 
          1257
        
        
          Technical Committee 202 /
        
        
          
            Comité technique 202
          
        
        
          simplified design scenario shown in Figure 2 if ground
        
        
          treatment is not carried out. In the absence of ground treatment,
        
        
          equilibrium solutions could not be obtained and the likely
        
        
          failure mechanisms are shown in Figure 3. The predicted failure
        
        
          mechanism involves concentrated shear strains mobilised along
        
        
          the base of the marine clay layer due to the constant strength
        
        
          assumption. The overall stability is directly dictated by the
        
        
          elevation of the soft marine clay layer which controls the
        
        
          overburden pressure exerted on the potential failure soil mass.
        
        
          To enhance the overall stability, jet grouting works was
        
        
          proposed.  The potential working principle of the jet grout
        
        
          columns has been studied by finite element analyses. The
        
        
          technique of strength reduction has been used in the analysis to
        
        
          quantify the margin of safety and to identify the most critical
        
        
          failure mechanism of the design scheme. In the analyses,
        
        
          several rows of 2 m diameter discrete jet grout columns which
        
        
          pass through the marine clay and alluvium layers are assumed.
        
        
          The uniaxial compressive strength (UCS) and the Young’s
        
        
          modulus of the jet grouted material are assumed to be 2 MPa
        
        
          and 300 MPa respectively. Due adjustment of these parameters
        
        
          have been made in the plane strain models.
        
        
          Figure 4. Finite element prediction for bermed excavation with jet
        
        
          grouting - incremental shear strain distributions at failure.
        
        
          Figure 4 shows the incremental shear strain distributions at
        
        
          failure when soil strengths have been reduced by a factor of
        
        
          1.45 through strength reduction calculations. It can be seen that
        
        
          the most critical failure mechanism no longer involves a sliding
        
        
          plan along the base of the marine clay layer due to the presence
        
        
          of the jet grout columns. Instead, a local failure in the marine
        
        
          clay and alluvium is observed.
        
        
          In the analysis, the jet grout columns are modeled as a non-
        
        
          porous elastic perfectly plastic material, with the maximum
        
        
          shear strength governed by the Mohr-Coulomb failure criterion.
        
        
          Jet grouted material is brittle and therefore the mobilised shear
        
        
          strains in the jet grout columns have been calculated to ensure
        
        
          sufficient strength can be mobilised at small deformation. A
        
        
          limiting criterion of maximum shear strain of 0.5% has been
        
        
          adopted.
        
        
          The design scenario depicted in Figure 2 is a gross
        
        
          simplification of the actual site conditions. It conservatively
        
        
          considers the adverse effects of the presence of soft marine clay
        
        
          on the overall stability. The actual characteristics of the marine
        
        
          clay, including its strength, thickness and elevation, may vary
        
        
          across the site. The finite element analyses merely confirm the
        
        
          feasibility of the design scheme under an extreme condition.
        
        
          The actual amount of jet grout columns to be installed is
        
        
          determined by considering the local ground conditions,
        
        
          excavation profiles and the characteristics of the marine clay.
        
        
          The key design criteria are the overall safety margin of the
        
        
          excavation including the slope in front of the wall, the
        
        
          mobilised deformation in the jet grouted material as well as the
        
        
          structural forces induced in the diaphragm wall. Verification of
        
        
          the assumed material parameters for the jet grout columns is
        
        
          described in the next section.
        
        
          3 PERFORMANCE VERIFICATION
        
        
          Although jet grouting has been used widely in many parts of the
        
        
          world, it has not been common in Hong Kong. Therefore, not
        
        
          much field data was available. As such, a site trial was carried
        
        
          out before commencement of the actual jet grouting works. The
        
        
          purpose of the site trial is to determine the control parameters of
        
        
          the grouting operation, for example, the grout pressure, nozzle
        
        
          size and lifting rate, etc. In addition, the site trial serves to
        
        
          confirm that the assumed design strength and stiffness of the jet
        
        
          grouted materials can be obtained. A total of twelve trial jet
        
        
          grout columns were constructed using different combinations of
        
        
          operation parameters. A photo showing the jet grouting works is
        
        
          shown in Figure 5. The entire process is fully automated with
        
        
          all the operation parameters shown on a digital display panel.
        
        
          Figure 5. Plant used for jet grouting works with fully automated control
        
        
          system.
        
        
          A comprehensive post-grouting investigation was carried
        
        
          out. This included multiple full-depth coring in the trial jet grout
        
        
          columns, laboratory testing of the core samples and in-situ
        
        
          pressuremeter tests in the core holes. Core samples were
        
        
          obtained at differnet depths and at different locations in order to
        
        
          confirm that an effective diameter of 2 m could be acheived.
        
        
          The core samples were tested to obtain the Young’s modulus
        
        
          and the UCS of the specimens. In-situ pressuremeter tests were
        
        
          conducted in the core holes to measure the stiffness of the
        
        
          grouted zone. The final operation parameters of the jet grouting
        
        
          works were determined according to the results of site trial.
        
        
          For working jet grout columns, full-depth corings were
        
        
          obtained at a particular sampling frequncy as a quality control
        
        
          measure. Typical cores are shown in Figure 6.
        
        
          Figure 6. Typical core sample obtained from jet grout column