 
          1256
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          2 DESIGN OF THE DEEP EXCAVATION
        
        
          The 30 m deep excavation at WKT has a plan area of
        
        
          approximately 550 m by 220 m, and is surrounded by high-rise
        
        
          residental and commerical buildings in West Kowloon – an
        
        
          urban area of Hong Kong. Construction of large diameter bored
        
        
          piles and rock-socketted steel H-piles for supporitng the station
        
        
          structure and the perimeter diaphragm wall was carried out
        
        
          before excavation commenced. The diaphragm wall serves as
        
        
          the temporary retaining structure for the deep excavation, the
        
        
          permenent wall of the station structure, as well as a load bearing
        
        
          wall to support the vertical load from the superstructure. This
        
        
          Section describes the ground conditions of the site, the
        
        
          construction seqenence and the design considerations of the
        
        
          deep excavation.
        
        
          
            2.1 Ground conditions
          
        
        
          The solid geology within the site area comprises Kowloon
        
        
          Granite from the Cretaceous Period of the Mesozoic Era which
        
        
          is a monzogranite pluton centered on Kowloon and Hong Kong
        
        
          Island. The superficial deposits include fill and transported
        
        
          materials such as alluvium, colluvium, marine deposits,
        
        
          estuarine deposits and the like.
        
        
          Reclamation fill has been placed on the site following the
        
        
          West Kowloon reclamation works carried out in the 1990s. The
        
        
          fill comprises the reclamation deposits and the remnants of the
        
        
          old seawalls, old breakwaters, revetments, old ferry pier and
        
        
          existing layers of building debris and rock fill. The in-situ
        
        
          deposits include weathered rock and the soil derived from the
        
        
          weathered rock such as saprolite and residual soil (i.e. the Grade
        
        
          VI material according to GEO (1988)). Variably jointed rock
        
        
          and soil masses with different proportions of rock and soil are
        
        
          present within the in-situ deposits.
        
        
          The site topography prior to the bulk excavation is generally
        
        
          characterised as flat and the average ground level is at about
        
        
          +5.5 mPD. The available groundwater level records from
        
        
          standpipes and vibrating wire piezometer indicate that the
        
        
          highest recorded groundwater level ranged from +1.56 mPD to
        
        
          +3.60 mPD and the lowest groundwater level recorded ranged
        
        
          from -1.29 mPD to +1.94 mPD.
        
        
          
            2.2 Construction sequence
          
        
        
          Excavation and construction of the station structure is carried
        
        
          out by two separate contractors who adopt different construction
        
        
          methods. The contractor on the northern side adopts open cut
        
        
          excavation (see Figure 1) which is then followed by bottom-up
        
        
          construction.  On the southern side, the contractor adopts top-
        
        
          down construction for the top two levels of slabs and then
        
        
          changes to bottom-up construction for lower levels.
        
        
          The focus of this paper is the open cut excavation carried out
        
        
          near the northern part of the site. Upon completion of the
        
        
          foundation works and diaphragm wall construction, jet grouting
        
        
          was carried out at locations where soft marine clayey deposits
        
        
          are present which adversely affect the stability of the bermed
        
        
          excavation. After sufficient strength had been gained in the jet
        
        
          grouted material, temporary cut slopes at a gradient of 1 on 2
        
        
          were formed in front of the diaphragm wall.  This was followed
        
        
          by bottom-up construction of the central core of the station
        
        
          structure. Construction of the entire structure would then be
        
        
          completed by top-down method between the diaphragm wall
        
        
          and the core station structure where the temporary slopes are
        
        
          gradually removed and replaced by reinforced concrete slabs
        
        
          connecting the diaphragm wall to the core station structure.
        
        
          
            2.3 Design considerations
          
        
        
          Figure 2 shows a simplified design scenario which illustrates
        
        
          the design concept. The diaphragm wall and the soil berm are to
        
        
          support an excavation with a maximum depth of approximately
        
        
          30 m. Since the diaphragm wall is designed as a foundation
        
        
          element for vertical loading, the wall is founded on the bedrock
        
        
          with a nominal embedment of 300 mm. The sufficiency of the
        
        
          embedment depth of the wall has been checked by trial wedge
        
        
          methods. For areas with a shallow rockhead, mini piles, denoted
        
        
          as shear pins, were constructed beneath the base of the
        
        
          diaphragm wall to increase the resistance against overturning.
        
        
          Figure 2. Simplified design scenario of bermed excavation design with
        
        
          ground treatment by jet grouting.
        
        
          The trial wedge method considers the soil berm as a passive
        
        
          support as far as stability of the embedded wall is concerned.
        
        
          The stability of the soil berm has to be considered separately.
        
        
          The marine deposits sandwiched between the reclamation fill
        
        
          and alluvium consist of interbeded cohesive and granular
        
        
          materials. The cohesive portion typically comprises of clay and
        
        
          in places silt with various proportion of sands and gravels.  The
        
        
          undrained shear strength ranged from a few kilopascals to >200
        
        
          kPa.  A general design value of 30 kPa was adopted, except for
        
        
          marine clay at shallow depths where a lower value of 20 kPa
        
        
          was used.
        
        
          (a)
        
        
          (b)
        
        
          Figure 3. Predictions of failure mode from finite element analysis (a)
        
        
          total deformation, (b) incremental shear strain distributions
        
        
          Finite element analyses have been conducted using Plaxis to
        
        
          predict the behaviour of the bermed excavation for the