 
          1331
        
        
          Technical Committee 202 /
        
        
          
            Comité technique 202
          
        
        
          Table 2. Design parameter of secant pile walls (plate model)
        
        
          Element
        
        
          
            Type
          
        
        
          
            EA
          
        
        
          
            (kN/m)
          
        
        
          
            EI
          
        
        
          
            (kN.m
          
        
        
          
            2
          
        
        
          
            /m)
          
        
        
          
            W
          
        
        
          
            (kN/m
          
        
        
          
            2
          
        
        
          
            )
          
        
        
          
            n
          
        
        
          Secant pile
        
        
          Elastic 1.2x10
        
        
          7
        
        
          3.6x10
        
        
          5
        
        
          14.4
        
        
          0.15
        
        
          Predicted magnitude of settlement was 0.39 m at the center
        
        
          of the road, 0.40 m at the middle and of the road towards to
        
        
          Tanjung Priok, and 0.38 m at the edge of the road towards
        
        
          Tanjung Priok. The time required to reach the amount of
        
        
          settlement is 6500 days.
        
        
          Summary of settlement and time rate of 3 observation points
        
        
          as mentioned above can be seen in Table 3.
        
        
          Table 3. Comparation of settlement value at Sta. 3+750.
        
        
          Settlement
        
        
          
            Existing
          
        
        
          
            Road
          
        
        
          
            Corrugated
          
        
        
          
            concrete
          
        
        
          
            Secant Piles
          
        
        
          At center line
        
        
          0.36 m
        
        
          0.29 m
        
        
          0.39 m
        
        
          At middle
        
        
          0.41 m
        
        
          0.33 m
        
        
          0.40 m
        
        
          At edge
        
        
          0.47 m
        
        
          0.36 m
        
        
          0.38 m
        
        
          Time (days)
        
        
          6800
        
        
          6900
        
        
          6500
        
        
          
            3.2 Zone 2: Sta 2+376 – Sta. 3+401
          
        
        
          In this Zone, there is a section of the road that had been
        
        
          strengthened by using sheet piles and stone works, while the
        
        
          other have not exist handling. Construction sheet pile
        
        
          implemented in 2011. This Zone is very vulnerable to both
        
        
          submerged from overflow of Japat River and from the
        
        
          surrounding environment (see Fig. 3), so raising works should
        
        
          be considered to be implemented.
        
        
          Analysis of proposed design in this zone is based on the road
        
        
          cross-section at approximately Sta. 3+275. Design parameters
        
        
          such as the friction angle, modulus of elasticity obtained by
        
        
          correlating the CPT #5 on shore and CPT #17 off shore  and
        
        
          evaluation of laboratory tests on undisturbed soil samples in
        
        
          BH6 at Sta. 3+150 and BH7 at Sta. 3+350.
        
        
          The results of stability analysis of the existing road condition
        
        
          indicating the road is relatively in critical condition due to FS =
        
        
          1.09. Predicted magnitude of settlement were 0.40 m at the
        
        
          center of the road, 0.51 m at the middle and of the road towards
        
        
          to Tanjung Priok, and 0.64 m at the edge of the road towards
        
        
          Tanjung Priok. The time required to reach the amount of
        
        
          settlement is 580 days.
        
        
          Therefore, some proposed trial designs were analyzed to
        
        
          fulfill minimum FS as follow:
        
        
          
            3.2.1 Corrugated prestressed concrete sheet piles
          
        
        
          The first trial design to strengthen the road is by using
        
        
          corrugated prestressed concrete sheet piles (see Table 1) to a
        
        
          depth of 14 m (to sandy silt clay soil, firm to very firm).
        
        
          To simulate the corresponding field condition i.e. water level
        
        
          fluctuation, two modeling analysis were conducted, which are to
        
        
          evaluate the influance of the highest water levels and the lowest
        
        
          water level measured on the tides. The results of stability
        
        
          analysis indicated FS = 1.15 at the highest water level, while FS
        
        
          at the lowest water level is 1.08 with large moments working on
        
        
          sheet piles 230 kN.m/m.
        
        
          
            3.2.2 Corrugated prestressed concrete sheet piles +
          
        
        
          
            horizontal bars
          
        
        
          Alternative proposed design is by using concrete sheet piles (see
        
        
          Table 1) and  horizontal steel bars reinforcement (see Table 4)
        
        
          placed across the road which binds sheet piles with continuous
        
        
          slab constructed on the left side of the road. Stability analysis
        
        
          indicates FS = 1.4.
        
