
        
        
          result of the tests, and subsequent project design optimization
        
        
          taking into account the increased loads, this number fell, in a
        
        
          second step, to 1,275 (an 18% decrease in the number of
        
        
          remaining piles). This decrease resulted in a direct cost
        
        
          reduction of 1.62 million reais, not taking into account the
        
        
          number of blocks needed, and also the indirect costs.
        
        
          Considering the costs involved in performing the load tests, the
        
        
          actual cost reduction amounted to 1.08 million reais.
        
        
          The final total of all piles placed, both before and after the
        
        
          revision, came to 3,838. A total of 38 (thirty-eight) static load
        
        
          tests were programmed throughout the project, 27 (twenty
        
        
          seven) for 500 mm piles, 9 (nine) for the 600 piles, and 2 (two)
        
        
          for 400 mm  piles. However, two of the load tests, specifically
        
        
          the 33rd and 34th, indicated problems in the pile caps, and had
        
        
          to be redone. Figure 2a shows the diagram regarding Load x
        
        
          Settling for the piles analyzed in the study. The Van der Veen
        
        
          equation was used as a criterion for extrapolating the rupture
        
        
          load for the load tests.
        
        
          Figure 1. Subsoil profile
        
        
          The final total of all piles placed, both before and after the
        
        
          revision, came to 3,838. A total of 38 static load tests were
        
        
          programmed throughout the project, 27 for 500 mm piles, 09 for
        
        
          the 600 piles, and 02 for 400 mm  piles. However, two of the
        
        
          load tests, specifically the 33rd and 34th, indicated problems in
        
        
          the pile caps, and had to be redone. Figure 2a shows the
        
        
          diagram regarding load versus settlement for the piles analyzed
        
        
          in the study. The Van der Veen equation was used as a criterion
        
        
          for extrapolating the geotechnical rupture load for the load tests.
        
        
          3 STATISTICAL ANALYSIS
        
        
          A mean value (µR) can be imagined in a representative area
        
        
          where the resistances are distributed, and a standard deviation
        
        
          (σR) can measure the distance this data is from this mean
        
        
          average. Analogically, in designing the details of a project with
        
        
          deep foundations, normally the piles are not designed with
        
        
          expectations to have to withstand maximum admissible loads.
        
        
          Generally, verifiable loads are less than, but close to admissible,
        
        
          presenting an average (µS), and standard deviation (σS)..Since
        
        
          not all locations in the subsoil present the same resistance, it is
        
        
          possible that in a certain location, the resistance is found to be
        
        
          less than that which is required to withstand the load indicated.
        
        
          The likelihood that this phenomenon occurs is called the
        
        
          probability of failure.
        
        
          Sample variation can be measured by the ratio between the
        
        
          standard deviation and the mean, this ratio is called the
        
        
          coefficient of variation. Reliability is a concept opposed to
        
        
          variability. The reliability index (β) is defined as the inverse of
        
        
          the coefficient of variation. The reliability index increases as the
        
        
          normal distribution is concentrated to a greater degree around
        
        
          the mean. The concept of a Safety Margin, which is defined as
        
        
          the difference between the requirements demanded, and the
        
        
          actual resistance, also is distributed normally, and through it can
        
        
          be obtained the parameters for analysis of potential for failure.
        
        
          For the case of the project under study, we studied the
        
        
          probability of failure values before and after revision of the
        
        
          foundation design project for the piles with 500 mm diameters,
        
        
          since the number of samples was greater. This review only
        
        
          changes the curve for requirements, considering that the mean
        
        
          load (μR) per pile was reviewed. For the first step, which
        
        
          preceded the review, mean and standard deviation values were
        
        
          verified for operating loads of 985 and 91.5 kN, respectively.
        
        
          For the second step, values of 1,086 and 106.0 kN, respectively,
        
        
          were determined. Regarding load resistance, values of 536 and
        
        
          3,167 kN were verified. A standard curve can only be set up
        
        
          using its mean value, and its standard deviation.
        
        
          From the data obtained, standard curves were plotted for
        
        
          both steps, similarly for the requirements, and the resistances.
        
        
          They are presented in Figure 2b. For the first step, the
        
        
          Reliability Index (β) measured 3.99, and the Probability of
        
        
          Failure (pf) was 1/30,893. For the second stage, β measured
        
        
          3.79, and the pf measured 1/13,373.
        
        
          (a)
        
        
          (a)
        
        
          (b)
        
        
          Figure 2. (a) Results of load tests for the 500mm piles; (b) Standard
        
        
          curves for the first and second phase compared to the normal curve of
        
        
          resistance.
        
        
          The load tests carried out for the project were not conducted
        
        
          all at once, thus, during the course of testing, the standard
        
        
          resistance curves could be adjusted to include the last test
        
        
          performed. As each new test is considered, a different pair of
        
        
          mean and standard deviation values is obtained. In such a
        
        
          manner, it is possible to trace standard curves that consider
        
        
          different steps for implementing quality controls for the
        
        
          foundation, or for different quantities of static load test
        
        
          performed, varying the size of the sample until the completion
        
        
          of predictive control for the work.
        
        
          As the sample increases, dispersion analysis is
        
        
          incorporated. This dispersion arises from the variability of the
        
        
          subsoil profile, the variability of the materials used, and from
        
        
          the uncertainties regarding  measurements of the loads and
        
        
          settlement.
        
