 
          1761
        
        
          Technical Committee 204 /
        
        
          
            Comité technique 204
          
        
        
          
            Proceedings of the 18
          
        
        
          
            th
          
        
        
          
            International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
          
        
        
          sch
        
        
          by 2 m work segments.
        
        
          ually.
        
        
          ments of existing footings, exceeding the 10 mm admissible
        
        
          value.
        
        
          It was decided not to take into account existing piles made in
        
        
          2005. This decision was based on two facts.
        
        
          Firstly, the static load tests on existing piles showed great
        
        
          scatter in results. In fact, bearing capacity was two times lower
        
        
          then its design. Secondly, the connection of reinforced concrete
        
        
          capping beam to existing foundation made of crushed stone was
        
        
          questionable. Assesment of existing foundation and its structural
        
        
          integrity confirmed that the major part of the building load still
        
        
          transfered through existing strip foundation despite the presence
        
        
          of underpining piles.
        
        
          With regard to aforementioned facts, a decision was made to
        
        
          cancel piling from the analyses to ensure a safety margin.
        
        
          There were considered various trench retaining options: root
        
        
          piles, pressed-in piles, subsoil stabilization that could be techni-
        
        
          cally possible in congested basement premises.  However, none
        
        
          of the existing methods could resolve the above issues and en-
        
        
          sure an adequate safety margin. Fast fabricated root piles usually
        
        
          have technological  settlements unacceptable for the building in
        
        
          question.  Pressed-in piles, having no such disadvantage, were
        
        
          used for the Bolshoi Theater refurbishment project, but they
        
        
          proved to be very labor intensive, and their installation
        
        
          required much more time than the time, remaining before
        
        
          the P.I. Tchaikovsky Competition. Subsoil stabilization is not a
        
        
          sufficiently safe solution, as in such soils it was difficult to en-
        
        
          sure adequate quality of respective construction  operations.
        
        
          In view of all above mentioned circumstances a decision
        
        
          was made to support 4.0...4.5 m ducts with root piles, reinforced
        
        
          with steel pipes.
        
        
          Realization of the project required a technique and a se-
        
        
          quence of the underground operations, which would minimize
        
        
          the construction the
        
        
          impact of construc-
        
        
          tion works on the
        
        
          building
        
        
          structure
        
        
          (Petruknin V.P. et al.
        
        
          2011). At the initial
        
        
          stage the soil was
        
        
          grouted with Micro-
        
        
          dur suspension, then
        
        
          the supporting root
        
        
          piles were erected
        
        
          (Figure 6), followed
        
        
          by stagewise soil
        
        
          excavation to design
        
        
          depths and raft con-
        
        
          creting, only then the
        
        
          duct walls and the
        
        
          floor were erected.
        
        
          Figure 6. Soil stabilization layout and retaining piling
        
        
          The reafter, in order to change the subsoil stress and strain
        
        
          behavior multiple compensation grouting was done behind the
        
        
          trench lining (Figure
        
        
          7). Geodetic monitor-
        
        
          ing of the footing
        
        
          settlements showed
        
        
          that the resulting
        
        
          upheaval of markers
        
        
          was up to 2…3 mm.
        
        
          Figure 7. Duct concret-
        
        
          ing layout with the com-
        
        
          pensation grouting
        
        
          eme
        
        
          As is known the root piles’ advantage is their low cost and
        
        
          fast erection, the only drawback is the respective technological
        
        
          settlements of footings, which can be as much as several centi-
        
        
          meters (Shulyatjev O.A. et al, 2008; Petrukhin V.P. et al, 2008).
        
        
          In order to exclude technological settlements due to root piling
        
        
          there were performed tests, and a drilling set-up was developed,
        
        
          protected by a RF patent (Petrukhin  V.P., Popsuenko I.K., Shu-
        
        
          lyatjev O.A., 2011), that compensated soil stress-strain behavior
        
        
          variation due to drilling by stagewise vertical pressurizing to-
        
        
          gether with  filling the  bore hole with cement-sand grout, whose
        
        
          composition excluded sedimentation. The operations were per-
        
        
          formed gradually
        
        
          According to the above mentioned patent the hole drilling
        
        
          was accompanied by compaction and hole walls troweling to
        
        
          prevent water-saturated liquefied soil falling in the borehole.
        
        
          Figure 8 shows a photograph of a duct segment under the Big
        
        
          Hall, dug out manually to the design depth.
        
        
          At  the fore-
        
        
          front root piles,
        
        
          made in 2005, are
        
        
          visible, they are
        
        
          joined together by
        
        
          a concrete raft, they
        
        
          are a sort of struts.
        
        
          Soil
        
        
          excavation
        
        
          from ducts is a
        
        
          rather
        
        
          labor-
        
        
          intensive process,
        
        
          therefore, as di-
        
        
          mensions of the
        
        
          premises
        
        
          were
        
        
          small, the soil was
        
        
          dug out man
        
        
          Figure 8. 4.5 m deep service duct
        
        
          In order to reduce footings settlements during ducts mining
        
        
          operations the soil under bearing walls was grouted with “Mi-
        
        
          crodur” suspension.
        
        
          Therefore, the subsequent soil excavation showed that soil
        
        
          stabilization had been done adequately, however, practically no
        
        
          traces of grouting were discovered at some points in spite  of the
        
        
          customer permanent strict control and designer  supervision.
        
        
          Thus, it indirectly proved that the safer selected option i.e., re-
        
        
          taining piles, was correct.
        
        
          Soil mining under bearing walls of the building was a com-
        
        
          plicated issue. As is mentioned above, it is wrong during soil
        
        
          mining to rely on earlier arranged root piling.   Therefore, a steel
        
        
          frame set-up was elaborated for 4,5 m deep ducts, which sup-
        
        
          ported a part of the wall, under  which the soil was dug out.
        
        
          Mining 1,8 deep ducts was even more difficult. Notably,
        
        
          shallow ducts mining was performed not only in soil,  it was
        
        
          often done along the  body of rabble stone footing (the footing
        
        
          width was up to 1,5 m), therefore, soil excavation looked as
        
        
          non-mechanized mining (all operations were manual).
        
        
          Underground development project involved various geo-
        
        
          technical operations that required on-line integrated geotechnical
        
        
          monitoring, performed by a specialized company in the most
        
        
          optimal way. Moreover, the designer company (Gersevanov
        
        
          NIIOSP) carried out their own supervision of the vertical and
        
        
          lateral displacements of the footings and of the Conservatory
        
        
          building  structure. The congested conditions of the refurbish-
        
        
          ment  operations, numerous labor force, multiple material stor-
        
        
          age sites, etc. restricted installation of an up-to-date on-line set-