 
          983
        
        
          Technical Committee 104 /
        
        
          
            Comité technique 104
          
        
        
          4 CENTRIFUGE SETUP
        
        
          4.1
        
        
          
            Centrifuge Package and Instrumentation
          
        
        
          The centrifuge setup consisted of a strongbox, with a loading
        
        
          frame/system and PIV cameras/lights (see Figure 4).  The
        
        
          strongbox had a Perspex face against which the piles rested, a
        
        
          steel U-frame and an aluminium back, which provided very
        
        
          high stiffness boundaries around the soil.
        
        
          The PIV markers were calibrated against known target
        
        
          positions.  The pile displacements measured through PIV, were
        
        
          also monitored with linear variable differential transformers
        
        
          (LVDT’s).
        
        
          To verify the values provided by the head and base load
        
        
          cells, Novatech F259 Miniature Diaphragm 1 kN Loadcells
        
        
          were attached to the loading system so that the change in head
        
        
          load could be measured independently.
        
        
          Figure 3. Pile calibration – before affixing to the pile body and after
        
        
          affixing to the pile body.
        
        
          4.2
        
        
          
            Sand
          
        
        
          The piles were placed firmly against the Perspex face and the
        
        
          sand rained down over them.  Fraction E Leighton Buzzard
        
        
          Sand was used in the experiments at a relative density of 76%
        
        
          ±2%.
        
        
          4.3
        
        
          
            Experimental Procedure
          
        
        
          Piles A and B (see Figure 4) were used to provide data on the
        
        
          effects of tunnelling on bored piles, whereas Pile C was used to
        
        
          provide details of the pile capacity and load settlement response.
        
        
          The centrifuge was accelerated slowly to the desired 75g,
        
        
          with photographs being taken from each of the PIV cameras at
        
        
          various stages.  The pile loads were monitored during the
        
        
          acceleration phase after which loads were added to the pile
        
        
          heads using a specially designed loading system, which applies
        
        
          only the dead load of a pile cap for Piles A and B.
        
        
          Pile C had a different loading system which also did not
        
        
          apply any load until the desired 75g had been reached.  This pile
        
        
          also had a pile cap but with a loading pin capable of applying a
        
        
          head beyond that of the cap dead weight.
        
        
          All the piles were sleeved to the base (for details see
        
        
          Williamson 2013) so that only the base component was a factor
        
        
          in the pile loading.
        
        
          5 RESULTS
        
        
          5.1
        
        
          
            Load Cell Response
          
        
        
          The response of the load cells to the changing head load for Pile
        
        
          C is shown in Figure 5.
        
        
          Clearly the comparison between the commercially available
        
        
          Novatech head load cell and the response of the new strain
        
        
          gauged load cells is very good compared with the ideal 1 in 1
        
        
          slope.  No greater than 8% variation between the different types
        
        
          of load cell is found.
        
        
          The variation between the head and base load cell response
        
        
          is relatively constant at around 80 N between 420 N and 1000N.
        
        
          It was found that the pile toe began to move away from the face
        
        
          slightly at 1000 N and hence the divergence is likely to be
        
        
          attributed to some high level bending to the base load cell.
        
        
          Piles A and B operate at working loads of between 100 and
        
        
          120 N depending upon the experiment.  Within this range the
        
        
          variation between the change in head and base loads is small,
        
        
          but the incremental loading is shown to be linear.  This would
        
        
          perhaps indicate slightly higher amounts of bending on the head
        
        
          load cell.  The calibration factors for the head load cells though
        
        
          linear were slightly less consistent throughout the tests than the
        
        
          base load cells.  It is thought that their shorter length and the
        
        
          slight inconsistency in the contact point between the pile cap
        
        
          and the load cell could have affected the calibration factor,
        
        
          though it was shown to vary by no more than 10 % throughout
        
        
          the test series.
        
        
          Figure 4. Centrifuge setup – illustrating the piles, loading system and
        
        
          PIV setup.