 
          1371
        
        
          Technical Committee 202 /
        
        
          
            Comité technique 202
          
        
        
          Table 2. Results of calculations
        
        
          Bending moment embedded
        
        
          63 kNm
        
        
          Bending moment retaining
        
        
          65 kNm
        
        
          Horizontal displacement
        
        
          21 mm
        
        
          Vertical displacement top of wall
        
        
          4 mm
        
        
          Max vertical displacement behind wall
        
        
          9 mm
        
        
          Load in nails row 1
        
        
          140 kN
        
        
          Load in nails row 2
        
        
          190 kN
        
        
          Load in nails row 3
        
        
          217 kN
        
        
          Load in nails row 4
        
        
          140 kN
        
        
          After excavation of a retaining height of 3 m, a guide wall
        
        
          for the jet grout columns was casted against the berliner’s
        
        
          soldier piles (HEB 300 beams). This guide wall also serves as
        
        
          temporary waler, since execution of jet grout columns decreases
        
        
          significantly the passive soil resistance in front of the soldier
        
        
          piles. To counter this effect, the installation of the jet grout
        
        
          columns was also carried out in a specified alternating
        
        
          sequence. guide wall also serves as temporary waler,
        
        
          Figure 4 shows the finite difference model geometry with
        
        
          bending moments in the wall and axial loads in the nails.
        
        
          Figure 4. The distribution of the nail forces along the nails and bending
        
        
          moments within the jet grout wall.
        
        
          The VHP jet grout columns only serve as a mean to install
        
        
          the beam reinforcement at depth and to transfer earth and water
        
        
          pressure to the reinforcement beams. For safety reasons, the 21
        
        
          m long reinforcement beams (HEB 280) had to be installed in 3
        
        
          m long sections which were bolted together. This installation is
        
        
          tedious and time consuming, and has to take place before the
        
        
          grout starts to harden. Due to the column length, installing the
        
        
          beams can only start about 2 h after commencing the
        
        
          (water)pre-cutting and 1 h after the (watercement) grouting.
        
        
          Including the bolting of the different beam sections, which takes
        
        
          up about 45 min in total, the last section reaches the bottom of
        
        
          the column 2 h after the start of the jet grouting at that depth.
        
        
          Furthermore, the VHP-piles are installed in alluvial soil.
        
        
          Although the strength of the grout was not an issue (since it is
        
        
          of minor importance in the design), it is challenging to realise a
        
        
          reasonable sized jet grout column in this alluvium, especially
        
        
          when peat is encountered. Test columns were installed prior to
        
        
          the wall installation, in which diameter measurements were
        
        
          carried out with a calliper in the wet column. During these tests,
        
        
          chunks of more than 10 cm diameter of compacted peat were
        
        
          found in the spoil (Figure 5). To aid in the realisation of the
        
        
          required diameter to install the beam reinforcement, a reamer of
        
        
          30 cm diameter was placed above the jet nozzles. Even with this
        
        
          reamer, the minimum diameter realized was equal to that of the
        
        
          reamer (Figure 6).
        
        
          Figure 5. Pieces of peat found in jet grout spoil.
        
        
          Figure 6. Cone resistance from CPT-E and measured diameter in wet jet
        
        
          grout column.
        
        
          After testing different jetting pressures, flow rates and nozzle
        
        
          diameters, a suitable set of parameters was chosen. Even with
        
        
          this most suitable set, it was difficult to install the last few
        
        
          meters of the reinforcement, due to decantation of soil inclusion
        
        
          (clay/peat) in the grout. To ease the installation, the jet grout
        
        
          columns were deepened 1 m to allow for a 1 m unreinforced
        
        
          length. The retaining wall was executed as primary (reinforced)
        
        
          and secondary (unreinforced) columns with hart-to-hart distance
        
        
          of 1 m between reinforcements. The secondary columns serve to
        
        
          fill up the gap between primary columns.
        
        
          Due to the nature of the fill and natural soil, a larger
        
        
          diameter than conventional soil nail diameters was necessary to
        
        
          provide sufficient bearing capacity of the nails. The soil nails
        
        
          were also executed as jet grout nails with a diameter of 30 cm.
        
        
          Pull-out tests were performed on sacrificial nails to check the
        
        
          design assumptions.
        
        
          Figure 7 gives a view on the retaining wall after excavation
        
        
          and creation of a working platform for the new pile foundation.