 
          1242
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          2 MULTI-STAGE EMBANKMENT STABILITY
        
        
          At Limerick Tunnel the designers adopted the undrained
        
        
          strength analysis approach as developed by Ladd (1991). This
        
        
          employs a normalised undrained strength ratio c
        
        
          u
        
        
          / p
        
        
          0
        
        
          ’ to predict
        
        
          the operational shear strengths that would apply at some future
        
        
          time after initial loading based on the estimated (or measured)
        
        
          partial consolidation and pore pressure conditions of the layer of
        
        
          soil in question. Stability at any stage of construction was
        
        
          evaluated by limit equilibrium methods using Bishops Modified
        
        
          Method for circular and Janbu’s Method for block shaped
        
        
          failure planes, the most critical of either being adopted in
        
        
          design. A minimum operating Factor of Safety of 1.25 was
        
        
          adopted for short term loading conditions assuming that the
        
        
          embankment was fully instrumented. In the long term fully
        
        
          drained condition a Factor of Safety of 1.3 was selected.
        
        
          A cautious design value of C
        
        
          vr
        
        
          = 1 m
        
        
          2
        
        
          /year was adopted
        
        
          for radial drainage and the contribution of vertical drainage was
        
        
          ignored. Vertical drains consisting of Mebradrain MD7007 were
        
        
          typically installed at 1.3 m c/c triangular spacing but in one
        
        
          200m long high fill area drains were installed at 1.0 m c/c
        
        
          spacings. If the total filling duration to achieve maximum height
        
        
          was deemed excessive, typically in excess of 6 to 9 months
        
        
          depending on the Contractor’s programme, then the use of basal
        
        
          geosynthetic reinforcement was considered to increase the
        
        
          temporary stability and thereby reduce the total time required
        
        
          for initial filling to full height. Basal reinforcement was
        
        
          required for approximately 1.7 km of the 6 km total
        
        
          embankment length requiring PVD and surcharge, typically
        
        
          where the total temporary embankment height (including
        
        
          surcharge fill) exceeded 6m.
        
        
          Multi-stage embankment construction designs were
        
        
          summarized in tabular format for each design profile and the
        
        
          earthwork drawings also reflected the reinforcement and stage
        
        
          hold durations. Earthworks construction was controlled in the
        
        
          field by careful review of instrumentation data by the designer’s
        
        
          site staff and the filling schedules and hold periods were altered
        
        
          to reflect the true soil behavior as monitored by field
        
        
          instrumentation.
        
        
          Jardine (2002) gives an excellent summary of the behaviour
        
        
          of multi-stage embankments constructed on soft foundation
        
        
          soils. Based on a number of fully instrumented and well
        
        
          documented case histories he notes the following key principles
        
        
          of their behaviour which can be of use in monitoring
        
        
          performance and assessing stability:
        
        
          
        
        
          Large ground movements due to volume changes can occur
        
        
          as instability is approached;
        
        
          
        
        
          Instability is primarily related to lateral spreading of the
        
        
          foundation and this can be monitored by assessing
        
        
          deformation ratios of lateral movement at the toe
        
        
          
        
        
          Y to
        
        
          maximum settlement at the crest
        
        
          
        
        
          S (see Figure 1). The
        
        
          limit criteria for such ratios will be different for single stage
        
        
          compared to multi-stage embankments and indeed will vary
        
        
          with each site due to soil material properties, embankment
        
        
          geometry, soil profile and loading rate;
        
        
          
        
        
          Similarly as instability is approached the ratio of pore
        
        
          pressure change in the foundation soils to increased total
        
        
          loading approaches and exceeds unity; and
        
        
          
        
        
          An observational approach is only valid if adequate
        
        
          instrumentation and a degree of redundancy due to loss is
        
        
          provided. The time necessary to acquire, process, evaluate
        
        
          and provide a control response must also be sufficiently
        
        
          short to avert a failure.
        
        
          Deformation ratio limits reported in CIRIA C185 (1999)
        
        
          typically range from 0.3 to 0.4 for embankments on soft ground.
        
        
          Data from Japan published by Wakita & Matsuo (1994) has
        
        
          suggested that the deformation ratio for a given degree of
        
        
          stability reduces as total settlement increases, failures being
        
        
          expected for deformation ratios in excess of 0.4 for observed
        
        
          settlements greater than 2m.
        
        
          Figure 1 Definition of Embankment Deformation Ratio
        
        
          (
        
        
          
        
        
          Y/
        
        
          
        
        
          S) (Jardine, 2002)
        
        
          Constitutive models used for soft alluvium included standard
        
        
          isotropic soft clay model in the PLAXIS  suite plus anisotropic
        
        
          models S-CLAY1 and ACM which was performed by
        
        
          University of Strathclyde. Further details of the anisotropic
        
        
          model parameters and results are given by Kamrat-
        
        
          Pietraszewska et al. (2008). The FEM results suggested that the
        
        
          maximum deformation ratio to be expected for the proposed
        
        
          stage loading schedules at adequate Factors of Safety might
        
        
          range up to 0.6. The following threshold limits for monitoring
        
        
          data were adopted as indicative of developing failure based on
        
        
          an average filling rate of 0.5 m/week with an absolute
        
        
          prohibition on any single incremental fill rate exceeding
        
        
          1m/week:
        
        
          
        
        
          Incremental pore pressure ratios
        
        
          
        
        
          u/
        
        
          
        
        
          v
        
        
          > 1.0 ;
        
        
          
        
        
          Global Deformation Ratios (
        
        
          
        
        
          Y/
        
        
          
        
        
          S) > 0.5;
        
        
          
        
        
          Deformation Ratios > 0.3 represented warning conditions
        
        
          where fill rates and performance data had to be more closely
        
        
          monitored; and
        
        
          
        
        
          Incremental change in settlement or toe movement > 0.1m
        
        
          between consecutive readings.
        
        
          3 INSTRUMENTATION MONITORING
        
        
          A total of 13 fully instrumented cross sections were selected at
        
        
          representative locations and near structures where temporary fill
        
        
          heights were greatest. A standard instrumentation cross section
        
        
          included a pair of settlement plates 5m inset from the
        
        
          embankment crest, survey monuments 1m offset from each toe,
        
        
          VW piezometers arranged at the centre point of the triangular
        
        
          PVD layout under the embankment centreline typically at 3m
        
        
          depth increments plus a single piezometer under both mid
        
        
          slopes at 2 metres depth. Inclinometers extended to stiff glacial
        
        
          till soils or bedrock were installed at the embankment toes.
        
        
          Settlement plates and toe survey monuments were generally
        
        
          arranged in pairs at 50 m c/c spacing along the mainline. Active
        
        
          areas of filling with settlement rates > 20 mm / week required
        
        
          twice weekly monitoring but daily monitoring was triggered
        
        
          when monitoring threshold limit values were exceeded.
        
        
          4 EMBANKMENT PERFORMANCE
        
        
          4.1
        
        
          
            Deformation Ratio & Stability
          
        
        
          A typical filling rate and deformation ratio history for the
        
        
          instrumented location at Ch 4+185 m is shown on Figure 2.
        
        
          During initial filling to heights of 4 m the deformation ratio
        
        
          rapidly rose to local maximum values of 0.4. The ratio then
        
        
          reduced to below 0.2 as settlement continues under constant
        
        
          load before increasing again during the next filling stage but