        
          With introduction of a new section bearing a heavier load,
        
        
          600 mm piles were also adopted, with load tests indicating a
        
        
          permissible load of 1,800 kN. At this point, 1,569 stakes had
        
        
          been planned for completion of the entire project. However, as a
        
        
          result of the tests, and subsequent project design optimization
        
        
          taking into account the increased loads, this number fell, in a
        
        
          second step, to 1,275 (an 18% decrease in the number of
        
        
          remaining piles). This decrease resulted in a direct cost
        
        
          reduction of 1.62 million reais, not taking into account the
        
        
          number of blocks needed, and also the indirect costs.
        
        
          Considering the costs involved in performing the load tests, the
        
        
          actual cost reduction amounted to 1.08 million reais.
        
        
          The final total of all piles placed, both before and after the
        
        
          revision, came to 3,838. A total of 38 (thirty-eight) static load
        
        
          tests were programmed throughout the project, 27 (twenty
        
        
          seven) for 500 mm piles, 9 (nine) for the 600 piles, and 2 (two)
        
        
          for 400 mm  piles. However, two of the load tests, specifically
        
        
          the 33rd and 34th, indicated problems in the pile caps, and had
        
        
          to be redone. Figure 2a shows the diagram regarding Load x
        
        
          Settling for the piles analyzed in the study. The Van der Veen
        
        
          equation was used as a criterion for extrapolating the rupture
        
        
          load for the load tests.
        
        
          Figure 1. Subsoil profile
        
        
          The final total of all piles placed, both before and after the
        
        
          revision, came to 3,838. A total of 38 static load tests were
        
        
          programmed throughout the project, 27 for 500 mm piles, 09 for
        
        
          the 600 piles, and 02 for 400 mm  piles. However, two of the
        
        
          load tests, specifically the 33rd and 34th, indicated problems in
        
        
          the pile caps, and had to be redone. Figure 2a shows the
        
        
          diagram regarding load versus settlement for the piles analyzed
        
        
          in the study. The Van der Veen equation was used as a criterion
        
        
          for extrapolating the geotechnical rupture load for the load tests.
        
        
          3 STATISTICAL ANALYSIS
        
        
          A mean value (µR) can be imagined in a representative area
        
        
          where the resistances are distributed, and a standard deviation
        
        
          (σR) can measure the distance this data is from this mean
        
        
          average. Analogically, in designing the details of a project with
        
        
          deep foundations, normally the piles are not designed with
        
        
          expectations to have to withstand maximum admissible loads.
        
        
          Generally, verifiable loads are less than, but close to admissible,
        
        
          presenting an average (µS), and standard deviation (σS)..Since
        
        
          not all locations in the subsoil present the same resistance, it is
        
        
          possible that in a certain location, the resistance is found to be
        
        
          less than that which is required to withstand the load indicated.
        
        
          The likelihood that this phenomenon occurs is called the
        
        
          probability of failure.
        
        
          Sample variation can be measured by the ratio between the
        
        
          standard deviation and the mean, this ratio is called the
        
        
          coefficient of variation. Reliability is a concept opposed to
        
        
          variability. The reliability index (β) is defined as the inverse of
        
        
          the coefficient of variation. The reliability index increases as the
        
        
          normal distribution is concentrated to a greater degree around
        
        
          the mean. The concept of a Safety Margin, which is defined as
        
        
          the difference between the requirements demanded, and the
        
        
          actual resistance, also is distributed normally, and through it can
        
        
          be obtained the parameters for analysis of potential for failure.
        
        
          For the case of the project under study, we studied the
        
        
          probability of failure values before and after revision of the
        
        
          foundation design project for the piles with 500 mm diameters,
        
        
          since the number of samples was greater. This review only
        
        
          changes the curve for requirements, considering that the mean
        
        
          load (μR) per pile was reviewed. For the first step, which
        
        
          preceded the review, mean and standard deviation values were
        
        
          verified for operating loads of 985 and 91.5 kN, respectively.
        
        
          For the second step, values of 1,086 and 106.0 kN, respectively,
        
        
          were determined. Regarding load resistance, values of 536 and
        
        
          3,167 kN were verified. A standard curve can only be set up
        
        
          using its mean value, and its standard deviation.
        
        
          From the data obtained, standard curves were plotted for
        
        
          both steps, similarly for the requirements, and the resistances.
        
        
          They are presented in Figure 2b. For the first step, the
        
        
          Reliability Index (β) measured 3.99, and the Probability of
        
        
          Failure (pf) was 1/30,893. For the second stage, β measured
        
        
          3.79, and the pf measured 1/13,373.
        
        
          (a)
        
        
          (a)
        
        
          (b)
        
        
          Figure 2. (a) Results of load tests for the 500mm piles; (b) Standard
        
        
          curves for the first and second phase compared to the normal curve of
        
        
          resistance.
        
        
          The load tests carried out for the project were not conducted
        
        
          all at once, thus, during the course of testing, the standard
        
        
          resistance curves could be adjusted to include the last test
        
        
          performed. As each new test is considered, a different pair of
        
        
          mean and standard deviation values is obtained. In such a
        
        
          manner, it is possible to trace standard curves that consider
        
        
          different steps for implementing quality controls for the
        
        
          foundation, or for different quantities of static load test
        
        
          performed, varying the size of the sample until the completion
        
        
          of predictive control for the work.
        
        
          As the sample increases, dispersion analysis is
        
        
          incorporated. This dispersion arises from the variability of the
        
        
          subsoil profile, the variability of the materials used, and from
        
        
          the uncertainties regarding  measurements of the loads and
        
        
          settlement.