 
          1745
        
        
          Technical Committee 204 /
        
        
          
            Comité technique 204
          
        
        
          Figure 6. Field trial for real-scale testing of the response of grouting
        
        
          underneath piled foundations.
        
        
          Due to the high void content of the soil a considerable grout
        
        
          take was observed during the pre-treatment phase. The targeted
        
        
          heave of 20 mm was achieved with grout efficiencies
        
        
          comparable to those with shallow foundations. The results can
        
        
          be seen in Fig. 7 for selected water levels.
        
        
          Figure 7. Vertical heave of selected pile heads monitored during the
        
        
          heaving phase.
        
        
          With the results obtained from the field trial the protection of
        
        
          4 buildings was designed. For the TAM arrays two deep shafts
        
        
          were realized in closest vicinity to service lines such as a high
        
        
          voltage power line and adjacent apartment buildings (see Figs. 8
        
        
          and 9). For the shaft construction Soilcrete-jet grouting was
        
        
          utilized for the lateral walls (two rows of columns) and the
        
        
          sealing slab as it proved to be a flexible and reliable solution.
        
        
          Buildings were monitored with real-time monitoring during jet
        
        
          grouting. The control of the jet grouting elements and the water
        
        
          tightness of the shaft was performed by means of pumping tests
        
        
          and thermal leakage and diameter controls.
        
        
          From the shafts (max. 24 m deep, inner diameter 5.0 m and
        
        
          6.0 m, respectively) two layers of TAMs at a maximum depth of
        
        
          approx. 20 m were installed without disturbance of the adjacent
        
        
          structures. Due to the variable pile length, TAMs were
        
        
          implemented at different depths in order to keep the distance
        
        
          between TAMs and piles constantly at 1.0 to 1.5 m.
        
        
          Figure 8. Schematic cross section of piled foundation at ‘Ionio Station’.
        
        
          Figure 9. Arial view of finished shaft with 6 m inner diameter and 24 m
        
        
          depth.
        
        
          The deformation of ’Building 146’ is represented in Fig. 10.
        
        
          Generally the passive effect of the pre-treatment phase reduced
        
        
          the deformation, with active grouting an additional reduction of
        
        
          absolute and differential settlement was obtained.
        
        
          Figure 10. Vertical response of buildings during TBM excavation.