 
          933
        
        
          Technical Committee 104 /
        
        
          
            Comité technique 104
          
        
        
          - a Fast Ground Based Synthetic Aperture Radar system,
        
        
          measuring a two-dimensional displacement field of the slope at
        
        
          the side of the failure every five seconds;
        
        
          - a total of four tubes measuring temperature and strain
        
        
          profiles over depth employing glass fibre optics: two vertical
        
        
          tubes 5.5m long halfway the slope at the side of the failure, one
        
        
          vertical tube 3.5m long at the toe at the same side in the centre
        
        
          line and one horizontal tube along the whole toe of the dike;
        
        
          - a thermic infrared camera facing the downstream slope,
        
        
          with a resolution of 640x480 pixels and an accuracy of 0.05 K;
        
        
          - one controllable drainage tubes with measurements of pore
        
        
          pressure, temperature and discharge, located inside the sand
        
        
          core, close to the toe at the side of the failure;
        
        
          - eight instruments measuring pore pressure, temperature and
        
        
          local inclination distributed over two cross-sections 10m away
        
        
          from the centre line, in each cross-section one instrument in the
        
        
          sand core close to the toe and three instruments distributed over
        
        
          depth in the soft soil deposits under the toe.
        
        
          4 RESULTS OF THE EXPERIMENTS
        
        
          4.1
        
        
          
            West dike
          
        
        
          The test on the West dike started on August 21
        
        
          st
        
        
          at 4:30 pm.
        
        
          Filling the reservoir about 1m already caused serious cracks in
        
        
          the upper part of the dike. Also, leakage through the small clay
        
        
          dike occurred. Compaction of this clay was not sufficient. Once
        
        
          the situation stabilized, the upstream level was increased again.
        
        
          At a head drop of 1.56m the first wells appeared and sand
        
        
          producing wells (piping) appeared at a head drop of 1.79m.
        
        
          At 66.7 hours after the start of the test (t=66.7hrs), at a head
        
        
          drop of 2.02m, the lower drainage tube was partly opened as
        
        
          piping had already been detected at the third line of pore
        
        
          pressure meters, i.e. upstream of this tube. This had a clear
        
        
          effect on the pore pressures, as shown in Figure 3, and the
        
        
          piping process stopped.
        
        
          Meanwhile, the sand core became saturated, as measured by
        
        
          the upper pore pressure meters. At t=63.6 hrs, the upper
        
        
          drainage tube was opened and the pore pressures in the core
        
        
          were controlled. At t=94.0 hrs, both tubes were closed and the
        
        
          pore pressures rised sharply. From t=97.6 hrs, sliding of the
        
        
          downstream slope started to occur.
        
        
          At t=110.1 hrs, considerable sliding of the downstream slope
        
        
          had occurred. Piping had resumed too, but the continued sliding
        
        
          from micro-instability of the sand core caused so much
        
        
          settlement of the crest that at t=111.9 hrs (August 26
        
        
          th
        
        
          at 8:24
        
        
          am) failure occurred.
        
        
          4.2
        
        
          
            East dike
          
        
        
          The test on the East dike started on August 21
        
        
          st
        
        
          at 3:20 pm and
        
        
          ran parallel to the test on the West dike. In many ways, both
        
        
          tests were similar, although the controllable drainage tubes were
        
        
          missing at the East dike. Wells occurred at the downstream
        
        
          slope at a head drop of 1.60m and piping started at a head drop
        
        
          of 2.02m. However, piping was detected only in the two lines of
        
        
          pore pressure meters downstream of the coarse sand filter,
        
        
          upstream no piping could be traced. Apparently, this measure
        
        
          worked.
        
        
          As the last stages of the hydraulic load were delayed in
        
        
          comparison with the West dike, severe settlements from micro-
        
        
          instability of the sand core occurred later. Here at t=138.9 hrs
        
        
          (August 27
        
        
          th
        
        
          at 10:18 am) failure from micro-instability
        
        
          occurred. Figure 5 shows an overview of both failures.
        
        
          4.3
        
        
          
            South dike
          
        
        
          The test on the South dike started on September 3
        
        
          rd
        
        
          at 12:12 pm,
        
        
          Figure 3. Pore pressures at sand/clay interface West
        
        
          Figure 4. West dike close before failure.
        
        
          Figure 5. West and East dikes after failure.
        
        
          by infiltration of water into the sand core. The next day, a small
        
        
          excavation was made in front of the dike. This had a limited
        
        
          effect on the dike, as shown in Figure 6 by the horizontal
        
        
          displacements at the toe of the dike. The next day, a final
        
        
          excavation was made and on the basis of slope stability
        
        
          calculations it was decided to continue by hydraulic loading
        
        
          only. In order to acquire a lot of measurement data, several days
        
        
          were taken to raise the phreatic surface in the sand core and to
        
        
          fill the water tanks on top. Finally, failure occurred on
        
        
          September 8
        
        
          th
        
        
          , at 2:27 pm, after 122.26 hours, see Figure 7.
        
        
          Table 1 shows the results of slope stability calculations at
        
        
          characteristic moments applying the models of Bishop (1955)
        
        
          and Van (2001). The latter is a geometrically more flexible
        
        
          variant to Bishop’s model. The results correspond well to the
        
        
          deformation behaviour shown in Figure 6: close to the critical
        
        
          value of 1, the deformations quickly increase. These results may
        
        
          even draw some suspicion, but it should be borne in mind that
        
        
          quite advanced soil investigations had been carried out prior to
        
        
          the test (Zwanenburg et al. 2011, Koelewijn and Bennett 2012)
        
        
          and detailed actual measurements of pore pressures were
        
        
          available. Moreover, the model by Bishop has already long ago
        
        
          been described as surprisingly accurate for conditions close to
        
        
          failure (Spencer 1967).
        
        
          Table 2 gives the measured values of the horizontal
        
        
          deformations during the last phase of the test for all