 
          1334
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          Photograph 1 (2) shows the newly developed post-tensioning
        
        
          rigid steel anchor used in CRE.  This anchor was improved
        
        
          from a slope reinforcement anchor. The  anchors is vertically
        
        
          penetrated from the top to the bottom layer and locked to the
        
        
          lower geosynthetics.
        
        
          Photographs 1. Geosynthetics and confining rigid steel anchors using
        
        
          Confined-Reinforced Earth.
        
        
          3 CONSTRUCTION METHOD
        
        
          Photographs 2 show the construction sequence of CRE. After
        
        
          preparing the lower subgrade, the 1
        
        
          st
        
        
          layer of geosynthetics is
        
        
          laid on the area to be reinforced (Photograph 2 (1)).
        
        
          Then crushed stones are carefully laid by a bulldozer or by a
        
        
          motor grader (Photograph 2 (2)) on the 1st layer of
        
        
          geosynthetics and the layer of crushed stone is fully compacted
        
        
          by vibrating rollers (Photograph 2 (2)).  After placing three
        
        
          layers of compacted crushed stone and laying of 2
        
        
          nd
        
        
          ,3
        
        
          rd
        
        
          and 4
        
        
          th
        
        
          layers of geosynthetics (Photograph 5 (3)), rigid steel anchors
        
        
          are vertically penetrated from the top to the bottom layer by the
        
        
          small pile driving equipment (Photograph 2 (4)) and
        
        
          mechanically locked to the lower geosynthetics employing a
        
        
          small hydraulic jack ( Photograph 2 (5)).
        
        
          It should be noted that the construction time of setting
        
        
          anchors is very short (about 40 to 50 anchors per hour).  Finally,
        
        
          a top steel plate is set through a rod and is fixed to the rod
        
        
          Photographs 2. Construction method of Confined-Reinforced Earth.
        
        
          (Construction in Joban Highway in Fukushima, Japan, 2011)
        
        
          with a nut using a torque wrench (Photograph 2 (6)).  Confining
        
        
          load of 30kN can be exactly maintained by setting torque. By
        
        
          use of this construction method, rapid construction of CRE
        
        
          becomes possible making it practical enough to apply this CRE
        
        
          for road in service. Photograph 3 shows the application of CRE
        
        
          for seismic retrofit of asphalt pavement on the actual highway
        
        
          embankment in Joban Highway, Fukushima, Japan, constructed
        
        
          in 2011.
        
        
          Photograph 3. Application of Confined-Reinforced Earth for actual
        
        
          highway embankment  in Joban Highway, Fukushima, Japan, 2011.
        
        
          4 FULL SCALE IN-SITU TEST
        
        
          
            4.1 Trial embankment
          
        
        
          A full-scale test of this high rigidity reinforced earth was carried
        
        
          out in the field in Ibaraki, Japan, from 9
        
        
          th
        
        
          to 16
        
        
          th
        
        
          March 2011 as
        
        
          shown in Photograph 4. The constructed trial embankment was
        
        
          of 25m length, 4m width and 2.5m height at the top of
        
        
          embankment. Full-scale asphalt pavements were placed on the
        
        
          trial embankment. The asphalt concrete pavement consisted of
        
        
          asphalt concrete of 50mm thickness and base course of 300mm
        
        
          thickness. Two types of asphalt pavement were constructed. The
        
        
          first type was conventional asphalt concrete pavement placed on
        
        
          the compacted soil subgrade, while the second was asphalt
        
        
          pavement placed on the high rigidity confined-reinforced earth
        
        
          consisting of the crushed stone sandwiched by four layers of
        
        
          geosynthetics and confined by confining rigid anchors.
        
        
          We aimed at direct comparison of performance of the two
        
        
          pavement types by artificially generating the differential
        
        
          settlement of trial embankment such as often seen during severe
        
        
          earthquakes. The forced differential settlement of the
        
        
          embankment was realized by using 10 multi-controlled large
        
        
          hydraulic jacks supporting the steel deck (10m long) placed
        
        
          under the embankment body. The layout of the trial
        
        
          embankment is shown in Figure 2.
        
        
          Photograph 4. Trial embankment after testing of 550mm differential
        
        
          settlement.  (Confined –Reinforced Earth tested  in Ibaraki, Japan,
        
        
          2011)