 
          1691
        
        
          Effect of pre-ground improvement method during shallow NATM tunnel excavations
        
        
          under unconsolidated conditions
        
        
          Effets de la méthode d’amélioration préalable des sols durant l’excavation de tunnel peu profond
        
        
          utilisant la nouvelle méthode autrichienne (NATM) dans un sol non-consolidé
        
        
          Cui Y.
        
        
          
            Meijo University, Japan
          
        
        
          Kishida K.
        
        
          
            Kyoto University, Japan
          
        
        
          ABSTRACT: During the construction of the Bullet Train lines in Japan, several shallow tunnels were excavated in unconsolidated
        
        
          ground using the New Austrian Tunnelling Method (NATM). However, ground and tunnel settlements frequently occurred due to the
        
        
          low stiffness of the ground and the shallow overburdens. In order to prevent such settlements and to ensure the stabilization of the
        
        
          cutting face of the tunnels, a pr-ground improvement method was adopted in the above fields. Various combinations of improved
        
        
          areas and levels of strength were tried in the fields, and the tunnels were excavated successfully. However, the mechanism of the
        
        
          effect of the pre-ground improvement method, the influence of the strengh of the improved ground, and the influence of the depth and
        
        
          the width of the improved areas are not clearly understood. Therefore, 2D elasto-plastic FE analyses are carried out here to clarify the
        
        
          effect of the pre-ground improvement method on the prevention of ground and tunnel settlements.
        
        
          RÉSUMÉ : Durant la construction des lignes du train rapide japonais, plusieurs tunnels peu profonds ont été excavés dans des sols
        
        
          non-consolidés en utilisant la nouvelle méthode autrichienne (NATM). Cependant, à cause de la faible cohésion du sol et du mort-
        
        
          terrain peu profond, des affaissements du sol et du tunnel arrivaient fréquemment. Dans le but de prévenir ces affaissements, et pour
        
        
          s’assurer de la stabilité des parois d
        
        
          u tunnel, une méthode supplémentaire d amélioration préalable du sol a été adoptée dans les
        
        
          terrains mentionnes ci-dessus. Divers combinaisons des surfaces améliorées et des niveaux de résistance ont été essayées sur place, et
        
        
          les tunnels ont été creusés a
        
        
          vec succès. Cependant, l’effet de la méthode d’amélioration préalable des sols et l’influence de la
        
        
          résistance des terrains améliorés, de leur profondeur et de leur largeur n’est pas clairement comprise. Dans cette étude, des analyses
        
        
          2D par éléments finis élasto-
        
        
          plastique sont effectuées afin de clarifier l’effet de la méthode d’amélioration préalable des sols sur la
        
        
          prévention des affaissements du sol et du tunnel.
        
        
          KEYWORDS: shallow tunnel, unconsolidated ground, NATM, pre-ground improvement method, surface settlement
        
        
          1 INTRODUCTION
        
        
          Up to now, the open-cut method has been the main tunneling
        
        
          method when excavating shallow tunnels in unconsolidated
        
        
          ground. And, the New Austrian Tunnelling Method (NATM)
        
        
          has been thought to be suitable when excavating tunnels in
        
        
          mountainous areas. Recently, however, not only because of
        
        
          advances in construction and measurement techniques, but also
        
        
          because it is more economical than either the shield tunneling
        
        
          method or the open-cut method, NATM has also become
        
        
          popular for shallow tunnel excavations. For example, during the
        
        
          construction of the Bullet Train lines in Japan, several shallow
        
        
          tunnels were excavated in unconsolidated ground using NATM
        
        
          (Kitagawa et al., 2005, 2009). However, ground and tunnel
        
        
          settlements frequently occurred due to the low stiffness of the
        
        
          unconsolidated ground and the significant reduction in the
        
        
          arching effect arising from the shallow overburdens. In order to
        
        
          prevent such settlements and to ensure the stabilization of the
        
        
          cutting face of the tunnels, a pre-ground improvement method
        
        
          was adopted in the above-mentioned fields.
        
        
          Figure 1 shows the construction process of the pre-ground
        
        
          improvement method. First of all, the ground is excavated to the
        
        
          upper part of the tunnel crown. Then, cement is mixed with the
        
        
          natural ground around the side wall of the tunnel using the
        
        
          shallow or deep mixing stabilization method. Thereafter,
        
        
          spreading and rolling compaction of the premixed soils are
        
        
          performed over the tunnel crown area. Finally, backfilling and
        
        
          rolling compaction of the excavated soils are performed to the
        
        
          ground surface. Thereafter, the tunnel is excavated using
        
        
          NATM. Various combinations of improved areas and levels of
        
        
          strength of the improved ground were tried in the fields, and the
        
        
          tunnels were excavated successfully. Morover, the effect of the
        
        
          pre-ground improvement method was confirmed in a previous
        
        
          analytical study (Cui et al., 2012). However, the mechanical
        
        
          behavior of the ground and the tunnel during the tunnel
        
        
          excavation process has not been discussed sufficiently. The
        
        
          strength of the improved ground, and the depth and the width of
        
        
          the improved areas, have been determined through practical
        
        
          construction works .
        
        
          In this study, therefore, 2D elasto-plastic finite element
        
        
          analyses, that simulate the tunnel excavation process, are carried
        
        
          out to clarify the effect of the pre-ground improvement method.
        
        
          Figure 1. Construction process of pre-ground improvement method