 
          932
        
        
          Proceedings of the 18
        
        
          th
        
        
          International Conference on Soil Mechanics and Geotechnical Engineering, Paris 2013
        
        
          Figure 2. Cross-section of South dike at start of test, showing settled
        
        
          geometry and indicating positions of reference monitoring.
        
        
          and subsequent erosion of the downstream slope. The earlier
        
        
          tests on piping had a similar configuration, but with a more
        
        
          sound clay dike (van Beek et al 2011). Those tests failed to
        
        
          piping at reservoir levels ranging from 1.75m to 2.3m. In order
        
        
          to make piping less likely this time, in each test dike a piping
        
        
          prevention measure has been placed. In the West dike, piping is
        
        
          controlled by a controllable drainage tube at 3.7m from the
        
        
          downstream toe, while in the East dike a coarse sand filter has
        
        
          been placed as a rectangular box 0.5m wide, 0.5m deep around
        
        
          3.5m from the downstream toe. The grain size of this filter
        
        
          varies from 1 to 2 mm, the grain size distribution is such that
        
        
          excessive loss of particles through this filter is prevented
        
        
          (Burenkova 1993).
        
        
          2.2
        
        
          
            South dike
          
        
        
          The South dike was built on a 4.5m thick composition of soft
        
        
          peat and clay. After construction, it was 4m high, 50m long at
        
        
          crest level, with a crest width of 3m and side slopes of 1:1.5
        
        
          (V:H). The core was made of sand, with a 0.5m thick clay layer.
        
        
          Figure 2 shows a cross-section of the dike at the start of the test,
        
        
          i.e. after consolidation resulting in a settlement of 0.99m.
        
        
          The designed failure modes of this dike were slope stability
        
        
          with a deep sliding plane through the subsoil with a minimum
        
        
          deformation of 20cm and rupture of the clay cover by high pore
        
        
          pressures inside the sand core as a result of saturating this core
        
        
          with water.
        
        
          3 INSTRUMENTATION
        
        
          For the instrumentation a clear distinction is made between the
        
        
          reference monitoring and the instruments of the participating
        
        
          companies. The reference monitoring was required (and
        
        
          sufficient) to closely monitor the course of the tests, while the
        
        
          other instruments were validated and the measurements were
        
        
          used to make updated predictions of the failures.
        
        
          A total of nine companies participated with their instruments
        
        
          – some in all tests, others in only one or two. Each of these
        
        
          companies were invited to use their own measurements to give
        
        
          an initial prediction of the failure mode and the conditions at
        
        
          which failure would occur, and to update this prediction at least
        
        
          every 24 hours.
        
        
          Three companies providing dike safety information systems
        
        
          participated in all three tests. These companies had access to the
        
        
          data of the monitoring systems being validated through a central
        
        
          data base. The data of the reference monitoring was not
        
        
          disclosed during the tests.
        
        
          3.1
        
        
          
            West dike
          
        
        
          The reference monitoring was primarily carried out with pore
        
        
          pressure meters: two to record the water levels in the upstream
        
        
          and downstream reservoirs, four lines of 17 meters each at the
        
        
          interface between the lower sand and the well-compacted clay
        
        
          layer at 0.9m, 2.5m, 4.3m and 11.2m from the downstream toe
        
        
          and a 3 by 3 grid of pore pressure meters at the bottom of the
        
        
          sand core: right behind the small clay dike and at 1.8m and
        
        
          6.0m downstream, respectively. In addition, visual inspections
        
        
          were carried out at regular intervals, an HD camera facing the
        
        
          downstream slope taking one frame every five seconds was
        
        
          used, rainfall data was recorded and the upstream and
        
        
          downstream discharges were measured.
        
        
          The following instrumentation was installed by the seven
        
        
          companies participating in this test:
        
        
          - glass fibre optics woven into geotextile, measuring
        
        
          temperature and strain approximately every metre in eight lines
        
        
          parallel to the toe of the dike, five at the sand/clay interface and
        
        
          three in the downstream slope;
        
        
          - a Fast Ground Based Synthetic Aperture Radar system,
        
        
          measuring a two-dimensional displacement field of the
        
        
          downstream slope every five seconds;
        
        
          - two vertical tubes, installed at the upstream crest line,
        
        
          measuring temperature and strain profiles over depth employing
        
        
          glass fibre optics;
        
        
          - a thermic infrared camera facing the downstream slope,
        
        
          with a resolution of 640x480 pixels and an accuracy of 0.05 K;
        
        
          - a ground penetrating radar system at 100 MHz, operated by
        
        
          moving it across the crest of the dike;
        
        
          - two controllable drainage tubes with measurements of pore
        
        
          pressure, temperature and discharge, located close to the
        
        
          sand/clay interface at 3.7m from the downstream toe (lower
        
        
          tube) and right behind the small clay dike at the bottom of the
        
        
          sand core (upper tube);
        
        
          - six pore pressure meters at the sand/clay interface, three at
        
        
          0.5m from the downstream toe and three at 2.2m.
        
        
          3.2
        
        
          
            East dike
          
        
        
          The reference monitoring at the East dike was almost identical
        
        
          to the West dike, but with four lines of 16 instead of 17 pore
        
        
          pressure meters at the sand/clay interface.
        
        
          The six companies participating in this test installed the
        
        
          following:
        
        
          - glass fibre optics woven into geotextile, measuring
        
        
          temperature and strain approximately every metre in eight lines
        
        
          parallel to the toe of the dike, five at the sand/clay interface and
        
        
          three in the downstream slope;
        
        
          - two vertical tubes, installed at the upstream crest line,
        
        
          measuring temperature and strain profiles over depth employing
        
        
          glass fibre optics;
        
        
          - an electric resistivity system employing two rows of 14
        
        
          electrodes on the downstream slope;
        
        
          - a thermic infrared camera facing the downstream slope,
        
        
          with a resolution of 640x480 pixels and an accuracy of 0.05 K;
        
        
          - a ground penetrating radar system at 100 MHz, operated by
        
        
          moving it across the crest of the dike;
        
        
          - ten pore pressure meters at the sand/clay interface, five at
        
        
          0.7m from the downstream toe and five at 2.2m.
        
        
          3.3
        
        
          
            South dike
          
        
        
          The reference monitoring at the South dike consisted of 34 pore
        
        
          pressure meters and six automatic inclinometers. Twentysix
        
        
          pore pressure meters were installed in two cross-sections each
        
        
          13m from the centre line, as indicated in Figure 2, six pore
        
        
          pressure meters were installed in six water tanks on top of the
        
        
          crest and the remaining two were installed in the basin on the
        
        
          non-failing side of the dike and in the ditch which was
        
        
          excavated during the test to reduce the overall stability. The
        
        
          inclinometers were distributed along the centre line and both
        
        
          instrumented cross-sections.
        
        
          The seven companies participating in this test installed the
        
        
          following:
        
        
          - glass fibre optics woven into geotextile, measuring
        
        
          temperature and strain approximately every metre in three
        
        
          parallel lines along the whole length of the dike, on ground level
        
        
          and on two higher levels;
        
        
          - a system of six extremely accurate inclination instruments,
        
        
          each mounted on top of a 5.6m steel rod placed on the slope of
        
        
          the dike (three on the side of the failure, three on the other side);