        
          Table 4. Design parameter of horizontal steel bars
        
        
          Steel grade
        
        
          
            Nominal
          
        
        
          
            diameter
          
        
        
          
            (mm)
          
        
        
          
            Ultimate
          
        
        
          
            stress
          
        
        
          
            (MPa)
          
        
        
          
            Cross
          
        
        
          
            section
          
        
        
          
            area (mm)
          
        
        
          
            Ultimate
          
        
        
          
            strength
          
        
        
          
            (kN)
          
        
        
          150
        
        
          45
        
        
          1035
        
        
          1716
        
        
          1779
        
        
          Raising 0.7m should be performed at this Zone to prevent
        
        
          the road submerged from overflow of Japat River and from the
        
        
          surrounding environment. Stability analysis indicates FS after
        
        
          raising is 1.3 with tensile force on a horizontal rebar is 176.7
        
        
          kN/m.  Predicted magnitude of settlement were 0.40 m at the
        
        
          center of the road, 0.35 m at the middle and of the road towards
        
        
          to Tanjung Priok, and 0.25 m at the edge of the road towards
        
        
          Tanjung Priok. The time required to reach the amount of
        
        
          settlement is 677 days.
        
        
          
            3.2.3 Concrete sheet pile and ground anchor
          
        
        
          Strengthening of the road with a combination of concrete sheet
        
        
          piles (see Table 1) and ground anchor. The results of the
        
        
          analysis by considering the road reinforced with sheetpile (type
        
        
          5) combined with additional ground anchors with an inclination
        
        
          from the horizontal of 40
        
        
          o
        
        
          . Giving prestressed ground anchor on
        
        
          presstress modeled with extreme force drawn from the total
        
        
          normal stress / FK, i.e. 211kPa / 3 = 70.33 kN/m/m. Extreme
        
        
          total normal stress obtained based on the forces acting on the
        
        
          parts that have the greatest displacement. The results of the
        
        
          analysis showed that the stability of the road which is reinforced
        
        
          with sheetpile and supplementary reinforcement combined with
        
        
          ground anchors provide FS = 1.55.
        
        
          Predicted magnitude of settlement was 0.40 m at the center
        
        
          of the road, 0.35 m at the middle and of the road towards to
        
        
          Tanjung Priok, and 0.25 m at the edge of the road towards
        
        
          Tanjung Priok. The time required to reach the amount of
        
        
          settlement is 702 days.
        
        
          
            3.3 Zone 3: Sta. 3+400 – Sta. 3+860
          
        
        
          Analysis of proposed design in this zone is based on the road
        
        
          cross-section at approximately Sta. 3+750. There is a temporary
        
        
          construction using bamboo and stone masonry. This location is
        
        
          expected to potentially experience stability problems and
        
        
          settlement.
        
        
          Design parameters such as the friction angle, modulus of
        
        
          elasticity obtained by correlating the CPT #9 on shore and
        
        
          evaluation of laboratory tests on undisturbed soil samples in
        
        
          BH9 at Sta. 3+750.
        
        
          The results of stability analysis of the existing road condition
        
        
          indicating the road is relatively in critical condition due to FS =
        
        
          1.02. Predicted value of settlement during 4600 days was 0.60
        
        
          m at the centerline, 0.68 m in the middle of the road directions
        
        
          to Tanjung Priok, and 0.75 m at the edge of the road way to
        
        
          Tanjung Priok. The time required to reach settlement is 4600
        
        
          days.
        
        
          As mentioned above, the existing road condition at Sta.
        
        
          3+750 is in relatively unstable condition due to FS value = 1.02.
        
        
          Therefore, some proposed alternative designs were analyzed to
        
        
          fulfill minimum FS as follow:
        
        
          
            3.3.1 Concrete sheet piles and ground anchor
          
        
        
          Strengthening of the road with a combination of concrete sheet
        
        
          piles (see Table 1) and ground anchor. The results of the
        
        
          analysis by considering the road reinforced with sheetpile (type
        
        
          5) combined with additional ground anchors with an inclination
        
        
          from the horizontal of 40
        
        
          o
        
        
          . Giving prestressed ground anchor on
        
        
          presstress modeled with extreme force drawn from the total
        
        
          normal stress / FK, ie 91.15kPa / 3 = 30.38 kN/m/m. Extreme
        
        
          total normal stress obtained based on the forces acting on the
        
        
          parts that have the greatest displacement. The results of the
        
        
          analysis showed that the stability of the road which is reinforced