 
          1696
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          and to gain an understanding of the stress reduction mechanism.
        
        
          This paper presents the results of stress measurements inside the
        
        
          trench protected using at-grade geogrid bridging as well as the
        
        
          results of numerical model that helped clarify mechanisms of
        
        
          stress reduction. The material presented in this paper is
        
        
          considered to be of interest to researches and engineers.
        
        
          2 METHODOLOGY
        
        
          2.1
        
        
          
            Description of the field test
          
        
        
          An instrumented test embankment is constructed by Ontario
        
        
          Ministry of Transportation over a 3 m deep trench to study the
        
        
          effects of embankment construction on the underground
        
        
          utilities. The test embankment is constructed as part of Highway
        
        
          407 contract and is located near the Highway 407 and Weston
        
        
          Road in Vaughan, Ontario. The test embankment comprised
        
        
          several sections which facilitated the evaluation of four different
        
        
          configurations including the positive projection installation,
        
        
          induced trench installation and at-grade geogrid reinforcing
        
        
          bridging. Since the objective of the testing program was to
        
        
          evaluate the stresses reductions achieved by each of the
        
        
          considered installation techniques, no actual culverts were
        
        
          installed. Instead, the earth pressure cells were placed in
        
        
          granular protective surrounds located at two different depths in
        
        
          the trench. The first section is constructed as a conventional
        
        
          control section (Section 1), which included an instrumented
        
        
          trench that was conventionally backfilled with granular material
        
        
          up to the grade level (Positive Projection Method). The second
        
        
          section represents an Induced Trench Method installation (ITM)
        
        
          (Section 2), which included an instrumented trench that was
        
        
          backfilled with granular material that is overlain by a layer of
        
        
          compressible Styrofoam chips up to the grade level. The third
        
        
          and fourth sections include geogrid void bridges installed on the
        
        
          instrumented trenches with different trench widths. The
        
        
          evaluation of the induced trench method installation section was
        
        
          performed as part of a separate study and is beyond the scope of
        
        
          the present work. This study involve the results of the PPM
        
        
          represented in Section 1 (the control case) and the 3 m wide at-
        
        
          grade geogrid bridging, GB (Section 4). The following is a
        
        
          general description of field tests. The layout of test embankment
        
        
          is depicted in Figure 1. The considered test configuration
        
        
          comprises a 3 m deep trench backfilled up to the grade level
        
        
          which underlies an embankment with the footprint dimension of
        
        
          64m x 34m in length and width and with a height of 6 m. The
        
        
          slopes of the embankment were constructed with a 2H:1V
        
        
          inclination. Figure 2a and 2b show the details of instrumented
        
        
          trenches for Section 1 and 4, respectively.
        
        
          Figure 1. Plan and Profile of Test Embankment
        
        
          Figure 2. Details of the instrumented trenches
        
        
          2.2
        
        
          
            Construction and Instrumentation
          
        
        
          The site was leveled and topsoil was removed prior to the
        
        
          construction of the test embankment. A 1.5 m wide trench was
        
        
          excavated to a depth of 3m. 1m above the bottom of trench,
        
        
          trench slopes were cut to 1H:1V to maintain the integrity of
        
        
          trench side slopes during the construction (see Figure 2). Two
        
        
          drainage sumps are installed at each end to maintain a dry
        
        
          condition in the trench. The base of the trench is filled with a
        
        
          300mm thick compacted granular pad comprising Granular-A
        
        
          (OPSS 314). Then, the installation of earth pressure cells was
        
        
          initiated. Earth pressure cells with vibrating wire pressure
        
        
          transducers were used.  The earth pressure transducers were
        
        
          placed at the bottom (3m from the grade) and the mid-height
        
        
          (1.5 m from grade) of the trench with horizontal and vertical
        
        
          orientations in order to allow measurement of vertical and
        
        
          horizontal pressures, respectively. The pressure transducers
        
        
          were placed in a 0.5m x 1m x 1m granular protective surrounds.
        
        
          The granular surrounds were constructed as lightly compacted
        
        
          at mid-height pressure cell and well compacted at the bottom
        
        
          pressure cell to see the effect of the surround compaction on the
        
        
          measured stresses. The protective surrounds, which were
        
        
          constructed to eliminate a possible damage to pressure cells
        
        
          were constructed using steel separators in four sides. The steel
        
        
          separators separate the lightly compacted and well compacted
        
        
          granular surrounds from compacted Granular-A, which
        
        
          constitutes the rest of the fill material in the trench. The steel
        
        
          separators were removed as the level of granular surrounds
        
        
          reached 0.5 m height.  A total of 2 transducer couples (vertical
        
        
          and horizontal) were installed at the bottom and mid-height of
        
        
          each trench for each section and an additional transducer is
        
        
          installed at the interface between trench backfill and
        
        
          embankment. The trench backfill encapsulating granular
        
        
          surrounds, comprise Granular A compacted to 95% of Standard
        
        
          Proctor Dry Density. The pneumatic lines were extended
        
        
          through a PVC pipe, which followed the edges of trench and
        
        
          connected to a monitoring station.
        
        
          The embankment was constructed using native cohesive soils in
        
        
          the area. The soil was placed in the lift of 300mm and
        
        
          compacted to 95% of Standard Proctor Dry Density. The
        
        
          portion of the embankment fill immediately above the trench
        
        
          was placed by hand and compacted by self-propelled
        
        
          compaction equipment (Bomag BW65S) in order to protect
        
        
          against heavy machine loading used for compaction of
        
        
          embankment fill. The embankment fill, including the zone
        
        
          above the trench, is compacted using regular compaction
        
        
          equipment after fill height reached 1.3 m.