 
          1744
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          2 COMPENSATION GROUTING FOR SHALLOW
        
        
          FOUNDATIONS
        
        
          Compensation grouting is frequently applied in urban tunnelling
        
        
          projects to reduce the impact of tunnelling to adjacent buildings
        
        
          providing the advantages of an active protection measure
        
        
          according to the observational method. For a detailed
        
        
          description of the compensation grouting method see Falk and
        
        
          Kummerer (2012). In the particular case of Metro B1,
        
        
          compensation grouting substituted the original design with full
        
        
          face (jet) grouting of the cross section for the following reasons:
        
        
          
        
        
          reduction of space requirements as all activities were
        
        
          located within small shafts and one site installation area
        
        
          
        
        
          no additional area needed to provide the space for drilling
        
        
          rigs (e.g. on roads closed for traffic)
        
        
          
        
        
          simple drilling geometry with two parallel grouting pipe
        
        
          (TAM) arrays avoiding complex 3D drilling set-ups
        
        
          
        
        
          reduction of spoil resulting from jet grouting
        
        
          
        
        
          real-time monitoring of critical buildings with the
        
        
          possibility of actively correct undue deformations.
        
        
          Before implementing compensation grouting for 8 critical
        
        
          buildings close to ‘Bologna station’, the actual state and
        
        
          tolerable deformations of these structures were assessed in
        
        
          comprehensive studies. The allowable maximum absolute and
        
        
          differential settlement was defined with 15 mm and 1/500,
        
        
          respectively. Deformation analyses based on the well-known
        
        
          soil behaviour showed that for the assumed volume loss of 0.6
        
        
          to 2.0% (with a tunnel diameter of 6.8 m) settlements would
        
        
          exceed the allowable value. To prove the efficiency of
        
        
          compensation grouting, a full-scale field trial under similar
        
        
          conditions was performed demonstrating that a controlled heave
        
        
          of an isolated footing of 4 cm was achieved after a cycle of
        
        
          repeated controlled grouting steps with special cement based
        
        
          grout mixes. For a detailed description of the design and the
        
        
          field trail see Sciotti et al. (2011).
        
        
          The grouting strategy identified by means of the field trial
        
        
          was applied to these building protected by 197 TAM pipes
        
        
          installed on a ground surface of approx. 3,000 m². All buildings
        
        
          were pre-heaved by max. 5 mm to prove the immediate reaction
        
        
          for concurrent grouting. To guarantee high accuracy drillings,
        
        
          all TAMs were installed with the Horizontal Directional
        
        
          Drilling-Technology. For ‘Building 1’ the grouting pipes had a
        
        
          radius of 120 to 140 m (see Fig. 3). Although the minimum
        
        
          distance of the TAMs was less than 1 m from the foundation, no
        
        
          significant settlement was measured during drilling.
        
        
          Figure 3. Cross section of compensation grouting for ‘Building 1’.
        
        
          In total, more than 100 monitoring points were installed for
        
        
          controlling the compensation grouting operation with a zero
        
        
          reading before any activity on site.
        
        
          As all grouting parameters (e.g. TAM spacing, grout mixes,
        
        
          injected volumes) were tested during the field trial, the grouting
        
        
          operation was very efficient during the excavation of both
        
        
          tunnels. The settlements were below the tolerable values. Fig. 4
        
        
          shows both tunnels from the final station shaft.
        
        
          Figure 4. Picture of finished upper tunnel and TBM in end position for
        
        
          lower tunnel.
        
        
          3 COMPENSATION GROUTING FOR PILED
        
        
          FOUNDATIONS
        
        
          Compared to the conditions of the above mentioned works with
        
        
          relatively shallow foundations, circumstances were different at
        
        
          ‘Ionio Station’ (Kummerer et al. 2012). The tunnel diameter
        
        
          was 9.8 m (double track tunnel). The grouted and excavated
        
        
          soils were gravels with a low content of fines. And more
        
        
          important, all buildings are founded on piles with a typical
        
        
          diameter of 600 mm and a pile length of max. 19 m. Therefore
        
        
          additional studies were necessary to address the very complex
        
        
          situation of compensation grouting for piled foundations.
        
        
          As a consequence and due to the fact that worldwide only
        
        
          limited experience was available for grouting underneath piled
        
        
          foundations, an additional real-scale field trial was performed.
        
        
          For the trial an already excavated station was chosen
        
        
          representing conditions similar to the actual compensation
        
        
          grouting works. A dead load of approx. 50 kPa above 9 piles
        
        
          with a length of 15 m and 20 m respectively represented the in-
        
        
          situ conditions (see Fig. 5).
        
        
          Figure 5. Photo of ‘Ionio Station’ full-scale field trial.
        
        
          Fig. 6 shows the schematic cross section of the field trial
        
        
          with ballast, piles and monitoring (liquid levels, pressure cells,
        
        
          precise levelling and incremental extensometers).