Actes du colloque - Volume 3 - page 193

1995
A Case Study of 3D FE Analysis of a Deep Excavation Adjacent to a Tunnel
Construction
Une étude de cas d'une simulation tridimensionnelle d'analyse par éléments finis d'une excavation
profonde adjacente à une construction d'un tunnel
Guler E.
Bosphorus University, Istanbul, Turkey
Osmanoglu U., Koç M.
ELC Group Inc. (Royal HaskoningDHV Turkey), Istanbul, Turkey
ABSTRACT: This paper describes the 3D geotechnical FE analysis and design of a deep excavation bracing system. The location is
situated in a very dense business area in Istanbul. The maximum height of the excavation is ~23 m to accommodate 7 basement floors.
The layout has a non-uniform shape, surrounded with existing high rise structures with multi-basement floors, and an underpass
connection to E-5 Motorway. In addition to these, the most outstanding characteristic of this design is the pedestrian tunnel and the
shaft that is very close to the excavation pit. Both of these underground structures were being constructed throughout the same
construction period as the deep excavation. At the non-anchoring zones adjacent to the tunnel and shaft, steel struts have been used.
As a compound engineering service, soil investigation – design – site supervision – geotechnical instrumentation works was carried
out. Therefore a comprehensive data for comparison between design results and in-situ performance could be gathered. This paper
focuses on the details of the sophisticated 3D FE analysis and the comparison with the in-situ performance of the shoring system.
RÉSUMÉ : Ce document décrit l'analyse géotechnique 3D par éléments finis et la conception d'un système de contreventement
utilisé
dans l'excavation profonde. L'emplacement est situé dans un quartier très dense à Istanbul. La hauteur maximale de l'excavation est de
23 m pour 7 sous-sols. Le site a une forme non uniforme, entouré de structures existantes de grande hauteur avec multi-sous-sols, une
connexion souterraine de l'autoroute E-5. En plus de cela, la caractéristique la plus remarquable de cette conception est le tunnel pour
piétons et l'arbre qui est très proche de l'excavation. Ces deux structures souterraines ont été construites pendant la même période que
la construction de l'excavation profonde. Au niveau des zones de non-ancrage adjacentes au tunnel et à l'arbre, des entretoises en acier
sont utilisées. En tant que service d'ingénierie
l'étude du sol
, - la conception - la supervision de chantier - les travaux en
instrumentation géotechnique ont été réalisées. Par conséquent un ensemble de données complètes pour la comparaison entre les
résultats de la conception et de la performance in-situ aurait pu être recueillie. Ce document se concentre sur les détails d'une
simulation 3D sophistiquée d'Analyse par éléments finis et la comparaison des performances in-situ du système d'étaiement.
KEYWORDS: 3D FE Analysis, Deep Excavation, Case Study, Excavation-Tunnel-Shaft interaction.
1 INTRODUCTION
The deep excavation retaining system project is located at the
European side of Istanbul. The plan view of the site is presented
in Figure 1. The depth of the excavation is 23 m. The ongoing
construction of a pedestrian tunnel and entrance shaft adjacent
to this excavation makes the design of the retaining system
complicated. Interaction with this deep excavation work was not
considered in the design of the tunnel and shaft. Hence, the
shoring design for the deep excavation had to consider the very
close tunnel and shaft which were still being constructed and
standing with their temporary support systems during the
excavation works. Since the interaction between the deep
excavation and the simultaneously constructed shaft and tunnel
cannot be modeled with only a 2D analysis (plain-strain model),
a 3D Geotechnical FE analysis (especially for the shaft location)
had to be conducted.
The pedestrian tunnel has a span of 7 m at a distance of 7 m
to the piles of the shoring system. The shaft has a diameter of 6
m at 2.5 m distance to the piles of the shoring system. The
tunnel and shaft’s temporary support system was composing of
~20 cm shotcrete facing and rock bolts. In the tunnel 4 m long
rock bolts were used only at the top heading. In the shaft 2 m
long radial rock bolts were used. The temporary excavation
system of the building is designed with micro piles, pre-stressed
anchors and steel struts at non-anchoring zones due to tunnel
and shaft. The elevation corresponds roughly to the foundation
level of the excavation pit.
The software used in this project were TNO DIANA for 3D
modeling and Plaxis V.11 for 2D modeling (for the analysis at
the tunnel side).
A
B
C
D
G
H
I
J
K
L
N
359
358
357
356
355
354
353
352
351
350
349
348
347
346
345
344
343
342
341
340
339
338
337
336
335
334
333
332
331
330
327
326
325
324
323
322
321
320
319
318
317
316
315
314
313
312
311
310
309
308
307
306
305
304
303
302
301
300
299
298
297
296
295
294
293
292
291
290
289
288
287
286
285
284
283
282
281
280
279
278
277
276
275
274
273
272
271
270
269
268
267
266
265
264
263
262
261
260
259
258
257
256
255
254
253
252
251
250
249
248
247
246
245
244
243
242
241
240
239
238
237
236
235
234
233
232
231
230
229
228
227
226
225
224
223
222
221
220
219
218
217
216
215
214
213
212
211
210
209
208
207
206
205
204
203
202
201
200
199
198
197
196
195
194
193
192
191
190
189
188
187
186
185
184
183
182
181
180
179
178
177
176
175
174
173
172
171
170
169
168
167
166
165
164
163
162
161
160
159
158
157
156
155
154
153
152
151
150
149
148
147
146
145
144
143
142
141
140
139
138
137
136
135
134
133
132
131
130
129
128
127
126
125
124
123
122
121
120
119
118
117
116
115
114
113
112
111
110
109
108
107
106
105
104
103
102
101
100
099
098
097
096
SHAFT
Highrise&
D'
Basements
Underpass
Highway
ExistingBuildigs
Existing
095
094
093
092
091
090
089
088
087
086
085
084
083
082
081
080
079
078
077
073
076
075
074
072
071
070
069
068
067
066
065
064
063
062
061
060
059
058
057
056
055
054
053
052
051
050
049
048
047
046
045
044
043
042
041
040
039
038
037
036
035
034
033
032
031
030
029
028
027
026
025
024
023
022
021
020
019
018
017
016
015
014
013
012
011
010
009
008
007
006
005
004
003
002
001
329
328
E
F
Deep Excavation
+131 to +108
M
B'
Figure 1. Site layout with surrounding structures
2 DESIGN PHASE
The design works were carried out based on the geological &
geotechnical data obtained from the site investigations.
Surcharge loads were considered wherever necessary.
1...,183,184,185,186,187,188,189,190,191,192 194,195,196,197,198,199,200,201,202,203,...840